Fundamentals of Financial Management (MindTap Course List)
15th Edition
ISBN: 9781337671002
Author: Brigham
Publisher: Cengage
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 11, Problem 11P
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $17,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Explain.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $5,000 per year for 5
years. Mutually exclusive Project L requires an initial outlay at t = 0 of $30,500, and its expected cash flows would be
$9,450 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?
Select the correct answer.
O a. Project S, because the NPVS > NPVL.
O b. Both Projects S and L, because both projects have NPV's > 0.
c. Both Projects S and L, because both projects have IRR's > 0.
O d. Project L, because the NPVL > NPVS.
O e. Neither Project S nor L, because each project's NPV < 0.
Give typing answer with explanation and conclusion
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,000, and its expected cash flows would be $13,850 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend?
Select the correct answer.
a. Neither Project S nor L, because each project's NPV < 0.
b. Both Projects S and L, because both projects have NPV's > 0.
c. Project S, because the NPVS > NPVL.
d. Both Projects S and L, because both projects have IRR's > 0.
e. Project L, because the NPVL > NPVS.
Project S requires an initial outlay at t= 0 of $16,000, and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t= 0 of $27,500, and its expected cash flows would be $10,150 per year for 5 years. If
both projects have a WACC of 14%, which project would you recommend?
Select the correct answer.
Ca. Project S, because the NPVs > NPVL.
Ob. Both Projects S and L, because both projects have IRR's > 0.
Oc. Both Projects S and L, because both projects have NPV's > 0.
Od. Project I because the NPVL > NPVs.
Oe. Neither Project S nor L, because each project's NPV < 0.
Chapter 11 Solutions
Fundamentals of Financial Management (MindTap Course List)
Ch. 11 - How are project classifications used in the...Ch. 11 - Prob. 2QCh. 11 - Why is the NFV of a relatively long-term project...Ch. 11 - Prob. 4QCh. 11 - If two mutually exclusive projects were being...Ch. 11 - Discuss the following statement: If a firm has...Ch. 11 - Why might it be rational for a small firm that...Ch. 11 - Project X is very risky and has an NPV of 3...Ch. 11 - Prob. 9QCh. 11 - A firm has a 100 million capital budget. It is...
Ch. 11 - NPV Project L costs 65,000, its expected cash...Ch. 11 - IRR Refer to problem 11-1. What is the projects...Ch. 11 - MIRR Refer to problem 11-1. What is the projects...Ch. 11 - Prob. 4PCh. 11 - DISCOUNTED PAYBACK Refer to problem 11-1. What is...Ch. 11 - NPV Your division is considering two projects with...Ch. 11 - CAPITAL BUDGETING CRITERIA A firm with a 14% WACC...Ch. 11 - Prob. 8PCh. 11 - CAPITAL BUDGETING CRITERIA: ETHICAL CONSIDERATIONS...Ch. 11 - CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE...Ch. 11 - CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE...Ch. 11 - Prob. 12PCh. 11 - MIRR A firm is considering two mutually exclusive...Ch. 11 - CHOOSING MANDATORY PROJECTS ON THE BASIS OF LEAST...Ch. 11 - NPV PROFILES: TIMING DIFFERENCES An oil-drilling...Ch. 11 - Prob. 16PCh. 11 - CAPITAL BUDGETING CRITERIA A company has an 11%...Ch. 11 - NPV AND IRR A store has 5 years remaining on its...Ch. 11 - Prob. 19PCh. 11 - NPV A project has annual cash flows of 5,000 for...Ch. 11 - Prob. 21PCh. 11 - MIRR A project has the following cash flows: This...Ch. 11 - CAPITAL BUDGETING CRITERIA Your division is...Ch. 11 - BASICS OF CAPITAL BUDGETING You recently went to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects’ NPVs, IRRs, MIRRs, and PIs, assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?arrow_forwardJasmine Manufacturing is considering a project that will require an initial investment of $52,000 and is expected to generate future cash flows of $10,000 for years 1 through 3, $8,000 for years 4 and 5, and $2,000 for years 6 through 10. What is the payback period for this project?arrow_forward9. Project S requires an initial outlay at t = 0 of $19,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,000, and its expected cash flows would be $12,150 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, because the NPVS > NPVL. b. Neither Project S nor L, because each project's NPV < 0. c. Both Projects S and L, because both projects have IRR's > 0. d. Both Projects S and L, because both projects have NPV's > 0. e. Project L, because the NPVL > NPVS. 10arrow_forward
- Project S requires an initial outlay at t=0 of $12,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $38,500, and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. Oa. Both Projects S and L, because both projects have NPV's > 0. Ob. Project S, because the NPVs > NPVL Oc. Both Projects S and L, because both projects have IRR's > 0. Od. Neither Project S nor L, because each project's NPV NPVs.arrow_forwardProject Q requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,000, and its expected cash flows would be $13,600 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Project S, since the NPVS > NPVL. c. Project L, since the NPVL > NPVS. d. Both Projects S and L, since both projects have IRR's > 0. e. Both Projects S and L, since both projects have NPV's > 0.arrow_forwardPlease calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000 $1,250,000 7 $2,000,000 $1,250,000 8 0 $1,600,000 Part 2 Please study the following capital budgeting project and then provide explanations for the questions outlined below: You have been hired as a consultant for Pristine Urban-Tech Zither, Inc. (PUTZ), manufacturers of fine zithers. The market for zithers is growing quickly. The company bought some land three years ago for $2.1 million in anticipation of using it as a toxic waste dump site but has recently hired…arrow_forward
- Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,500, and its expected cash flows would be $7,600 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, because each project's NPV < 0. b. Both Projects S and L, because both projects have NPV's > 0. c. Project S, because the NPVS > NPVL. d. Both Projects S and L, because both projects have IRR's > 0. e. Project L, because the NPVL > NPVS.arrow_forwardProject S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects’ NPVs, IRRs, assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?arrow_forward(Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Cash Flow Project B Cash Flow 0 $(100,000) $(100,000) 1 33,000 0 2 33,000 0 3 33,000 0 4 33,000 0 5 33,000 220,000 If the appropriate discount rate on these projects is 10 percent, which would be chosen and why? The NPV of Project A is $ (Round to the nearest cent.) The NPV of Project B is $ (Round to the nearest cent.) Which project would be chosen and why? (Select the best choice below.) A. Choose Upper B because its NPV is higher. B. Cannot choose without comparing their IRRs. C. Choose Upper A because its NPV is higher. D. Choose both because they both have positive NPVs.arrow_forward
- Project GS costs $15,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually Exclusive project LL costs $37,500, and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend?arrow_forwardA project has an initial cost of $40,000, expected net cash inflows of $9,000 per year for 7 years, and a cost of capital of 11%. Requirements: What is the project’s NPV? What is the project’s IRR? What is the project’s PI? What is the project’s payback period? What is the project’s discounted payback period?arrow_forwardProject X has an initial cost of $20,000 and a cash inflow of $25,000 in Year 3. Project Y costs $40,700 and has cash flows of $12,000, $25,000, and $10,000 in Years 1 to 3, respectively. The discount rate is 6 percent and the projects are mutually exclusive. Based on the individual project's IRRs you should accept Project. based on NPV you should accept Project: the final decision should be to accept Project. Multiple Choice O O O O Y; Y, Y Y.XY Y: X, X X;X;X X, Y, Yarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTIntermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License