Traffic and Highway Engineering
5th Edition
ISBN: 9781305156241
Author: Garber, Nicholas J.
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Question
Chapter 11, Problem 13P
To determine
Estimated construction cost in 2014 (in$).
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Answer the following questions.
1. Determine the normal duration of the project
2. Determine the normal cost of the project
3. Determine the critical path under normal conditions.
4. Determine the "minimum duration" of the project
5. Determine the minimum cost of the project if it is to be accelerated (crashed) to its "minimum duration"
A contractor who does not meet the deadline on the construction of a building is fined P8,000.00 per day for each of the first ten days of extra time, and for each additional day thereafter the fine is increased by P1,600.00 each day. If the contractor is fined P201,600.00, by how much extra days was the construction time delayed?
Kindly show the detailed solution.
1. Assume that the following goals have been established for a transportation planning study.Goal 1: The transportation system should provide mobility for all segments of the population.Goal 2: The transportation system should minimize the impact on the natural environment.Define at least three objectives for each goal that could be used to achieve the stated purpose.
2. From the sketch below, calculate the interzonal trips due to 450 work trips produced at zone i. There are 750 attractions at zone 1, 400 attractions at zone 2, and 300 attractions at zone 3. The exponent of travel time is 0.6 and the travel times are 9 minutes to zone 1, 5 minutes to zone 2, and 7 minutes to zone 3. Assume all socioeconomic adjustment factors and the value of C are equal to 1.0.
Chapter 11 Solutions
Traffic and Highway Engineering
Ch. 11 - Prob. 1PCh. 11 - Prob. 2PCh. 11 - Prob. 3PCh. 11 - Prob. 4PCh. 11 - Prob. 5PCh. 11 - Prob. 6PCh. 11 - Prob. 7PCh. 11 - Prob. 8PCh. 11 - Prob. 9PCh. 11 - Prob. 10P
Ch. 11 - Prob. 11PCh. 11 - Prob. 12PCh. 11 - Prob. 13PCh. 11 - Prob. 14PCh. 11 - Prob. 15PCh. 11 - Prob. 16PCh. 11 - Prob. 17PCh. 11 - Prob. 18PCh. 11 - Prob. 19PCh. 11 - Prob. 20PCh. 11 - Prob. 21PCh. 11 - Prob. 22PCh. 11 - Prob. 23PCh. 11 - Prob. 24PCh. 11 - Prob. 25PCh. 11 - Prob. 26PCh. 11 - Prob. 27P
Knowledge Booster
Similar questions
- Determine the amount of slack in each of a project's activities (presented below), identify the critical path, and identify the expected duration of the project. Activity Duration a (1-2) 4 b(1-3) 9 C (3-4) 5 d(2-4) 2 e(4-5) 3arrow_forwardDevelop a logic network for the sequence of activities listed in the table. Calculate the ES, EF, LS and LF times for all activities. What is the project duration? What are the critical activities? Activity Duration PIB 5 4 None 10 2 None 15 4 5 20 3 5 25 5 10 30 1 15 35 3 25 40 7 20, 30, 35arrow_forwardThe following bar chart shows the activities to complete a project in 6 months (each cell represents 1 month). The total project cost is $700. After 3 months, Activities A, B, half of C, and half of D are completed, for a cost of $200. For this point in time (2 months after the start date), what are the values of the budgeted cost of work performed, the budgeted cost of work scheduled, and the actual cost of the work performed?arrow_forward
- List several reasons for smart growth.arrow_forward1. A project your firm is considering for implementation has these estimated costs and revenues: an investment cost of $50,000; maintenance costs that start at $5,000 at the end of year (EOY) 1 and increase by $1,000 for each of the next 4 years, and then remain constant for the following 5 years; savings of $20,000 per year (EOY 1-10); and finally a resale value of $35,000 at the EOY 10. If the project has a 10-year life and the firm's MARR is 10% per year, what is the present worth of the project? Is it a sound investment opportunity? 2. A toll bridge across the Mississippi River is being considered as a replacement for the current 1-40 bridge linking Tennessee to Arkansas. Because this bridge, if approved, will become a part of the U.S. Interstate Highway system, the B-C ratio method must be applied in the evaluation. Investment costs of the structure are estimated to be $17,500,000 and $325,000 per year in operating and maintenance costs are anticipated. In addition, the bridge…arrow_forwardDetermine the probability that the project will take longer than 50 weeksarrow_forward
- engineering economy Costs for maintaining buildings at an industrial complex over a 10-year periodare expected to be $7000 in year 1, increasing at the rate of 10% per yearthrough year 10. At an interest rate of 15% per year, what uniform annualpayment is equivalent to the series of maintenance costs?arrow_forwardAssume the following project data given in Table 1. It is required to crash the project duration from its original duration to a final duration of 110 days. Assume daily indirect cost of LE 100 *arrow_forwardidentify and discuss factors that influencr well-being and life satisfaction.arrow_forward
- The following eight activities constitute an overall bar chart portrayal of a 4-month project. After 1.5 months, Activities A, B, D, and half of E were completed, for a cost of $8,000. For this project, using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead or behind schedule.arrow_forwardA construction company has an opportunity to submit a bid for the construction of a new apartment building. From the specification provided by the developer, the PERT network along with the three-time estimate (in a week) for each activity is shown in figure-1. Determine:a) Critical path and its standard deviation?b) Probability of completing the work in 38 weeks?c) Completion time duration for which the company should bid to provide 95% probability of completing the work in time?arrow_forwardA warehouse rents for $5,236 per month. Assuming that the warehouse contains 9,520 square feet (sq. ft.), calculate the annual rent per square foot.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage LearningFundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,