MANAGERIAL ACCT.(LL)-W/ACCESS >CUSTOM<
MANAGERIAL ACCT.(LL)-W/ACCESS >CUSTOM<
16th Edition
ISBN: 9781260198188
Author: Garrison
Publisher: MCG CUSTOM
bartleby

Videos

Question
Book Icon
Chapter 11, Problem 14P

1)

To determine

Delivery Cycle, Throughput Time, Manufacturing Cycle Efficiency

The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

It consists of throughput time, Value added time and non-value added time.

To depict delivery cycle in the formula form, the following formula maybe used:

Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

To Determine:

  • Throughput Time
  • Delivery Cycle
  • Manufacturing Cycle Efficiency

1)

Expert Solution
Check Mark

Answer to Problem 14P

Solution:

     
    Average Time per month (in days)
    Particulars 1 2 3 4
    Throughput Time
    7.40
    8.00
    8.80
    9.50
    Delivery Cycle
    23.40
    25.50
    27.80
    30.00
    Manufacturing Cycle Efficiency
    0.23
    0.24
    0.25
    0.26

Explanation of Solution

  • Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.

  • Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.

  • Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products

  • Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time

  • Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent

  • Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.

  • Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.

  • Given:

     
    Average Time per month (in days)
    Particulars1.0
    2.0
    3.0
    4.0
    Move time per unit
    0.4
    0.3
    0.4
    0.4
    Process Time per unit
    2.1
    2.0
    1.9
    1.8
    Wait time per order
    16.0
    17.5
    19.0
    20.5
    Queue Time per unit
    4.3
    5.0
    5.8
    6.7
    Inspection Time per unit
    0.6
    0.7
    0.7
    0.6

  • Formulas Used:

  • Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)

  • Delivery Cycle = Non Value Added activities + Total Throughput Time

  • Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.

  • Time Taken by value added activities = Time taken for Process Time

  • Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time

  • Calculations:

     
    Average Time per month (in days)
    Particulars1.02.03.04.0
         
    Move time per unit
    0.4
    0.3
    0.4
    0.4
    Queue Time per unit
    4.3
    5.0
    5.8
    6.7
    Inspection Time per unit
    0.6
    0.7
    0.7
    0.6
    Total Time For Non Value Added Activities (A)
    5.3
    6.0
    6.9
    7.7
    Process Time per unit
    2.1
    2.0
    1.9
    1.8
    Total Time For Value Added Activities (B)
    2.1
    2.0
    1.9
    1.8
    Throughput Time (A+B) [C]
    7.4
    8.0
    8.8
    9.5
    Wait time per order [D]
    16.0
    17.5
    19.0
    20.5
    Delivery Cycle (C+D)
    23.4
    25.5
    27.8
    30.0
    Manufacturing Cycle Efficiency
    Time Taken by value added activities / Total Throughput Time.
    Manufacturing Cycle Efficiency
    22.65%
    23.53%
    24.82%
    25.67%

Conclusion

Hence the throughput time, delivery cycle, and manufacturing cycle efficiency has been calculated for each months.

2)

To determine

Delivery Cycle, Throughput Time, Manufacturing Cycle Efficiency

The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

It consists of throughput time, Value added time and non-value added time.

To depict delivery cycle in the formula form, the following formula maybe used:

Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

To Determine:

Evaluation of the company’s performance over the months

2)

Expert Solution
Check Mark

Answer to Problem 14P

Solution:

The performance has improved over the last few months.

Explanation of Solution

  • Manufacturing cycle efficiency helps keep track of where time and cost is incurred in non-value added activities and performance efficiency measurement.

  • Manufacturing cycle efficiency is denoted by the following formula:

    Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.

    Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities

  • For example if the time Taken by value added activities is 25 minutes per unit and the Time Taken by non-value added activities is 35 minutes then manufacturing cycle efficiency would be 0.42.

  • Thus it can be interpreted as, the value added activities take up only 42 % of the total time taken to complete the manufacturing process and the rest is attributable to non-value added activities.

  • Given:

     
    Average Time per month (in days)
    Particulars 1 2 3 4
    Manufacturing Cycle Efficiency
    0.23
    0.24
    0.25
    0.26

  • If manufacturing cycle efficiency is 0.23, then it means that non value added activities contribute to 77% of the total throughput time and production process.

  • Since the manufacturing cycle efficiency is increasing with every month, it can be said that the time taken by non-value added activities is reducing.

Conclusion

Hence it can be said that the Manufacturing cycle efficiency improves, the time taken by non value added activities reduces.

3)

a)

To determine

Throughput Time, Manufacturing Cycle Efficiency

The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

It consists of throughput time, Value added time and non-value added time.

To depict delivery cycle in the formula form, the following formula maybe used:

Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

To Determine:

  • Throughput Time for Month 5
  • Manufacturing Cycle Efficiency for Month 5

3)

a)

Expert Solution
Check Mark

Answer to Problem 14P

Solution:

     
    Average Time per month (in days)
    Particulars 4 5
    Throughput Time
    9.50
    2.80
     
     
     
    Manufacturing Cycle Efficiency for month 5
    0.26
    0.64

Explanation of Solution

  • Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.

  • Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.

  • Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products

  • Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time

  • Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent

  • Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.

  • Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.

Given:

     
    Average Time per month (in days)
    Particulars456
       
    Move time per unit
    0.4
    0.4

    Queue Time per unit
    6.7
    0.0

    Inspection Time per unit
    0.6
    0.6

    Process Time per unit
    1.8
    1.8

Formulas Used:

  • Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)

  • Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.

  • Time Taken by value added activities = Time taken for Process Time

  • Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time

Calculations:

     
    Average Time per month (in days)
    Particulars45
       
    Move time per unit
    0.4
    0.4
    Queue Time per unit
    6.7
    0.0
    Inspection Time per unit
    0.6
    0.6
    Total Time For Non Value Added Activities (A)
    7.7
    1.0
    Process Time per unit
    1.8
    1.8
    Total Time For Value Added Activities (B)
    1.8
    1.8
    Throughput Time (A+B) [C]
    9.5
    2.8
     
     
     
    Manufacturing Cycle Efficiency
    Time Taken by value added activities / Total Throughput Time.
    Manufacturing Cycle Efficiency
    0.26
    0.64

  • Since it is given that the lean production has eliminated the queue time, the same is not considered.

Conclusion

Hence the throughput time and manufacturing cycle efficiency has been calculated for month 5.

3)

b)

To determine

Throughput Time, Manufacturing Cycle Efficiency

The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

It consists of throughput time, Value added time and non-value added time.

To depict delivery cycle in the formula form, the following formula maybe used:

Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

To Determine:

  • Throughput Time for Month 6
  • Manufacturing Cycle Efficiency for Month 6

3)

b)

Expert Solution
Check Mark

Answer to Problem 14P

Solution:

     
    Average Time per month (in days)
    Particulars 4 6
    Throughput Time
    9.50
    2.20
     
     
     
    Manufacturing Cycle Efficiency for month 6
    0.26
    0.82

Explanation of Solution

  • Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.

  • Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.

  • Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products

  • Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time

  • Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent

  • Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.

  • Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.

Given:

     


    Particulars46
       
    Move time per unit
    0.4
    0.4
    Queue Time per unit
    6.7
    0.0
    Inspection Time per unit
    0.6
    0.0
    Process Time per unit
    1.8
    1.8

Formulas Used:

  • Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)

  • Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.

  • Time Taken by value added activities = Time taken for Process Time

  • Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time

Calculations:

     
    Average Time per month (in days)
    Particulars46
       
    Move time per unit
    0.4
    0.4
    Queue Time per unit
    6.7
    0.0
    Inspection Time per unit
    0.6
    0.0
    Total Time For Non Value Added Activities (A)
    7.7
    0.4
    Process Time per unit
    1.8
    1.8
    Total Time For Value Added Activities (B)
    1.8
    1.8
    Throughput Time (A+B) [C]
    9.5
    2.2
     
     
     
    Manufacturing Cycle Efficiency
    Time Taken by value added activities / Total Throughput Time.
    Manufacturing Cycle Efficiency
    0.26
    0.82

  • Since it is given that the lean production has eliminated the queue time and inspection time, the same is not considered.

Conclusion

Hence the throughput time and manufacturing cycle efficiency has been calculated for month 6.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!

Chapter 11 Solutions

MANAGERIAL ACCT.(LL)-W/ACCESS >CUSTOM<

Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Elements of cost | Direct and Indirect: Material, Labor, & Expenses; Author: Educationleaves;https://www.youtube.com/watch?v=UFBaj6AHjHQ;License: Standard youtube license