Refer to Example 3. Suppose that regular-time capacity will be reduced to 440 units in period 3 to accommodate a companywide safety inspection of equipment. What will the additional cost of the optimal plan be as compared to the one shown in Example 3? Assume all costs and quantities are the same as given in Example 3 except for the regular-time output in period 3. Solve by modifying Table 11.6.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of 100. The projected demand, lot size, and time standards are shown in the following table:
Item
Touring
Mountain
Demand forecast
Lot size
Standard processing time
Standard setup time
5,000 units/year
100 units
.25 hour/unit
2 hours/lot
10,000 units/year
100 units
.50 hour/unit
3 hours/lot
The shop currently works 8 hours a day, 5 days a week, 50 weeks a year. It operates five workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime and without decreasing the firm’s current capacity cushion?
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component
combinations. Identical bicycles are produced in lots of 110. The projected demand, lot size, and time standards are
shown in the following table:
i
Item
Demand forecast
Lot size
Standard processing time
Standard setup time
Touring
4,000 units/year
130 units
0.20 hour/unit
2 hours/lot
Mountain
10,000 units/year
110 units
0.50 hour/unit
3 hours/lot
The shop currently works 8 hours a day, 5 days a week, 48 weeks a year. It operates five workstations, each producing
one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations
will be required next year to meet expected demand without using overtime and without decreasing the firm's current
capacity cushion?
The number of workstations required next year is. (Enter your response rounded up to the next whole number.)
16
Chapter 11 Solutions
OPERATIONS MANAGEMENT LL
Ch. 11 - What three levels of planning involve operations...Ch. 11 - What are the three phases of intermediate...Ch. 11 - Prob. 3DRQCh. 11 - Why is there a need for aggregate planning?Ch. 11 - What are the most common decision variables for...Ch. 11 - Prob. 6DRQCh. 11 - Briefly discuss the advantages and disadvantages...Ch. 11 - What are the primary advantages and limitations of...Ch. 11 - Briefly describe the planning techniques listed as...Ch. 11 - What are the inputs to master scheduling? What are...
Ch. 11 - Prob. 11DRQCh. 11 - What general trade-offs are involved in master...Ch. 11 - Who needs to interface with the master schedule...Ch. 11 - How has technology had an impact on master...Ch. 11 - Service operations often face more difficulty in...Ch. 11 - Name several behaviors related to aggregate...Ch. 11 - Compute the total cost for each aggregate plan...Ch. 11 - A manager would like to know the total cost of a...Ch. 11 - Determine the total cost for this plan given the...Ch. 11 - a. Given the following forecast and steady regular...Ch. 11 - Manager T. C. Downs of Plum Engines, a producer of...Ch. 11 - Manager Chris Channing of Fabric Mills, Inc., has...Ch. 11 - SummerFun. Inc., produces a variety of recreation...Ch. 11 - Nowjuice, Inc., produces Shakewell fruit juice. A...Ch. 11 - Wormwood, Ltd., produces a variety of furniture...Ch. 11 - Refer to Solved Problem 1. Prepare two additional...Ch. 11 - Refer to Solved Problem 1. Suppose another option...Ch. 11 - Prob. 12PCh. 11 - Prob. 13PCh. 11 - Prob. 14PCh. 11 - Prob. 15PCh. 11 - Refer to Example 3. Suppose that regular-time...Ch. 11 - Prob. 17PCh. 11 - Prob. 18PCh. 11 - Prepare a master production schedule for...Ch. 11 - Update the master schedule shown in Figure 11.11...Ch. 11 - Prepare a master schedule like that shown in...Ch. 11 - Determine the available-to-promise (ATP)...Ch. 11 - Prepare a schedule like that shown in Figure 11.12...Ch. 11 - The objective is to choose the plan that has the...Ch. 11 - Prob. 2CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Proctoring Enabled: Chapter 12 Computer Simulati. O Help Save & Exit Submit Saved Given this frequency distribution, what demand values would be associated with the following random numbers? (Do not round intermediate calculations.) Demand Frequency 29 1 23 2. 19 3. 29 Random Number Simulated Demand 0.3 0.5 0.9 Mc Graw Hill < Prev 2 of 5 ASUSarrow_forward15-arrow_forward601 Ana Chavarria, front office manager at The Times Hotel, has completed a revenue management semi- nar at Keystone University and is preparing an argu- ment in favor of adopting this concept at The Times Hotel to present to Margaret Chu, the general man- ager. She begins by compiling a history of room occupancy and ADRS, which she hopes will reveal areas in which revenue management could help. She prepares an electronic spreadsheet that lists rooms sold with corresponding room rates and correlates the data to tourism activities in the area. Ana sends an analysis of revenue realized and revenue potential to Ms. Chu for review prior to their discussion After reviewing the analysis, Ms. Chu concludes, "This is just another scam; the industry is slow to adopt this," and disregards the entire report. She knows that occupancy percentage, ADR, and RevPAR are all you need to be efficient today, so why change? Ana passes Ms. Chu in the lobby, and Ms. Chu indicates her distrust of the revenue…arrow_forward
- In year 1, if the aggregate demand of a bronze manufacturing operation is 450000 and the corresponding capacity is 150000 per machine (there are 3 machines in total with 2 operators per machine), what are the machine requirements and the corresponding labor requirements in year 1?arrow_forwardUse the Wagner–Whitin and Silver–Meal methods to find production schedules for the following dynamic lot-size problem: K $30, h $1, d1 40, d2 60, d3 10, d4 70, d5 20.arrow_forwardAn airline company must plan its fleet capacity and its long-term schedule of aircraft usage. For one flight segment, the average number of customers per day is 70, which represents a 65 percent utilization rate of the equipment assigned to the flight segment. If demand is expected to increase to 80 customers for this flight segment in three years, what capacity requirement should be planned? Assume that management deems that a capacity cushion of 20 percent is appropriate. what the needed capacity requirement is ----------- customers per day. (Enter your response rounded up to the next whole number.)arrow_forward
- S Weatherly Lumber Company processes wood pulp for manufacturing various paper products. The company employs a process costing system for its manufacturing operations. All direct materials are added at the beginning of the process, and conversion costs are incurred uniformly throughout the process. This is the company's production schedule for May: Percent Completed Materials Conversion. 100% 50% Work-in-Process Inventory, May 1 Started during May Units to account for Units from beginning Work-in-Process, which were completed and transferred out during May Started and completed during May Work-in-Process Inventory, May 31 Total units accounted for The following cost data are available: Work-in-Process Inventory, May 1 Direct materials Conversion Costs incurred during May Direct materials Conversion $ 38,010 46,568 168,300 275,380 Tons of Pulp 2,000 11,000 13,000 2,000 6,600 4,400 13,000 100% 50% Required: 1. Calculate the equivalent units of direct materials and conversion during May.…arrow_forwardSupertronics, Inc., would like to know how the firm’s profit-ability is altered by product mix. Currently, product mix isdetermined by giving priority to the product with the highestper-unit contribution margin (defined as the difference be-tween price and material cost). Details on the Supertronicsproduct line, including processing time at each workstation,follow:a. Assume that Supertronics has 5,500 minutes of capacityavailable at each workstation each week. Develop a linearprogram to define the production mix that maximizescontribution margin.b. Solve your formulation using a computer package such asPOM for Windows. c. Given your solution for part (b), which machine is thebottleneck?d. How would your formulation and solution in part(b) change if 50 units of each product were alreadycommitted to customers and thereby had to beproduced?arrow_forwardReserve capacity is a general consideration for any manufacturing or service enterprises. Which among the following is a measure of the reserve capacity which handles unexpected increases in demand O a. Capacity cushion O b. Capacity bottleneck Capacity limit O d. Capacity Planningarrow_forward
- d CE Additional Algo 5-11 Attrition Losses and Yields A process has three resources and two types of flows. The first flow has a demand of 20 units per day, and the second flow has a demand of 40 units per day. The first flow type visits all three resources, while the second flow type only visits the first and the third resources. The capacity is 100 units per day at the first resource, 40 units per day at the second resource, and 70 units per day at the third resource. 1. What is the demand total for each resource? Note: Do not round intermediate calculations. Resource Resource 1 Resource 2 Resource 3 Resource Resource 1 Resource 2 Resource 3 Type 1 20 20 20 Implied Utilization Actual Flow Rate 1 Actual Flow Rate 2 Type 2 2. What is the implied utilization for each resource? Note: Round your answers to 2 decimal places. 40 TO 40 Demand Total 3. What is the actual flow rate for each flow? Note: Round your answers to 2 decimal places.arrow_forwardSoutheastern Oklahoma State University's business program has the facilities and faculty to handle an enrollment of 2,200 new students per semester. However, in an effort to limit class sizes to a "reasonable" level (under 200, generally), Southeastern's dean, Holly Lutze, placed a ceiling on enrollment of 1,500 new students. Although there was ample demand for business courses last semester, conflicting schedules allowed only 1,400 new students to take business courses. What is the utilization rate for Southeastern? (enter your response as a percentage rounded to one decimal place). 63.6% 68.2% 90% 92.5% 93.3%arrow_forwardIIn a job shop, effective capacity is only 69 percent of design capacity, and actual output is 76 percent of effective output. What design capacity would be needed to achieve an actual output of 13 jobs per week? What is its effective capacity? a. The Design Capacity needed to achieve the required actual job outputs =Blank 1 (round to whole number) b. The Effective Capacity needed to achieve the required actual job outputs = Blank 2 (round to whole number) Blank 1 Blank 2 Add your answer Add your answerarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY