Textbook Question
Book Icon
Chapter 11, Problem 19P

Prepare a master production schedule for industrial pumps in the manner of figure 11.11 in the chapter. Use the same inputs as the example, and lot sizes of 70, but change the MPS rule from “schedule production when the projected on-hand inventory would be negative without production” to “schedule production when the projected on-hand inventory would he less than 10 without production.”

Blurred answer
Students have asked these similar questions
A initially assume that Phi wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using a lot-for-lot (L4L). Gear box requirements Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Input shaft requirements Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release
For a given store demand in Week 5 is 375 and onhand inventory at the end of Week 4 is 450 If the manufacturing lead time for this particular item is two weeks then what will be the Store demand
. Worldwide Can-Openers, Inc., makes a family of two hand-operated can openers. The production plan is based on months. There are 4 weeks in this month. Opening inventory is 2000 dozen, and it is planned to increase that to 4000 dozen by the end of the month. The MPS is made using weekly periods. The forecast and projected available balance for the two models follow. The lot size for both models is 1000 dozen. Calculate the production plan and the MPS for each item.

Chapter 11 Solutions

Operations Management (McGraw-Hill Series in Operations and Decision Sciences)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY