FUND. OF CORPORATE FIN. 18MNTH ACCESS
FUND. OF CORPORATE FIN. 18MNTH ACCESS
15th Edition
ISBN: 9781259811913
Author: Ross
Publisher: MCG CUSTOM
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 19QP

Project Analysis [LO1, 2, 3, 4] You are considering a new product launch. The project will cost $1,750,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 190 units per year; price per unit will be $17,300, variable cost per unit will be $10,400, and fixed costs will be $515,000 per year. The required return on the project is 12 percent, and the relevant tax rate is 35 percent.

a. Based on your experience, you think the unit sales, variable cost, and fixed cost projections given here are probably accurate to within ±10 percent. What are the upper and lower bounds for these projections? What is the base-case NPV? What are the best-case and worst-case scenarios?

b. Evaluate the sensitivity of your base-case NPV to changes in fixed costs.

c. What is the cash break-even level of output for this project (ignoring taxes)?

d. What is the accounting break-even level of output for this project? What is the degree of operating leverage at the accounting break-even point? How do you interpret this number?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The upper and lower bounds of unit sales, variable costs, and fixed costs projections under the scenario analysis.

Introduction:

Fixed costs remain the same as the total costs despite of the changes in the level of activity. However, the fixed cost per unit has a negative relationship with activity, that is, if the activity volume increases then total cost will decrease and vice-versa.

Variable costs are the type of costs that would vary according to the production output. It depends on the production volume.

Answer to Problem 19QP

Under the scenario analysis, the lower (worst scenario) and upper (best scenario) bounds of unit sales, variable costs, and fixed costs projections are as follows:

Scenarios

Unit sales

(in units)

Variable cost

(in $)

Fixed cost

(in $)

Base19010,400515,000
Best2099,360463,500
Worst17111,440566,500

Explanation of Solution

Given information:

The unit sales is 190 units, variable costs is $10,400, and fixed costs is $515,000. The accurate estimate is ±10%.

Formula:

The formula to calculate upper bounds of unit sales projection under the scenario analysis:

Unit sales for best case = [Value of base case unit sales +(  Percenatge of accurate estimate×Value of base case unit sales)]

The formula to calculate upper bounds of variable costs projection under the scenario analysis:

Variable costs for best case = [Value of base case variable costs ( Percenatge of accurate estimate× Value of base case variable costs)]

The formula to calculate upper bounds of fixed costs projection under the scenario analysis:

Fixed costs for best case = [Value of base case fixed costs( Percenatge of accurate estimate× Value of base case fixed costs)]

The formula to calculate lower bounds of unit sales projection under the scenario analysis:

Unit sales for worst case = [Value of base case unit sales  (  Percenatge of accurate estimate×Value of base case unit sales)]

The formula to calculate lower bounds of variable costs projection under the scenario analysis:

Variable costs for worst case = [Value of base case variable costs( Percenatge of accurate estimate× Value of base case variable costs)]

The formula to calculate lower bounds of fixed costs projection under the scenario analysis:

Fixed costs for worst case = [Value of base case fixed costs+( Percenatge of accurate estimate× Value of base case fixed costs)]

Compute the upper bounds of unit sales projection under the scenario analysis:

Unit sales for best case = [Value of base case unit sales +(  Percenatge of accurate estimate× Value of base case unit sales)]=[190+(10100×190)]=[190+(0.1×190)]

=190+19=209 units

Hence, the upper bounds of unit sales projection under the scenario analysis are 209 units.

Compute the upper bounds of variable costs projection under the scenario analysis:

Variable costs for best case = [Value of base case variable costs ( Percenatge of accurate estimate× Value of base case variable costs)]=[$10,400(10100×$10,400)]=[$10,400(0.10×$10,400)]

=$10,400$1,040=$9,360

Hence, the upper bounds of variable costs projection under the scenario analysis are $9,360.

Compute the upper bounds of fixed costs projection under the scenario analysis:

Fixed costs for best case = [Value of base case fixed costs( Percenatge of accurate estimate× Value of base case fixed costs)]=[$515,000(10100×$515,000)]=[$515,000(0.10×$515,000)]

=$515,00051,500=$463,500

Hence, the upper bounds of fixed costs projection under the scenario analysis are $463,500.

Compute the lower bounds of unit sales projection under the scenario analysis:

Unit sales for worst case = [Value of base case unit sales  (  Percenatge of accurate estimate× Value of base case unit sales)]=[190(10100×190)]=[190(0.10×190)]

=19019=171 units

Hence, the lower bounds of unit sales projection under the scenario analysis are 171 units.

Compute the lower bounds of variable costs projection under the scenario analysis:

Variable costs for worst case = [Value of base case variable costs( Percenatge of accurate estimate× Value of base case variable costs)]=[$10,400+(10100×$10,400)]=[$10,400+(0.10×$10,400)]

=$10,400+$1,040=$11,440

Hence, the lower bounds of variable costs projection under the scenario analysis are $11,440.

Compute the lower bounds of fixed costs projection under the scenario analysis:

Fixed costs for worst case = [Value of base case fixed costs+( Percenatge of accurate estimate× Value of base case fixed costs)]=$515,000+(10100×$515,000)=$515,000+(0.10×$515,000)

=$515,000+$51,500=$566,500

Hence, the lower bounds of fixed costs projection under the scenario analysis are $566,500.

Expert Solution
Check Mark
Summary Introduction

To determine: The base-case Net present value (NPV)

Introduction:

Net present value (NPV) refers to the discounted value of the future cash flows at present. The company should accept the project, if the net present value is positive or greater than zero and vice-versa. If there are two mutually exclusive projects, then the company has to select the project that has higher net present value.

Answer to Problem 19QP

The NPV for the base-case scenario is $286,619.11.

Explanation of Solution

Given information:

The fixed costs of the project are $515,000 per year and the initial cost of the project is $1,750,000 for the lifetime of 4 years. The variable cost per unit is $10,400 and the price per unit of the project is $17,300. The unit sold is 190 units per year, the required rate of return is 12%, and the tax rate is 35%.

The formula to calculate the operating cash flow under the base-case scenario:

Operating cash flow of base case scenario}=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation

Where,

P refers to the price per unit of the project

v refers to the variable cost per unit

Q refers to the number of unit sold

FC refers to the fixed costs

The formula to calculate the NPV of base-case operating cash flow:

Net present value of base case cash flow}=Initial investment+Base case operating cash flow

Compute the operating cash flow in the base-case scenario:

Operating cash flow of base case scenario}=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation=[($17,300$10,400)190$515,000]×(135100)+(35100×$1,750,0004)=[($6,900×190)$515,000]×(10.35)+(0.35×$437,500)=[$1,311,000$515,000]×(10.35)+$153,125=($796,000×0.65)+$153,125=$517,400+$153,125=$670,525

Hence, the operating cash flow under the base-case scenario is $670,525.

Compute the NPV for the base-case scenario:

Note: To determine the present value of annuity of $1 period for 4 period at a discount rate of 12% refer the PV of an annuity of $1 table. Then find out 12% discount rate and period of 8 years value from the table. Here, the value for the rate 12% and 4 years period is 3.03735.

Net present value of base case cash flow}=[Initial investment+Base case operating cash flow×(Present value of an annuity of $1 period for R% of N period)]=[$1,750,000+$670,525×(Present value of an annuity of $1 period for 12% of 4 period)]=$1,750,000+($670,525×3.03735)

=$1,750,000+$2,036,619.10875=$286,619.11

Hence, the NPV for the base-case scenario is $286,619.11.

Expert Solution
Check Mark
Summary Introduction

To determine: The worst-case scenario

Introduction:

Worst-case scenario is a particular case under the scenario analysis to determine the worst scenarios of the project. The financial managers of the company use this worst-case technique to anticipate potential losses and operational issues of the project.

Answer to Problem 19QP

The NPV for the worst-case scenario is -$1,309,315.

Explanation of Solution

Given information:

The fixed costs of the project are $515,000 per year and initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300. The unit sold is 190 units per year, required rate of return is 12%, and tax rate is 35%.

The formula to calculate the operating cash flow for worst-case scenario:

Operating cash flow of worst case scenario}=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation

Where,

P refers to the price per unit of the project

v refers to the variable cost per unit

Q refers to the number of unit sold

FC refers to the fixed costs

The formula to calculate the NPV for worst- case operating cash flow:

Net present value of worst case cash flow}=Initial investment+Worst case operating cash flow

Compute the operating cash flow under the worst-case scenario:

Operating cash flow of worst case scenario}=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation=[($17,300$11,440)×171$566,500]×(135100)+35100×($1,750,0004)=[($5,900×171)$566,500]×(10.35)+(0.35×$437,500)=[$1,008,900$566,500]×0.65+$153,125=($442,400×0.65)+$153,125=$287,560+$153,125=$440,685

Hence, the operating cash flow under the worst-case scenario is $440,685.

Compute the NPV for worst case scenario:

Net present valueof worst case cash flow}=Initial investment+Worst case operating cash flow=$1,750,000+$440,685=$1,309,315

Hence, the NPV for the worst-case scenario is -$1,309,315.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The sensitivity of base-case NPV to change in fixed costs

Introduction:

Sensitivity analysis is analyzing the impact of changing only one variable of the net present value. It helps to identify the areas in which the forecasting errors would be severe. The basic concept of sensitivity analysis is to freeze all the variables except one variable.

Answer to Problem 19QP

The sensitivity of NPV to change in the sales value is -$1.97.

Explanation of Solution

Given information:

The fixed costs of the project are $515,000 per year and initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300. The unit sold is 190 units per year, required rate of return is 12%, and tax rate is 35%. Assume the fixed cost has $516,000.

Formula:

The formula to calculate the sensitivity of NPV to make changes in the sales value:

Sensitivity of NPV to change in the sales value}=Change in NPVChange in fixed cost

The formula to calculate the NPV of the new case operating cash flow:

NPV of the new case cash flow=[Initial investment+ New case cash flow×(Present value of an annuity of $1 period for R% of N period)]

The formula to calculate the new case operating cash flow:

New case operating cash flow=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation

Where,

P refers to the price per unit of the project

v refers to the variable cost per unit

Q refers to the number of unit sold

FC refers to the fixed costs

Compute the new case operating cash flow:

New case operating cash flow=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation=[[($17,300$10,400)×190$516,000]×(135100)+35100×($1,750,0004)]=[($6,900×190)$516,000]×(10.35)+(0.35×$437,500)=[$1,311,000$516,000]×0.65+$153,125

=($795,000×0.65)+$153,125=$516,750+$153,125=$669,875

Hence, the new case operating cash flow is $669,875.

Compute the NPV of new case operating cash flow:

Note: To determine the present value of annuity of $1 period for 4 period at a discount rate of 12% refer the PV of an annuity of $1 table. Then find out 12% discount rate and period of 8 years value from the table. Here, the value for the rate 12% and 4 years period is 3.03735.

NPV of the new case operating cash flow}=[Initial investment+ New case cash flow×(Present value of an annuity of $1 period for R% of N period)]=$1,750,000+$669,875×(Present value of an annuity of $1 period for 12% of 4 period)=$1,750,000+($669,875×3.03735)=$1,750,000+$2,034,644.83125=$284,644.83

Hence, the NPV of the new case operating cash flow is $284,644.83.

Compute the sensitivity of NPV to change in the sales value:

Sensitivity of NPV to change in the sales value}=Change in NPVChange in fixed cost=($286,619.11$284,644.83)($515,000$516,000)=$1,974.28$1,000=$1.97

Hence, the sensitivity of NPV to change in the sales value is -$1.97. As a result, for every dollar of fixed cost, the NPV decrease by $1.97.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The cash break-even level of output of the project

Introduction:

Cash break-even point specifies a sales level which can result in zero operating cash flow.

Answer to Problem 19QP

The cash break-even level of output is 74.64 units.

Explanation of Solution

Given information:

The unit price is $17,300, unit variable costs are $10,400, and fixed costs are $515,000.

The formula to calculate the cash break-even quantity:

Cash break-even quantity=Fixed cost(Selling price per unitVariable cost per unit)

Compute the cash break-even quantity:

Cash break-even quantity=Fixed cost(Selling price per unitVariable cost per unit)=$515,000($17,300$10,400)=$515,000$6,900=74.64 units

Hence, the cash breakeven quantity is 74.64 units.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The accounting break-even level of output

Introduction:

Accounting break-even is a sales point at which there is no profit or loss. It is the most widely used measure of break-even point.

Answer to Problem 19QP

The accounting break-even level of output is 138.04 units.

Explanation of Solution

Given information:

The fixed costs of the project are $515,000 per year. The initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300.

The formula to calculate the accounting break-even quantity:

Accounting break-even quantity=(Fixed cost+Depreciation)(Unit priceUnit variable cost)

Compute the accounting break-even quantity:

Accounting break-even quantity=(Fixed cost+Depreciation)(Unit priceUnit variable cost)=$515,000+($1,750,0004)($17,300$10,400)=($515,000+$437,500)$6,900

=$952,500$6,900=138.04 units

Hence, the accounting breakeven quantity is 138.04 units.

Expert Solution
Check Mark
Summary Introduction

To determine: The degree of operating leverage

Introduction:

Degree of operating leverage is a measure that indicates the sensitivity on the fixed cost of a project. It interprets that a company with more high operating leverage indicates higher fixed costs and vice versa.

Answer to Problem 19QP

The degree of operating leverage is 2.18 times.

Explanation of Solution

Given information:

The fixed costs of the project are $515,000 per year. The operating cash is $$670,525.

The formula to calculate the degree of operating leverage:

Degree of operating leverage=1+(Fixed costOperating cash flow)

Compute the degree of operating leverage:

Degree of operating leverage=1+(Fixed costOperating cash flow)=1+($515,000$670,525)=1+0.76=1.76 times

Hence, the degree of operating leverage is 1.76 times. The operating cash flows will increase by 1.76% for each 1% increase in unit sales.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A3 8aii You are considering a new product launch. The project will cost $680,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 100 units per year, price per unit will be $19,000, variable cost per unit will be $14,000, and fixed costs will be $150,000 per year. The required return on the project is 15%, and the relevant tax rate is 35%. Ignore the half-year rule for accounting for depreciation.                            a. Calculate the following six numbers for this project. Round your answers to two decimal places.                                                                                               (ii) Profitability Index (PI)
1 Downside scenarios Consider a proposal to produce and market a new tennis racquet. The most likely outcome scenario for the project incl. Expected sales of 30,000 units per year, Unit price of $200, Variable cost per racquet of $120, Fixed cost of $1,200,000. The project will last for 10 years and requires an initial investment of $4 million, which will be depreciated straight-line over the project life to a fnal value of zero. The firm´s tax rate is 30%, and the required rate of return is 12%. 1. What is the project NPV? However, you recognize that some of these estimates are subject to error. Sales could fall 20% below expectations for the life of the project and, if that happens, the unit price would probably be only $150. The good news is that Öxed costs could be as low as $800,000, and total Variable costs1 would decline in proportion to sales. 2. What is NPV in the worst-case scenario?3. How else could you consider the downside scenario in your NPV calculation? (Answer…
Project Evaluation [LO1] Dog Up! Franks is looking at a new sausage systemwith an installed cost of $460,000. This cost will be depreciated straight-line to zero over the project's five-year life, at the end of which the sausage system can be scrapped for $55,000. The sausage system will save the firm $155,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $29,000. If the tax rate is 21 percent and the discount rate is 10 percent, what is the NPV of this project?

Chapter 11 Solutions

FUND. OF CORPORATE FIN. 18MNTH ACCESS

Ch. 11.5 - What is operating leverage?Ch. 11.5 - How is operating leverage measured?Ch. 11.5 - Prob. 11.5CCQCh. 11.6 - What is capital rationing? What types are there?Ch. 11.6 - Prob. 11.6BCQCh. 11 - Prob. 11.1CTFCh. 11 - Marcos Entertainment expects to sell 84,000...Ch. 11 - Delta Tool has projected sales of 8,500 units at a...Ch. 11 - What is true for a project if that project is...Ch. 11 - A capital-intensive project is one that has a...Ch. 11 - Pavloki, Inc., has three proposed projects with...Ch. 11 - Forecasting Risk [LO1] What is forecasting risk?...Ch. 11 - Sensitivity Analysis and Scenario Analysis [LO1,...Ch. 11 - Prob. 3CRCTCh. 11 - Operating Leverage [LO4] At one time at least,...Ch. 11 - Operating Leverage [LO4] Airlines offer an example...Ch. 11 - Prob. 6CRCTCh. 11 - Prob. 7CRCTCh. 11 - Prob. 8CRCTCh. 11 - Prob. 9CRCTCh. 11 - Scenario Analysis [LO2] You are at work when a...Ch. 11 - Calculating Costs and Break-Even [LO3] Night...Ch. 11 - Prob. 2QPCh. 11 - Scenario Analysis [LO2] Sloan Transmissions, Inc.,...Ch. 11 - Sensitivity Analysis [LO1] For the company in the...Ch. 11 - Sensitivity Analysis and Break-Even [LO1, 3] We...Ch. 11 - Prob. 6QPCh. 11 - Prob. 7QPCh. 11 - Calculating Break-Even [LO3] In each of the...Ch. 11 - Calculating Break-Even [LO3] A project has the...Ch. 11 - Using Break-Even Analysis [LO3] Consider a project...Ch. 11 - Calculating Operating Leverage [LO4] At an output...Ch. 11 - Leverage [LO4] In the previous problem, suppose...Ch. 11 - Operating Cash Flow and Leverage [LO4] A proposed...Ch. 11 - Cash Flow and Leverage [LO4] At an output level of...Ch. 11 - Prob. 15QPCh. 11 - Prob. 16QPCh. 11 - Sensitivity Analysis [LO1] Consider a four-year...Ch. 11 - Operating Leverage [LO4] In the previous problem,...Ch. 11 - Project Analysis [LO1, 2, 3, 4] You are...Ch. 11 - Project Analysis [LO1, 2] McGilla Golf has decided...Ch. 11 - Prob. 21QPCh. 11 - Sensitivity Analysis [LO1] McGilla Golf would like...Ch. 11 - Break-Even Analysis [LO3] Hybrid cars are touted...Ch. 11 - Break-Even Analysis [LO3] In an effort to capture...Ch. 11 - Prob. 25QPCh. 11 - Operating Leverage and Taxes [LO4] Show that if we...Ch. 11 - Scenario Analysis [LO2] Consider a project to...Ch. 11 - Sensitivity Analysis [LO1] In Problem 27, suppose...Ch. 11 - Prob. 29QPCh. 11 - Prob. 30QP
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License