Textbook Question
Chapter 11, Problem 38E
(Appendix 11A) Manufacturing Cycle Efficiency
Ventris Company found that one of its manufacturing cells had actual cycle time of 15 minutes per unit. The theoretical cycle time for this cell was 9 minutes per unit.
Required:
- 1. Calculate the amount of processing time per unit and the amount of nonprocessing time per unit.
- 2. Calculate the MCE.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Patagania Company reports that its average delivery cycle time is 20.0 days; its average throughput time is 7.5 days; its manufacturing cycle efficiency is 0.32; its average move time is 0.2 day; and its average queue time is 4.0 days: a. What is the wait time? b. What is the process time? c. What is the inspection time?
Answer with complete set solution pls
Schurz Corporation's management reports that its average delivery cycle time is 29 days, its average throughput time is 13.0 days, its
manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.6 day, and its average queue time is 3.0 days.
Required:
a. What is the wait time? (Round your answer to 1 decimal place.)
b. What is the process time? (Round your answer to 1 decimal place.)
c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.)
a
b
C
Wait time
Process time
Inspection time
days
days
days
SanaMolp management reports that its average delivery cycle time is 20.0 days; its average throughput time is 7.5 days; its manufacturing cycle efficiency is 0.32; its average move time is 0.2 day; and its average queue time is 4.0 days: a. What is the wait time? b. What is the process time? c. What is the inspection time?
Answer with solution pls
Chapter 11 Solutions
EBK MANAGERIAL ACCOUNTING: THE CORNERST
Ch. 11 - Discuss the differences between centralized and...Ch. 11 - Prob. 2DQCh. 11 - Explain why firms choose to decentralize.Ch. 11 - What are margin and turnover? Explain how these...Ch. 11 - What are the three benefits of ROI? Explain how...Ch. 11 - What is residual income? What is EVA? How does EVA...Ch. 11 - Can residual income or EVA ever be negative? What...Ch. 11 - What is transfer price?Ch. 11 - Prob. 9DQCh. 11 - (Appendix 11A) What is the Balanced Scorecard?
Ch. 11 - (Appendix 11A) Describe the four perspectives of...Ch. 11 - The practice of delegating authority to...Ch. 11 - Which of the following is not a reason for...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - The key difference between residual income and EVA...Ch. 11 - It ROI for a division is 15% and the company's...Ch. 11 - Prob. 9MCQCh. 11 - Prob. 10MCQCh. 11 - (Appendix 11A) Which of the following is a...Ch. 11 - (Appendix 11A) The length of time it takes to...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 16BEACh. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 21BEBCh. 11 - Calculating Transfer Price Teslum Inc. has a...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Types of Responsibility Centers Consider each of...Ch. 11 - Margin, Turnover, Return on Investment Pelak...Ch. 11 - Margin, Turnover, Return on Investment, Average...Ch. 11 - Return on Investment, Margin, Turnover Data follow...Ch. 11 - Residual Income The Avila Division of Maldonado...Ch. 11 - Economic Value Added Falconer Company had net...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Prob. 33ECh. 11 - Use the following information for Exercises 11-33...Ch. 11 - Prob. 35ECh. 11 - (Appendix 11A) Cycle Time and Velocity Prakesh...Ch. 11 - (Appendix 11A) Cycle Time and Velocity Lasker...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - Return on Investment and Investment Decisions...Ch. 11 - Return on Investment, Margin, Turnover Ready...Ch. 11 - Return on Investment for Multiple Investments,...Ch. 11 - Return on Investment and Economic Value Added...Ch. 11 - Transfer Pricing GreenWorld Inc. is a nursery...Ch. 11 - Prob. 45PCh. 11 - Prob. 46PCh. 11 - (Appendix 11A) Cycle Time, Velocity, Conversion...Ch. 11 - (Appendix 11A) Balanced Scorecard The following...Ch. 11 - (Appendix 11A) Cycle Time and Velocity,...Ch. 11 - Prob. 50C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- A manual assembly line is being designed for a product with annual demand = 100,000 units. The line will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/shift. Work units will be attached to a continuously moving conveyor. Work content time = 42.0 min. Assume line efficiency E = 0.97, balancing efficiency Eb = 0.92, and repositioning time Tr = 6 sec. Determine: (a) hourly production rate to meet demand, (b) number of workers required.arrow_forwardWrite a linear cost function equation for each of the following conditions. Use y for estimated costsand X for activity of the cost driver. Machine operating costs include $1,000 of maintenance per month, and $15.00 of coolant usagecosts for each day the machinery is in operation.arrow_forwardPrakesh Company has the following data for one of its manufacturing cells: Maximum units produced in a month: 62,500 units Actual units produced in a month: 56,250 units Hours of production labor in one month: 10,000 hours Required: 1. Compute the theoretical cycle time. Round your answer to the nearest whole minute.fill in the blank 1 minutes per unit 2. Compute the actual cycle time. Round your answer to the nearest whole minute.fill in the blank 2 minutes per unit 3. Compute the theoretical velocity. Round your answer to the nearest whole unit.fill in the blank 3 units per hour 4. Compute the actual velocity. Round your answer to the nearest whole unit.fill in the blank 4 units per hourarrow_forward
- (Chapter 4: Process Improvement) Consider a process consisting of three resources. Assume the demand rate is 8 units/hour. The process activities are always performed in the following sequence. Resource 1 has a processing time of 5 minutes per unit. Resource 2 has a processing time of 4 minutes per unit. Resource 3 has a processing time of 6 minutes per unit. Resource 1 is staffed by worker A and A's wage rate is $13 per hour. Resource 2 is staffed by worker B and B's wage rate is $13 per hour. Resource 3 is staffed by worker C and C's wage rate is $20 per hour. If one additional worker could be hired, to which resource should this worker be assigned? Calculate the new process capacity in units/hr. O Assign the new worker to Resource 3. The process capacity is 12 units per hour. O Assign the new worker to Resource 3. The process capacity is 10 units per hour. O Assign the new worker to Resource 1. The process capacity is 20 units per hour. O Assign the new worker to Resource 2. The…arrow_forwardCompute (a) cycle time, (b) value-added time, (c) non-value-added time, and (d) cycle efficiency using the following information for a manufacturer. Process time. 2.10 days Move time. 0.75 days Inspection time. 0.50 days Wait time. 0.15 daysarrow_forwardAssume that a company has the following data for one of its manufacturing cells: Theoretical velocity – 40 units per hour; Productive minutes available (per year) – 1,200,000; Annual conversion costs - $4,800,000; and Actual velocity – 30 units per hour. choose the correct letter of answer Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute.a.$6b.$8c.$7d.$3 calculate the ideal conversion cost per unit using theoretical cycle time and the standard cost per minute.a.$6b.$8c.$7d.$3arrow_forward
- Delko Company has the following data for one of its manufacturing plants: Maximum units produced in a quarter (3-month period): 250,000 units Actual units produced in a quarter (3-month period): 210,000 units Productive hours in one quarter: 25,000 hours The actual cycle time for Indy Company is 7.14 minutes, and the theoretical cycle time is 6 minutes. Required: 1. Calculate the amount of processing time and the amount of nonprocessing time. If required, round your answers to two decimal places. Processing time minutes Nonprocessing time minutes 2. Calculate the MCE. If required, round your answer to nearest whole number.arrow_forwardProduct A has a contribution margin per unit of $500 and required 2 hours of machine times. Product B has a contribution margin per unit of $1,000 and requires 5 hours of machine time. How much of each product should be produced given there are 100 hours of variable machine time?arrow_forwardHernandez Corp. wants to compute its throughput for August. The following production data are available: Good units produced and sold 2,923,200 Total units produced 4,844,000 Total processing (in hours) 201,600 Value-added time (in hours) 50,300 a. Determine the manufacturing cycle efficiency. ______% b. Determine the process productivity. ______ units per hour c. Determine the process quality yield. ______% d. Determine the throughput using only good units and total time. ______ units per hourarrow_forward
- For a typical order, assume the following times (in hours): storage time (in between processes), 4.0; inspection time, 2.0; move time (from process to process), 3.0; and manufacturing (processing) time, 6.0. Given this information, what is the manufacturing cycle efficiency (%)? (Hint: Refer to Exhibit 14.14.) (Round your answer to 1 decimal place. (e.g., 32.463% = 32.5%))arrow_forwardThe assembly-line activities are given as follows for the manufacturing of a product: Performance Time (mins) Performance Time (mins) 6 4 5 3 Task A B с D Predecessors A B B Task E F G H 524 2 Predecessors C с D, E, F G For a given 7-minute cycle time after allowances, the theoretical minimum number of workstations = (round your response to the immediate higher whole number).arrow_forwardCraig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 20 minutes Inspection time: 18 minutes Rework time: 12 minutes Required: Calculate MCE. Comment on its significance.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license