Textbook Question
Chapter 11, Problem 4P
Figure 11.31 shows a partially completed MPS record for ball bearings.
- Develop the MPS for ball bearings.
- Four customer orders arrived in the following sequence:
Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
From the perspective of the development of manufacturing support systems, the "Product Management Integration" phase includes all of the following systems EXCEPT:
Question 19 options:
MRP II (Manufacturing Resource Planning)
MRP (Materials Requirements Planning)
CL MRP (Closed Loop Material Requirements Planning)
LIS (Logistics Information System)
Previous PageNext Page
MGT 314 (Operation Management)
MCQ:
ecently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning.
Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine…
Chapter 11 Solutions
Operations Management: Processes and Supply Chains (11th Edition)
Ch. 11 - Consider the master flight schedule of a major...Ch. 11 - For an organization of your choice, such as where...Ch. 11 - Consider a service provider that is in the...Ch. 11 - Complete the MPS record in Figure 11.29 for a...Ch. 11 - Complete the MPS record in Figure 11.30 for a...Ch. 11 - Prob. 3PCh. 11 - Figure 11.31 shows a partially completed MPS...Ch. 11 - Tabard Industries forecasted the following demand...Ch. 11 - Figure 11.32 shows a partially completed MPS...Ch. 11 - The forecasted requirements for an electric hand...
Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Additional Business Textbook Solutions
Find more solutions based on key concepts
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
What is precedent, and how does it affect common law?
Business in Action
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Assume you are the manager of Assembly, Inc. You have just received an order for 27 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot.arrow_forwardAssume you are the manager of Assembly Inc., you have just received an order for 40 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order, given the subassembly G must be ordered in multiples of 80 units & all other components are ordered lot for lot. Assume that the components are used only for this particular robot. Item Lead time (ks) On Hand Components B, G, C(3) Robot 2 10 1 E, F G(2), H C E F G H 1 2 3 2 1 5 20 4 8 15 10arrow_forwardAssume you are the manager of Assembly, Inc. You have just received an order for 24 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot. Item Robot B с CBECE F G H Lead Time (weeks) On Hand 10 5 20 2 1 1 2 3 2 1 Click here for the Excel Data File Subassembly G order quantity (in units) Order subassembly G at start of week 4 HA 850 15 10 о Components B, G, C(3) E, F G(2), H LIFE 2 80arrow_forward
- Culinary Creations caters weddings, office parties, and the like. Monica, the owner of Culinary Creations, offers delectable dishes and impeccable service. Her firm has gained a reputation for offering unique themed dinners and parties. Consequently, there is no shortage of demand. If a customer wants to customize a party beyond the regular “themes,” the customer must reserve a date several months in advance so that Monica can plan for all contingencies and deliver perfection. Culinary charges a premium price for its unique services. Required: a. Describe three internal processes that Culinary must execute well to deliver on its value proposition. Justify your choices. b. What might be the appropriate performance measures for these critical processes?arrow_forwardIf the the Net Requirement for a product for a particular time period in a MRP problem is 78 and the organization uses a policy of ordering in multiples of 100, what would be the Planned Order Receipt?arrow_forwardPlease do not give solution in image format thankuarrow_forward
- Assume that you are the manager of Assembly, Inc. You have just received an order for 25 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot. Item Lead Time (weeks) On Hand Components Robot 2 10 B, G, C(3) B 1 5 E, F C 1 20 G(2), H E 2 4 — F 3 8 — G 2 15 — H 1 10 — Subassembly G order quantity (in units) Subassembly G should start at beginning of Week (Click to select) 1 2 3 4arrow_forwardh4q3barrow_forwarda. Given the following master schedule, fill in the projected available and availableto promise rows: b. A customer wants an order of 100 in period 4. What can you tell him?c. The customer from part (b) cancels his request, but then says he wants 120 in period 5.What do you tell him now?d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs fora sales promotion. What do you tell them and why?e. What action (if any) should be taken in period 11? Why is it okay to take theaction?arrow_forward
- The Finishing Department had 5,000 incomplete units in its beginning Work-in-Process Inventory which were 100% complete as to materials and 30% complete as to conversion costs. 15,000 units were received from the previous department. The ending Work-in-Process Inventory consisted of 2,000 units which were 50% complete as to materials and 30% complete as to conversion costs. The Finishing Department uses first-in, first-out (FIFO) process costing.What are the equivalent units of production for the conversion costs during the period? 17,100. 14,500. 15,100. 16,500.arrow_forwardTuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of 100. The projected demand, lot size, and time standards are shown in the following table: Item Touring Mountain Demand forecast Lot size Standard processing time Standard setup time 5,000 units/year 100 units .25 hour/unit 2 hours/lot 10,000 units/year 100 units .50 hour/unit 3 hours/lot The shop currently works 8 hours a day, 5 days a week, 50 weeks a year. It operates five workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime and without decreasing the firm’s current capacity cushion?arrow_forwardMgt-314 (Operations Management) MCQ:arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY