Textbook Question
Book Icon
Chapter 11, Problem 7P

A company produces to a seasonal demand, with the forecast for the next 12 months as given below. The current labor force can produce 500 units per month. Each employee can produce 20 units per month and is paid $2,000 per month. The inventory-carrying cost is $50 per unit per year. Changes in the production level cost s100 per unit due to hiring or layoffs, line changeover costs, and so forth. Assume 200 units of initial inventory.

  1. a. What is the cost of carrying inventory for the month of January for the level strategy?
  2. b. What is the total cost of the level strategy including regular time, inventory carrying cost and changes in production level?
  3. c. What is the total cost of the chase strategy?

Chapter 11, Problem 7P, A company produces to a seasonal demand, with the forecast for the next 12 months as given below.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The inventory carrying cost for the month of January for the level strategy.

Introduction:

The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. There are three kinds of aggregate planning; they are level strategy, chase strategy, and mixed strategy.

Explanation of Solution

Given information:

The present labor force can produce 500 units per month, and the demand with the forecast for the next 12 months is given below:

Month Demand
J 651
F 700
M 850
A 702
M 650
J 500
J 600
A 850
S 803
O 900
N 703
D 600

Each employee can produce 20 units per month and is paid $2,000 per month. Inventory carrying cost is given as $50 per unit per year. Changes in the production level is $100 per unit during line changeover costs, hiring, and layoffs. Initial inventory is given as 200 units.

Determine the inventory for 12 months:

Month Demand Production Inventory
J 651 709.08 258.08
F 700 709.08 267.17
M 850 709.08 126.25
A 702 709.08 133.33
M 650 709.08 192.42
J 500 709.08 401.50
J 600 709.08 510.58
A 850 709.08 369.67
S 803 709.08 275.75
O 900 709.08 84.83
N 703 709.08 90.92
D 600 709.08 200.00
Total 8509 8509.00 2910.50

Computation of inventory for 12 months:

OPERATIONS MANAGMENT IN...-ACCESS, Chapter 11, Problem 7P , additional homework tip  1

Determine the cost of carrying inventory for the month of January for the level strategy:

It is calculated by multiplying the inventory for the month of January (refer table), and the value is attained by dividing inventory carrying cost and number of months.

Inventory carrying cost=Sum of inventory units×Inventory carrying costNumber of months=258.08×5012=1,075.33

Hence, the inventory carrying cost is $1,075.33.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The total cost of level strategy.

Introduction:

The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. There are three kinds of aggregate planning; they are level strategy, chase strategy, and mixed strategy.

Explanation of Solution

Given information:

The current labor force can produce 500 units per month, and the demand with the forecast for the next 12 months is given below:

Month Demand
J 651
F 700
M 850
A 702
M 650
J 500
J 600
A 850
S 803
O 900
N 703
D 600

Each employee can produce 20 units per month and is paid $2,000 per month. Inventory carrying cost is given as $50 per unit per year. Deviations in the production level is $100 per unit during line changeover costs, hiring, and layoffs. Initial inventory is given as 200 units.

Determine the regular time cost:

It is calculated by multiplying production units, number of months, and changes in the production level cost.

Regular time cost=Number of months×Changes in the production line×Production units=12×100×709.08=850,896

Hence, the regular time cost is $850,896.

Determine the inventory carrying cost:

It is computed by multiplying the sum of inventory (refer table), and the value is attained by dividing inventory carrying cost and number of months.

Inventory carrying cost=Sum of inventory units×Inventory carrying costNumber of months=2,910.50×5012=12,127.08

Determine the change in production level:

It is calculated by multiplying the changes in the production line and the difference between regular production per month and the calculated production.

Changing in production level=Cost of change in production line×(ProductionRegular production)=100×(709500)=100×209=$20,900

Determine the total cost of level strategy:

It is calculated by adding regular time cost, inventory carrying cost, and change in production level cost.

Total cost of level strategy=(Regular time cost+Inventory carrying cost+Change in production level cost)=$850,896+$12,127.08+$20,900=$883,923.08

Hence, the total cost of level strategy is $883,923.08.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The total cost of chase strategy.

Introduction:

The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. There are three kinds of aggregate planning; they are level strategy, chase strategy, and mixed strategy.

Explanation of Solution

Given information:

The current labor force can produce 500 units per month, and the demand with the forecast for the next 12 months is given below:

Month Demand
J 651
F 700
M 850
A 702
M 650
J 500
J 600
A 850
S 803
O 900
N 703
D 600

Each employee can produce 20 units per month and is paid $2,000 per month. Inventory carrying cost is given as $50 per unit per year. Changes in the production level is $100 per unit during line changeover costs, hiring, and layoffs. Initial inventory is given as 200 units.

Determine the inventory for 12 months:

Month Demand Production Inventory Change in production level
J 651 651 200 151
F 700 700 200 49
M 850 850 200 150
A 702 702 200 148
M 650 650 200 52
J 500 500 200 150
J 600 600 200 100
A 850 850 200 250
S 803 803 200 47
O 900 900 200 97
N 703 703 200 197
D 600 600 200 103
Total 8509 8509 2400 1494

Computation of inventory for 12 months:

OPERATIONS MANAGMENT IN...-ACCESS, Chapter 11, Problem 7P , additional homework tip  2

Determine the regular time cost:

It is computed by multiplying production units, number of months, and changes in the production level cost.

Regular time cost=Changes in the production line×Sum of production units=100×8,509=$850,900

Hence, the regular time cost is $850,900.

Determine the inventory carrying cost:

It is calculated by multiplying the sum of inventory (refer table), and the value is attained by dividing inventory carrying cost and number of months.

Inventory carrying cost=Sum of inventory units×Inventory carrying costNumber of months=2,400×5012=10,000

Determine the change in production level:

It is calculated by multiplying the sum of changes in the production level and cost of change in production line.

Changing in production level=(Cost of change in production line×Sum of change in production level)=100×1,494=$149,400

Determine the total cost of chase strategy:

It is calculated by adding regular time cost, inventory carrying cost, and change in production level cost.

Total cost of chase strategy=(Regular time cost+Inventory carrying cost+Change in production level cost)=$850,900+$10,000+$149,400=$1,010,300

Hence, the total cost of chase strategy is $1,010,300.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The Yeasty Brewing Company Produces a popular local beer known as Iron Stomach. Beer sales are somewhat seasonal, and Yeasty is planning its production and workforce levels on March 31 for the next six months. The demand forecasts are as follows: month production days demand(in hundred of cases) April 14 75 May 20 100 June 24 200 July 26 140 August 20 100 September 18 50 As of March 31, Yeasty had 70 workers on the payroll. Over a period of 20 working days when there are 100 workers on the pay roll, Yeasty produced 10,000 cases of beer. The cost to hire each worker is $200 and the cost of laying off each worker is $400. Holding costs amount to 1 dollar per case per month. As of March 31, Yeasty expects to have 3,000 cases of beer in stock. It plans to start October with 3,500 cases on hand. a) Formulate the problem of planning Yeasty’s production levels as a linear program. b) Use Excel solver to solve the problem and give the solution (decision variables and…
Demand for a product is forecasted for the six periods is 263, 256, 301, 312, 304, and 294 respectively. If a CHASE DEMAND strategy is adopted, and the regular production cost is RO 12 per unit with a maximum regular production of 280 units per period. While, the overtime and subcontract costs are RO 20 and RO 25 per unit respectively. There is no limit on subcontracting however, maximum overtime production capacity is 10. Average inventory holding cost is RO 5 per unit per period. What will be the tatal cost of subrontracting the production? Select one: O a 12/5 O b. 19668 O C. RO0 Odo O e. None is correct
The ABC Company is making a production plan for the next year, given the sales forecast for the next year as: Quarter 1 2 3 4 Total Sales Forecast (units) 9,000 12,000 16,000 12,000 49,000 Currently, the firm has 12 employees, each producing up to 1,000 units per quarter and earning $2,000 per quarter. The firm estimates its inventory carrying cost to be $2 per unit of ending inventory per quarter and its hiring or layoff costs to be $1,600 per employee. The company currently has an inventory of 2,000 units and wishes to have an ending inventory of at least 1,000 units at the end of each quarter. The company does not plan to incur inventory shortages. Find the optimal production plan that minimizes the total cost by Excel solver
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Single Exponential Smoothing & Weighted Moving Average Time Series Forecasting; Author: Matt Macarty;https://www.youtube.com/watch?v=IjETktmL4Kg;License: Standard YouTube License, CC-BY
Introduction to Forecasting - with Examples; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=98K7AG32qv8;License: Standard Youtube License