EBK 3N3-EBK: INFORMATION TECHNOLOGY PRO
EBK 3N3-EBK: INFORMATION TECHNOLOGY PRO
9th Edition
ISBN: 9780176900601
Author: SCHWALBE
Publisher: VST
Expert Solution & Answer
Book Icon
Chapter 12, Problem 6QQ
Program Description Answer

The Point of Total Assumption is when the contractor is held responsible for every extra dollar of the contract cost.   

Hence, the correct answer is option “D”.

Blurred answer
Students have asked these similar questions
Question One (1)   You participated in an evaluation of proposals for consulting services. At the end of the Technical Evaluation which required a minimum of 70 points, you got the following results:   CONSULTANTS KANYIHAMPA MUSANGILA Technical Score 75.17 76.17 Amount USD475,000.00 USD625,000.00   The lowest evaluated financial proposal (Fm) is given the maximum financial score of 100. The formula for determining the financial score is as follows: SF = 100 x Fm /F in which SF is the financial score, Fm is the lowest price and F is the price of the proposal under consideration. The weights given to the Technical and Financial proposals are 80 and 20 respectively. Calculate for each consultant below (a – c): Weighted Technical score. Financial score Combined weighted Technical and weighted Financial score Indicate the best evaluated bidder and their points
Table that fulfills the function of relating each project requirement to the deliverable that satisfies it.   a.BCG Matrix b.Project Requirements Traceability Matrix c.Traceability Matrix
Use Critical Path Method to estimate in how many weeks the project below will be submitted and find the critical path. (Choose 2 answers weeks and critical path) Activity A: Prepare initial design B: Identify new potential clients C: Develop prospectus for tenants A D: Prepare final design E: Obtain planning permission F: Obtain finance from bank G: Select contractor H: Construction I: Finalize tenant contracts dependent time 8 D 3 D 4 6, F В, С, Е I, H 17 13 J: Tenants move in Critical path : A-D-E-F-H-J O Critical path: A-C-E-F H-J 35 weeks 29 Weeks Critical path : A-G-E-F-H-J 34 Weeks
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning