Question
Chapter 12, Problem 7P
Summary Introduction
To calculate: The selection of the investment using pay-back period.
Introduction:
Pay-back period (PBP):
It is one of the methods of capital budgeting that helps evaluate the time period in which the amount of initial investment is recovered. The formula for the calculation of the PBP is shown below:
Where,
Year = The year in which cumulative cash flow is near and less than the initial investment.
Initial investment = The amount of the investment.
Cumulative cash flow = The cumulative cash flow which is near and less than the initial investment.
Cash flow = The cash flow of the next year from the “Year� used for the calculation.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider two investments with the following sequences of cash flows:
(a) Compute the IRR for each investment.(b) At MARR = 10%, determine the acceptability of each project.(c) If A and B are mutually exclusive projects, which project would you selecton the basis of the rate of return on incremental investment?
Consider two investments with the following sequences of cash flows:
(a) Compute the IRR for each investment.(b) At MARR = 15%. determine the accepta bility of each project.(c) If A and B are mutually exclusive projects. which project would you selecton the basis of the rate of return on incremental investment?
Consider the following cash flows, for four different projects: (given)
(a) Calculate the conventional payback period for each project.(b) Determine whether it is meaningful to caJculate a payback period for Project D.(c) Assuming i = I 0% calculate the discounted-payback period for each project.
Chapter 12 Solutions
FOUND.OF FINANCIAL MANAGEMENT-ACCESS
Ch. 12 - Prob. 1DQCh. 12 - Why does capital budgeting rely on analysis of...Ch. 12 - Prob. 3DQCh. 12 - Prob. 4DQCh. 12 - What does the term mutually exclusive investments...Ch. 12 - Prob. 6DQCh. 12 - If a corporation has projects that will earn more...Ch. 12 - What is the net present value profile? What three...Ch. 12 - How does an asset’s ADR (asset depreciation...Ch. 12 - Assume a corporation has earnings before...
Ch. 12 - Assume a corporation has earnings before...Ch. 12 - Assume a firm has earnings before depreciation and...Ch. 12 - Assume a firm has earnings before depreciation and...Ch. 12 - Al Quick, the president of a New York Stock...Ch. 12 - Prob. 6PCh. 12 - Prob. 7PCh. 12 - Assume a 90,000 investment and the following cash...Ch. 12 - Prob. 9PCh. 12 - X-treme Vitamin Company is considering two...Ch. 12 - You buy a new piece of equipment for 16,230, and...Ch. 12 - Prob. 12PCh. 12 - Home Security Systems is analyzing the purchase of...Ch. 12 - Aerospace Dynamics will invest 110,000 in a...Ch. 12 - The Horizon Company will invest 60,000 in a...Ch. 12 - Skyline Corp. will invest 130,000 in a project...Ch. 12 - The Hudson Corporation makes an investment of ...Ch. 12 - The Pan American Bottling Co. is considering the...Ch. 12 - You are asked to evaluate the following two...Ch. 12 - Turner Video will invest 76,344 in a project. The...Ch. 12 - The Suboptimal Glass Company uses a process of...Ch. 12 - Keller Construction is considering two new...Ch. 12 - Davis Chili Company is considering an investment...Ch. 12 - Telstar Communications is going to purchase an...Ch. 12 - Assume 65,000 is going to be invested in each of...Ch. 12 - The Summit Petroleum Corporation will purchase an...Ch. 12 - Oregon Forest Products will acquire new equipment...Ch. 12 - Universal Electronics is considering the purchase...Ch. 12 - Prob. 30PCh. 12 - Prob. 31PCh. 12 - Prob. 32PCh. 12 - Hercules Exercise Equipment Co. purchased a...Ch. 12 - Prob. 2WECh. 12 - Returning to TXN’s summary page, record the...
Knowledge Booster
Similar questions
- Assume a company is going to make an investment in a machine of $825,000 and the following are the cash flows that two different products would bring. Which of the two options would you choose based on the payback method?arrow_forwardYou are choosing between two projects. The cash flows for the projects are given in the following table ($ million): a. What are the IRRs of the two projects? b. If your discount rate is 4.6%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently?arrow_forwardYou are choosing between two projects. The cash flows for the projects are given in the following table ($ million): a. What are the IRRs of the two projects? b. If your discount rate is 4.6%, what are the NPVS of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the IRRS of the two projects? The IRR for project A is%. (Round to one decimal place.) Data table CHE (Click on the following icon in order to copy its contents into a spreadsheet.) Project Year 0 Year 1 Year 2 A -$48 $25 $21 B - $98 $20 $39 Print Done Year 3 $19 $52 Year 4 $14 $62 -arrow_forward
- consider the following two investments with the cashfow as shown. given the project are mutually exclusive, use Incremental-Investement Analysis to determine which of the two projects you should select. Given that the MARR required by management is 12%.arrow_forwardConsider two investment projects with the following cash flow transactions: Compute the rate of return for each project.arrow_forwardBelow is the schedule of cash flows for Investment PEK and Investment PVG. Using the NPV, and IRR as criteria, which between Investment PEK and Investment PVG will you choose? Which is the best decision criterion? Justify your answer. Note that your capital outlay for Investment PEK is RMB 85,000.00 and your capital outlay for Investment PVG is also RMP 85,000.00. Assume that the interest rate is 10%. How will your answer in (1) change if the interest rate increases by 5%? How will your answer in (1) change if the interest rate decreases by 5%? Comment on the impact of changing the interest rate on your NPV and IRR. Year Year-end Cash Flow PEK PVG 1 30,000.00 50,000.00 2 30,000.00 20,000.00 3 30,000.00 24,000.00 4 30,000.00 26,000.00 5 30,000.00 18,000.00arrow_forward
- Consider two assets with the following cash flow streams: Asset A generates $4 at t=1, $3 at t=2, and $10 at t=3. Asset B generates $2 at t=1, $X at t=2, and $10 at t=3. Suppose X=6 and the interest rate r is constant. Suppose r=0.2. Find the value X such that the present value of asset B is 12. Suppose the (one-period) interest rates are variable and given as follows: r01=0.1,r12=0.2, r23=0.3. Calculate the yield to maturity of asset A. (You can use Excel or ascientific calculator to find the solution numerically.)arrow_forwardYou identify an investment project with the following cash flows. If the discount rate is 10%, what is the present value of these cash flows? Y1- $500 Y2- $550 Y3- $800 Y4- $450. Please type answer no write by hend.arrow_forwardYou are choosing between two projects. The cash flows for the projects are given in the following table ($ million): - a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the IRRs of the two projects? The IRR for project A is%. (Round to one decimal place.) Data table (Click on the following icon in order to copy its contents into a spreadsheet.) Project Year 0 Year 1 Year 2 A - $49 $23 $19 B - $101 $19 $40 Print Done Year 3 $18 $49 Year 4 $14 $62 Xarrow_forward
- Consider two investments with the following sequences of cash flows: (a) Compute the i* for each investment.(b) Plot the present-worth curve for each project on the same chart and find the interest rate that makes the two projects equivalent.(c) If A and B are mutually exclusive investment projects, which project is more economically desirable at MARR of 15%?arrow_forwardConsider two assets with the following cash flow streams:Asset A generates $4 at t=1, $3 at t=2, and $10at t=3. Asset B generates $2 at t=1, $X at t=2, and $10at t=3.Suppose X=6 and the interest rate r is constant. (a)For r=0.1, calculate the present value of the two assets. (b)Determine the set of all interest rates {r} such that asset A is more valuable than asset B. (c)Draw the present value of the assets as a function of the interest rate. (d)Suppose r=0.2.Find the value X such that the present value of asset B is 12. (e)Suppose the (one-period) interest rates are variable and given as follows: r01=0.1, r12=0.2, r23=0.3. Calculate the yield to maturity of asset A.arrow_forwardYou are considering an investment project with the cash flows of -300 (the initial cash flow), 700 (cash flow at year 1), -200 (cash flow at year 2). Given the discount rate of 10%, compute the Modified Internal Rate of Return (MIRR) using the discounting approach. 50.44% 10.72% O 28.64% O 37.84%arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College