A construction company is negotiating on a construction project with a six-month duration. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. The owner also holds 5% retention. Final payment is expected one month after completion of the project and includes payment of the retention. The construction company pays material suppliers in full when it receives payment from the owner. The construction company pays subcontractors when it receives payment from the owner but withholds 5% retention from the subcontractor’s payment. The construction company pays for labor weekly. The projected monthly material, labor, and subcontractor costs, as well as the amount the construction company will bill the project’s owner each month, are shown in Table 12-9. Determine the monthly cash flows and the total cash generated by the project at the end of each month and just before each payment is received from the project’s owner. What is the maximum amount of cash invested by the company during the completion of the project?
Trending nowThis is a popular solution!
Chapter 12 Solutions
Construction Accounting And Financial Management (4th Edition)
- Bridgeport Corp. enters into a contract with a customer to build an apartment building for $921,300. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $156,000 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $52,000 each week that completion is delayed. Bridgeport commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability August 1, 2018 70 % August 8, 2018 20 August 15, 2018 6 After August 15, 2018 4 Determine the transaction price for this contract.arrow_forwardInfotech Bhd enters a contract on 1 January 2019 to produce software for a customer for RM5,000,000. Infotech Bhd receives RM2,000,000 from the customer upon contract signing and the balance at the completion of the contract. According to the contract, the customer controls the system during the creation of the program. Infotech Bhd estimates that it will take two years to complete the project and uses the number of labor hours to estimate the rate of completion. Macro Tech spends 30,000 hours in the first year of the contract and another 20,000 hours the second year. Required: Prepare the entries recorded by Macro Tech over the life of this contract. Assume that all payments are complete by the end of 2020.arrow_forwardBlossom Snow Removal Ltd. is a residential and commercial snow removal company Blossom signs contracts with customers for snow removal services that start on November 1 and end on March 30. The company starts signing contracts in the month of September for the winter season. Blossom has a year end on December 31 and had the following transactions involving current liabilities during the year: 1 Blossom signs contracts with customers and requests 100% of the contract price as a deposit at the time of signing. The company signed contracts for snow removal totaling $615,000. Based on past history, Blossom estimates that ane third (1/3) of the contract amount is earned by December 31. 2 Blossom has 10 employees, who are on standby in the event it snows. The employees earn gross wages of $125.000 for the year. From this, the company deducted 15% for income taxes, $6,813 in CPP premiums, and $1,975 in El premiums before distributing the pay cheques to the staff. As an employer, Blossom was…arrow_forward
- Metlock Corp. enters into a contract with a customer to build an apartment building for $1,061,500. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $147,900 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $49,300 each week that completion is delayed. Metlock commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by August 1, 2021 August 8, 2021 August 15, 2021 After August 15, 2021 Probability Transaction Price $ 70 % 20 5 5 (a) Determine the transaction price for the contract, assuming Metlock is only able to estimate whether the building can be completed by August 1, 2021, or not (Metlock estimates that there is a 70% chance that the building will be completed by August 1, 2021). (If answer is 0, please enter 0. Do not leave any fields blank.) (b) Determine the transaction price for…arrow_forwardHeadland Corp. enters into a contract with a customer to build an apartment building for $995,600. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $145,500 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $48,500 each week that completion is delayed. Headland commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability August 1, 2018 70 % August 8, 2018 20 August 15, 2018 5 After August 15, 2018 5 (a) Determine the transaction price for the contract, assuming Headland is only able to estimate whether the building can be completed by August 1, 2018, or not (Headland estimates that there is a 70% chance that the building will be completed by August 1, 2018). (If answer is 0, please enter 0. Do not leave any fields blank.) Transaction Price $…arrow_forwardRomano Services provides room cleaning arrangements for hotels in Ohio. On April 1, Silvia Hotels & Resorts signed an agreement to outsource its room-cleaning functions to Romano. The contract specifies the service fee to be $15,000 per month, and all payments are to be made shortly after the end of each quarter. It also specifies that Romano will receive an additional quarterly bonus of $3,000 if, during that quarter, Silvia receives no more than five complaints from customers about room cleanliness. On April 1, based on historical experience, Romano estimated that there is a 75% chance that it will receive the quarterly bonus. On May 5, Romano learned that, during March, there were two complaints from customers related to room cleanliness. Based on this new information, Romano revised its estimate downward to 40% that it would be entitled to receive the quarterly bonus. On June 30, Silvia notified Romano that, for the quarter ended, there were four complaints associated with…arrow_forward
- 1. A contractor is constructing a project for which he will be paid in one lump sum upon satisfactory completion of the project. The contractor needs cash to finance the construction and opens a line of credit at their bank (the loan would be repaid at the end of the project). The construction project is expected to last 16 months, and the contractor expects to borrow $100,000 at the beginning of the first month, and at the end of each of the first six months, making a total borrowing of $700,000. The contractor then needs to borrow $250,000 per month at the end of month 7 through 16, for an additional $2,500,000. The owner agrees to pay the contractor the lump sum payment for the project at EOM 20, at which time the contractor will repay the bank. Interest on the contractors outstanding loan balance is 1.5% per month for the first 10 months and then 2% per month until EOM 20. Given this scenario, please answer the following questions. a. What is the minimum contract price for this…arrow_forwardIndigo Corp. enters into a contract with a customer to build an apartment building for $1,061,800. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $139,200 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $46,400 each week that completion is delayed. Indigo commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by August 1, 2021 August 8, 2021 August 15, 2021 After August 15, 2021 Transaction Price Probability 70 % Transaction Price $ 20 6 (a) Determine the transaction price for the contract, assuming Indigo is only able to estimate whether the building can be completed by August 1, 2021, or not (Indigo estimates that there is a 70% chance that the building will be completed by August 1, 2021). (If answer is O, please enter O. Do not leave any fields blank.) 4 (b) Determine the…arrow_forwardCulver Corp. enters into a contract with a customer to build an apartment building for $970,000. The customer hopes to rent apartments at the beginning of the school year and offers a performance bonus of $171,000 to be paid if the building is ready for rental beginning August 1, 2020. The bonus is reduced by $57,000 each week that completion is delayed. Culver commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability August 1, 2020 70 % August 8, 2020 20 August 15, 2020 5 After August 15, 2020 5 Determine the transaction price for this contract, assuming Culver is only able to estimate whether the building can be completed by August 1, 2020, or not. (Culver estimates that there is a 70% chance that the building will be completed by August 1, 2020.) Transaction price $…arrow_forward
- Clark Corp. enters into a contract with a customer to build an apartment building for $1,000,800. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $135,600 to be paid if the building is ready for rental beginning August 1, 2026. The bonus is reduced by $45,200 each week that completion is delayed. Clark commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by August 1, 2026 August 8, 2026 August 15, 2026 After August 15, 2026 Transaction price $ Probability Transaction price 70 % $ 20 (a) Determine the transaction price for the contract, assuming Clark is only able to estimate whether the building can be completed by August 1, 2026, or not (Clark estimates that there is a 70% chance that the building will be completed by August 1, 2026). 5 5 (b) Determine the transaction price for the contract, assuming Clark has limited information…arrow_forwardhelp mearrow_forwardTeal Corp. enters into a contract with a customer to build an apartment building for $1,031,300. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $144,300 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $48,100 each week that completion is delayed. Teal commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability August 1, 2021 70 % August 8, 2021 20 August 15, 2021 4 After August 15, 2021 6 (a) Determine the transaction price for the contract, assuming Teal is only able to estimate whether the building can be completed by August 1, 2021, or not (Teal estimates that there is a 70% chance that the building will be completed by August 1, 2021). (If answer is 0, please enter 0. Do not leave any fields blank.) Transaction Price $enter the…arrow_forward