Question:
••• 13.10 The S&OP team (see Problem 13.9) is considering two more mixed strategies. Using the data in Problem 13.9, compare plans C and D with plans A and B and make a recommendation.
► Plan C: Keep the current workforce steady at a level producing 1,300 units per month. Subcontract the remainder to meet demand. Assume that 300 units remaining from June are available in July.
► Plan D: Keep the current workforce at a level capable of producing 1,300 units per month. Permit a maximum of 20% overtime at a premium of $40 per unit. Assume that warehouse limitations permit no more than a 180-unit carryover from month to month. This plan means that any time inventories reach 180, the plant is kept idle. Idle time per unit is $60. Any additional needs are subcontracted at a cost of $60 per incremental unit.
Want to see the full answer?
Check out a sample textbook solutionChapter 13 Solutions
MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Sustainability and Supply Chain Management
- 3. Your independent oil and gas company is considering the purchase at time zero of a 100 % working interest in a property. If you elect to develop the lease for an 87.5% revenue interest, the following costs will be incurred: in time zero, the lease bonus cost is $100,00o, intangible drilling costs are estimated at $550,000 while tangible completion costs are estimated at $300,000. Operating costs are estimated to remain constant at $8.00 per barrel (includes production costs, severance taxes and ad-valorem taxes) in each of years 1, 2, 3 and 4. Oil prices are forecasted to be $50.00 per barrel in each of years 1, 2, 3, and 4. Production is summarized in the following table. The escalated dollar minimum rate of return is 12.0%. Use net present value analysis to determine if the acquisition and development of this lease is economically viable: (a) Before considering income taxes, (b) Assuming income tax rate of 30%. (Expense 100% of intangible drilling costs at the end of first year,…arrow_forwardTranscribed Image Text On hand: 35 Planning time fence: 10 Lot size: 200 Demand time fence: 2 Period 2 4 6. 7 9. 10 11 12 Forecast 30 40 40 50 40 40 30 40 40 50 40 40 Customer Orders 31 35 29 21 17 14 33 11 5 2 Projected Available Available to Promise MPS 200 200 3. a. Given the following master schedule, fill in the projected available and availableto promise rows: b. A customer wants an order of 100 in period 4. What can you tell him?c. The customer from part (b) cancels his request, but then says he wants 120 in period 5.What do you tell him now?d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?e. What action (if any) should be taken in period 11? Why is it okay to take theaction? I only need question D and E answeredarrow_forwardExplain AGGREGATE PLANNING TECHNIQUES?arrow_forward
- D Question 1 Capacity Planning Using Oversli Factors does not consider historical percentages at the work centers when computing capacity needs. Ⓒue False Question 2 In aggregate planning, the amount of overtime and the size of the work force are both adjustable elements of capacity. Othe Falsearrow_forwardQuestion 4.4 Montreal Hardware Co. is making a make-or-buy decision. The market feedback shows that the optimal price for this item is $10 each. If the item is outsourced to Laval Hardware Co, there is virtually no cost other than the $6 per unit that they would pay Laval Hardware Co. Internally, they have two choices. Process A requires an investment of $120,000 for design and equipment, but it results in a $4 per unit cost. Process B requires only a $100,000 investment, but its per unit cost is $5. Regardless of whether the item is subcontracted or produced internally, there is a 50% chance that they will sell 50,000 units, and a 50% chance that they will sell 100,000 units. Draw the decision tree appropriate to the alternatives and outcomes stated. Using the decision tree and EMV, what is their best choice?arrow_forwardQUESTION TWO An aggregate plan is to be developed for the forecast of demand covering nine periods shown in Table below. Other relevant production and cost information is also provided. Find the cost associated with an aggregate plan that involves varying the size of the work force in order to have a production rate that matches demand. Note: Since this plan does not allow for any inventory build-up, a decision has been made to carry 10 units of safety stock, but no overtime or subcontract labour is used. Table showing Demand, production, and cost information Month Jan. Feb. Mar. April May June July Aug. Sept. Total Forecast 40 25 30 60 40 55 30 50 30 360 Production information Cost information Current number of workers Worker time/month Time to produce one unit 10 Hiring cost K600/employee 160 hrs Layoff cost K500/employee 40 hrs Regular time cost K30/hr Individual worker output Overtime cost K45/hr (160 hr/month/40 hr/unit) Subcontract labour K50/hr 4 units cost Safety stock of…arrow_forward
- Question 4 An alternative will have fixed costs of $10,000 per month, variable costs of $50 per unit, and revenue of $70 per unit. The break-even point volume is:arrow_forwardWhat is aggregate planning?arrow_forwardProblem 3 Workspace Back Hint: Exponential Smoothing: The company has accumulated the demand data, shown below, for its computers, from which it wants to develop exponential smoothing forecast for period 13 a equal to 0.50. Month Demand 37 40 3. 41 37 5 45 6. 50 43 8. 47 9. 56 10 52 11 55 12 54 13arrow_forward
- QUESTION THREE The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to Prepare a master schedule by completing the table below for the given information: schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows: Weeks Forecast 1 2 3 4 Use a production lot size of 75 units and beginning inventory is 55. 3 Week Customer orders (committed) Projected on-hand inventory MPS Available-to-promise inventory (uncommitted) 1 Customer Orders 2 52 35 20 12 4 5 6 7 8arrow_forwardWeek 4 6 7 Gross req. 60 20 150 Item# What is needed# Quantity needed A B 1 A C 2 B C 1 Item# On hand (beginning) inventory# Lot sizing# Lead time A 35 L4L 1 B 65 30 1 C 110 L4L 1 The three tables above shows the master production schedule and the bill of materials of part A, and the inventory records of all the parts. There are no scheduled receipts. Given this information, what is the planned order receipt of part C in Week 6?arrow_forwardQ4 Lab2 Subject: Production And operation Mnagement please answer ASAParrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.