Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand
John’s job is to develop an aggregate plan. The three initial options he wants to evaluate are:
♦ Plan A: a strategy that hires and fires personnel as necessary to meet the forecast.
♦ Plan B: a level strategy.
♦ Plan C: a level strategy that produces 1,200 cases per quarter and meets the forecast demand with inventory and sub-contracting.
a) Which strategy is the lowest-cost plan?
b) If you are John’s boss, the VP for operations, which plan do you implement and why?
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Chapter 13 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- Manager T. C. Downs of Plum Engines, a producer of lawn mowers and leaf blowers, must develop an aggregate plan given the forecast for engine demand shown in the table. The department has a regular output capacity of 135 engines per month. Regular output has a cost of $60 per engine. The beginning inventory is zero engines. Overtime has a cost of $100 per engine. a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Regular production can be less than regular capacity. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required.) b. Compare the costs to a level plan that uses inventory to absorb fluctuations. Inventory carrying cost is $2 per engine per month. Backlog cost is $120 per engine per month. There should not be a backlog in the last month. Set regular production equal to the monthly average of total forecasted demand. Assume that using overtime is not an option. (Negative amounts…arrow_forwardSoutheast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: Click the icon to view the demand forecast. E Click the icon to view the cost data. John's job is to develop an aggregate plan. The three initial options he wants to evaluate are: • Plan A: a strategy that hires and fires personnel as necessary to meet the forecast. • Plan B: a level strategy. • Plan C: a level strategy that produces 1,000 cases per quarter and meets the forecast demand with inventory and subcontracting. a) Which strategy is the lowest-cost plan? Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole numbers). Hiring and Layoff Plan Layoff (Units) Hire Quarter Forecast Production Inits) 1,300 1 1,700 Costs/Other Data Previous quarter's output = 1,300 cases Beginning inventory = 0 cases Stockout cost of backorders = $140 per case Inventory holding cost = $45 per…arrow_forward1.Describe the overall frameworks for resource planning in both goods-producing and service-providing organizations. 2.Explain options for aggregate planning 3.Explain the three basic strategies for aggregate planning.arrow_forward
- 1. Develop an aggregate plan for the following forecast Period 3 4 5 6 7 Total 1 2 8 Forecast 190 230 260 280 210 170 160 260 180 1,940 There are 20 workers who can produce 10 units per period at a cost of P6.00 per unit. There is no beginning invetory and the cost of carrying inventory is P5.00 per unit per period. Backlog cost is P10.00 per unit per period. Will the present workforce able to produce the forecast? b. What is the total cost of the plan? a.arrow_forwardSoutheast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: demand forecast. Quarter Forecast 1 1,900 2 1,200 3 1,600 4 800 Costs/Other Data Previous quarter's output=1,200 cases Beginning inventory=0 cases Stockout cost of backorders=$160 per case Inventory holding cost=$40 per case at end of quarter Hiring employees=$35 per case Terminating employees=$80 per case Subcontracting cost=$65 per case Unit cost on regular time=$30 per case Overtime cost=$20 extra per case Capacity on regular time=1,900 cases per quarter John's job is to develop an aggregate plan. The three initial options he wants to evaluate are: • Plan A: a strategy that hires and fires personnel as necessary to meet the forecast. • Plan B: a level strategy. • Plan C: a level strategy that…arrow_forward7-3. Nowjuice, Inc., produces Shakewell fruit juice. A planner has developed an aggregate forecast for demand (in cases) for the next eight months. month Apr forecast 4500 May 4400 Jun 6200 Jul 6400 Aug 5800 Sep 6600 Oct 7200 Nov 6900 Use the following information to develop aggregate plans. Regular production cost: $10.00 per case Regular production capacity: 5,000 cases Overtime production cost: $16 per case Subcontracting cost: $20 per case Holding cost: $1 per case per month Beginning inventory: 0 Develop an aggregate plan using each of the following guidelines and compute the total cost for each plan. Which plan has the lowest total cost? (a) Use level production of 5,000 case per month. Supplement using overtime as needed (b) Use a combination of overtime (500 cases per month for the first five months), inventory, and subcontracting (500 cases per month from September to November, if necessary) to handle variations in demand. Note that suitable amounts of overtime for the last…arrow_forward
- The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: alculator DEPREFERESSESES Cara be Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $65 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs Evaluate the following plan. This exercise contains only Plan E. Plan E: Keep the current workforce, which is producing 1,600 units per month, and subcontract to meet the rest of the demand. Subcontract cost is $75 per unit. mummill M Pla $100433443 January February March April MESS Month 0 December 1 January 2 February 3 March 4 April 5 May 6 June 7 July 8 August Ask my instructor 1,400 1,600 1,800 1,800 Demand 1.400 1,600 1,800 1,800 2,200 2,100 1,800 1.400 May June July August Production (Units) 1,600 1,600 1,600 1,600 1,600 1,600 1,600 1,600 2,200 2.100 1.800 1,400 S Plan E Subcontract…arrow_forward. Manager T. C. Downs of Plum Engines, a producer of lawn mowers and leaf blowers, must developan aggregate plan given the forecast for engine demand shown in the table. The department has aregular output capacity of 130 engines per month. Regular output has a cost of $60 per engine. Thebeginning inventory is zero engines. Overtime has a cost of $90 per engine.a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Regularproduction can be less than regular capacity. b. Compare the costs to a level plan that uses inventory to absorb fluctuations. Inventory carryingcost is $2 per engine per month. Backlog cost is $90 per engine per month. There should not bea backlog in the last month.MONTH1 2 3 4 5 6 7 8 TotalForecast 120 135 140 120 125 125 140 135 1,040arrow_forward2.15 The opening backlog is 900 units. Forecast demand is shown in the following. Calculate the weekly production for level production if the backlog is to be reduced to 200 units. Week 1 2 3 4 5 6 Total Forecast Demand 600 700 700 700 600 500 Planned Production Projected 900 Backlogarrow_forward
- Table below provides the demand forecast and production day information for an aggregate plan. Assume that no back orders are allowed in this case. Month January February March April May June Demand Forecast 3,000 4,500 3,400 2,500 4,000 3,200 Production Days 22 18 21 21 22 20 The costing information that is used to evaluate the total cost of each plan is as follows:• Inventory carrying cost: $4 per unit per month• Subcontracting cost per unit: $15 per unit• Working hours: 8 hours per day• Average pay rate: $12 per hour ($96 per day per worker)• Labour-hours to produce a unit: 2 hours per unit• Cost of increasing daily production rate (hiring and training): $300 per unit• Cost of decreasing daily production rate (layoffs): $700 per unitUse these information to formulate an aggregate plan. The firm would like to use level strategy: constant workforce for the aggregate planning. The firm chooses the average demand of the…arrow_forwardThe forecast demand for fudge for the next four months is 120, 160, 20, and 60 pounds. a. What is the recommended production rate if a level strategy is adopted with no backorders or stock outs? b. What is the ending inventory for Month 4 under this plan? c. What is the level production rate with no ending inventory in month 4.arrow_forwardA Pizza Company has a demand forecast for the next 12 months that is shown in Table 1 The current workforce of 100 staff can produce 1500 cases of pizzas per month. (a) Prepare a production plan that keeps the output level. How much warehouse space would the company need for this plan? (b) Prepare a demand chase plan. What implications would this have for staffing levels, assuming that the maximum amount of overtime would result in production levels of only 10 per cent greater than normal working hours? Table 1 demand forecast Month Demand (cases per month) January 600 February 800 March 1000 April 1500 May 2000 June 1700 July…arrow_forward