Operations Management In The Supply Chain Decisions And Cases 7th
7th Edition
ISBN: 9781259718779
Author: Roger G Schroeder And Susan Meyer Goldstein
Publisher: McGraw Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 13, Problem 4P
A plant start-up is based on the following network:
Activity | Immediate Predecessor | Activity Time |
A | – | 4 |
B | – | 8 |
C | – | 3 |
D | A | 3 |
E | A | 6 |
F | C | 5 |
G | B, D | 6 |
- a. Draw a network for this project.
- b. What is the project completion time?
- c. Identify the critical path
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A plant start-up is based on the following network :a. Draw a network for this project.b. What is the project completion time?c. Identify the critical path.
A project has these activities, precedence relationships, and activity durations:
Activity Immediate Predecessor Activity Activity Duration (Week)a * 3b * 4c * 3d c 12e b 5f a 7g e,f 3
a. Draw a CPM network for the project.
b. Provide an overview for the project by computing the duration for each path.
c. What is the critical path? What is the project's estimated duration?
The following information is known about a project:-
Activity
Activity time (Weeks)
Immediate Predecessor(s)
A
3
-
B
11
-
C
7
A
D
13
B, C
E
10
B
F
6
D
G
5
E
H
8
F, G
a) Draw the network diagram for this project
b) Calculate for the slack time
c) Find the critical path
d) When is the project completion time
Chapter 13 Solutions
Operations Management In The Supply Chain Decisions And Cases 7th
Ch. 13 - How, precisely, does project scheduling differ...Ch. 13 - How would you, after the fact, audit a project to...Ch. 13 - Prob. 3DQCh. 13 - Contrast and compare CPM and PERT as...Ch. 13 - Define the terms critical path, ES, and LF.Ch. 13 - What is the management significance of finding the...Ch. 13 - Prob. 7DQCh. 13 - What is meant by the need to make trade-offs...Ch. 13 - Why are a forward pass and a backward pass needed...Ch. 13 - What is the definition of the earliest and latest...
Ch. 13 - A public accounting firm requires the following...Ch. 13 - The following activities are required in starting...Ch. 13 - A construction project has the following network...Ch. 13 - A plant start-up is based on the following...Ch. 13 - An entrepreneur is starting a new business. The...Ch. 13 - Prob. 6PCh. 13 - Construction of a building is based on the...Ch. 13 - The professor from problem 6 is considering...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A project has been defined to contain the following list of activities along with their required times for completion. activity No activity nickname Time(week) predecessor (result needed before start) 1 A 3 2 B 2 1 3 C 2 2 4 D 6 2 5 E 3 3 6 F 2 3,4 7 G 4 5,6 Calculate the earliest expected completion time with middle steps. List all nodes the critical path.arrow_forwardPaul Silver, owner of Sculptures International, just initiateda new art project. The following data are available for theproject:Activity Activity Time (days) Immediate Predecessor(s)A 4 —B 1 —C 3 AD 2 BE 3 C, Da. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardThe following represents a project with known activity times. All times are in weeks.Activity ImmediatePredecessor TimeA - 4B - 3C - 1D B 2E A 3F C, E 5G D 3H F 2I G, H 3J I 6K I 4L J 21) Create a CPM Network. 2) What is the total project time? 3) What activities are on the critical path?4) Compute the slack time for all non-critical activities. 5) What is the latest possible start time for activity D? Please show all work in excel and how you did it, Thank you!arrow_forward
- The following information concerns a project to raise moneyfor the Kids Against Crime Foundation:Activity Activity Time (days) Immediate Predecessor(s)A 10 —B 11 —C 9 A, BD 5 A, BE 8 A, BF 13 C, EG 5 C, DH 10 GI 6 F, GJ 9 E, HK 11 I, Ja. Draw the network diagram for this project.b. Determine the critical path and project completion time.arrow_forwardThe following information is known about a project toupgrade a point-of-sale system at Kids and Tots Apparel.Activity Activity Time (days) Immediate Predecessor(s)A 7 —B 2 A C 4 AD 4 B, CE 4 DF 3 EG 5 Ea. Draw the network diagram for this project.b. Determine the critical path and project duration.c. Calculate the slack for each activity.arrow_forwardGiven the construction activities below, develop the construction schedule (in days) that includes Early Start, Early Finish, Late Start, Late Finish, and Float of each activity. Indicate the critical path. Activity: Precedency: Days: A --- 4 B A 9 C A 11 D B 5 E B 3 F C 7 G D,F 7 H E,G 2 K H 1arrow_forward
- Given the following information, a. Draw a project network. b. Complete the forward and backward pass, compute activity slack, and identify the critical path. c. How sensitive is the network schedule? Briefly justify your answer? d. Which activities have free slack? Activity Predecessor Duration (days) A None 10 B None 20 C A 10 D A 30 E B 10 F C 30 G C, D 20 H D, E 10 I F, G, H 20arrow_forwardA clinic start-up is based on the following network: Activity ImmediatePredecessor ActivityTime A – 4 B – 8 C – 3 D A 3 E A 6 F C 5 G B, D 6 Draw the network and answer the following questions. a. What is the project completion time?arrow_forwardTo complete the problem the following is necessary. 1) project network diagram (AON), 2) table that shows ES, EF, LS, LF, and Slack for each activity, 3) How long will the project take to be completed?, 4) Which activities are critical? Immediate Time Activity Predecessors (weeks) A none 8 B A 2 C A 3 D A 60 E B 60 F C 2 G D 2 H…arrow_forward
- A public accounting firm requires the following activities a. Draw a network for this project.b. Make a forward pass and a backward pass to determine ES, LS, EF, and LF.c. What are the critical path and the project completion time?d. If the project completion must be reduced by twodays, which activities might be affected?arrow_forwardHoff & Catherine Building company has plans to build a City Centre for the Government. The stages of the project are depicted in the table below: Activity Immediate Predecessor Duration (weeks) Remarks A - 2 B A 7 C B 5 D C 6 E C 4 F E 10 G D 7 H E, G 12 I C 7 J F, I 9 K J 4 L J 5 M H 5 N K,L 10 Calculate the earliest start, earliest finish, latest start, latest finish and slack time for each activity. Calculate the critical path How long does it take to complete the project assuming no delays?arrow_forwardMemorial College is considering building a new multipurpose athletic complex on campus. The following activities would have to be undertaken before construction can begin. Activity Description ImmediatePredecessor Time(weeks) A Survey building site 7 B Develop initial design 10 C Obtain board approval A, B 13 D Select architect C 3 E Establish budget C 5 F Finalize design D, E 14 G Obtain financing E 11 H Hire contractor F, G 9 (a) Draw a project network. (b) Identify the critical path. (c) Develop the activity schedule for the project. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F G H (d) What is the expected completion time for the project? The expected completion time is weeksarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY