Chapter 13, Problem 52AP
Summary Introduction
Interpretation: Probability that the lights would burn from the beginning of Christmas Eve (Dec24) to end of New Year's Day (Jan 1) without failure
Concept Introduction: Poisson distribution is the probability distribution of discrete random variable series in which frequency of outcomes is calculated in a given period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A collection of 30 Christmas tree lights are arranged in a pure series circuit; that is, ifone of the lights burns out, then the entire string goes out. Suppose that each light failscompletely at random at a rate of one failure every year. What is the probability that thelights will burn from the beginning of Christmas Eve (December 24) to the end of NewYear’s Day (January 1) without failure?
Six thousand light bulbs light a large hotel and casino marquee. Each bulb fails completely at random, and each has an average lifetime of 3,280 hours. Assuming that the marquee stays lit continuously and bulbs that burn out are replaced immediately, how many replacements must be made each year on the average?
A design engineer is considering the number of levels of redundancy to buildinto a particular circuit. The circuit will be part of a sensitive piece of equipmentwith cost estimated at $500 per failure. Each additional level of redundancy costs$100. If each component fails at random at a rate of one failure every five years,what level of redundancy most closely equates the cost of the design with the expected failure cost of the equipment over its 10-year life cycle?
Chapter 13 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
Ch. 13.1 - Prob. 3PCh. 13.1 - Prob. 4PCh. 13.1 - Prob. 5PCh. 13.1 - Prob. 6PCh. 13.2 - Prob. 7PCh. 13.2 - Prob. 9PCh. 13.3 - Prob. 13PCh. 13.3 - Prob. 14PCh. 13.4 - Prob. 15PCh. 13.4 - Prob. 16P
Ch. 13.4 - Prob. 17PCh. 13.4 - Prob. 18PCh. 13.4 - Prob. 19PCh. 13.4 - Prob. 20PCh. 13.6 - Prob. 21PCh. 13.6 - Prob. 22PCh. 13.6 - Prob. 23PCh. 13.6 - Prob. 24PCh. 13.6 - Prob. 25PCh. 13.7 - Prob. 26PCh. 13.7 - Prob. 27PCh. 13.7 - Prob. 28PCh. 13.7 - Prob. 30PCh. 13.7 - Prob. 31PCh. 13.7 - Prob. 32PCh. 13.7 - Prob. 33PCh. 13.7 - Prob. 34PCh. 13.8 - Prob. 35PCh. 13.8 - Prob. 36PCh. 13.8 - Prob. 37PCh. 13.8 - Prob. 38PCh. 13.8 - Prob. 39PCh. 13.8 - Prob. 40PCh. 13.8 - Prob. 41PCh. 13 - Prob. 42APCh. 13 - Prob. 43APCh. 13 - Prob. 44APCh. 13 - Prob. 45APCh. 13 - Prob. 46APCh. 13 - Prob. 48APCh. 13 - Prob. 49APCh. 13 - Prob. 51APCh. 13 - Prob. 52APCh. 13 - Prob. 53AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A system consists of three identical components. In order for the system to perform as intended, all of the components must perform. Each has the same probability of performance. If the system is to have a .92 probability of performing, what is the minimum probability of performing needed byeach of the individual components?arrow_forwardThe length of time between breakdowns of an essential piece of equipment is important in the decision of the use of auxiliary equipment. An engineer thinks that the best “model” for time between breakdowns of a generator is the exponential distribution with a mean of 15 days. If the generator has just broken down, what is the probability that it will break down in the next 12 to 24 days?arrow_forwardJankord Jewelers permits the return of their diamond wedding rings, provided the return occurs within two weeks. Typically, 20 percent are returned. If nine rings are sold today, what is the probability that fewer than four will be returned? A- 0.914 B- 0.962 C- 0.923 D- 0.935arrow_forward
- A product engineer has developed the following equation for the cost of a system component: C = (10P)2, where C is the cost in dollars and P is the probability that the component will operate as expected. The system is composed of 3 identical components, all of which must operate for the system to operate. The engineer can spend $254 for the 3 components. What is the largest component probability that can be achieved? (Do not round your intermediate calculations. Round your final answer to 4 decimal places.) Probability 0.8466arrow_forwardA product engineer has developed the following equation for the cost of a system component: C = (10P)2, where is the cost in dollars and Pis the probability that the component will operate as expected. The system is composed of two identical components, both of which must operate for the system to operate. The engineer can spend $173 for the two components. To the nearest two decimal places, what is the largest component probability that can be achieved?arrow_forwardA Florida lottery machine and printer at Store #8302 operates 360 days a year. If the machine does not work and breaks down, it costs the Florida Lottery Commission $2,160 per day. If store employees are trained to perform local tests on the machine each day plus the costs of machine repairpersons, these preventive maintenance costs average $850 per day. If preventive maintenance is performed daily, the probability the equipment fails is zero. The probability of store lottery machine breakdown is as follows. Number of Lottery Machine Breakdowns per Day 0 1 1/3 Probability of a breakdown What are the economics of the situation? Do not round intermediate calculations. Round your answers to the nearest dollar. The expected cost of a breakdown per day is $ The Florida Lottery Commission saves $ by performing preventive maintenance daily. 2 1/3 1/3 per yeararrow_forward
- A product engineer has developed the following equation for the cost of a system component: C = (10P) 2, where C is the cost in dollars and P is the probability that the component will operate as expected. The system is composed of two identical components, both of which must operate forthe system to operate. The engineer can spend $173 for the two components. To the nearest two decimal places, what is the largest component probability that can be achieved?arrow_forwardZemansky’s sells tires with a pro rata warranty. The tires are warranted to deliver50,000 miles with the rebate based on the remaining tread on the tire. The tires failon the average after 35,000 miles of wear. Suppose the tires sell for $50 each withthe warranty. If failures occur completely at random, what would be a consistentprice for the tires if no warranty were offered?arrow_forwardHabard’s, a chain of hardware stores, sells a variety of tools and home repair items.One of their best wrenches sells for $5.50. Habard’s will include a three-year freereplacement warranty for an additional $1.50. The wrench is expected to be subject to heavy use and, based on past experience, will fail randomly at a rate of oneevery eight years. Is it worth purchasing the warranty?arrow_forward
- If events X and Y are mutually exclusive then A- P(X)P(Y) = 0 B- they are independent events C- their joint probability is zero D- P(X)P(Y) = P(X | Y)arrow_forwardTenTen Company manufactures video recorders. It is so certain of its quality control that it is offering a complete replacement warranty if the set fails within two years. Based upon compiled data, the company has a need that only 1% of its recorders fail during the first year and 5% fail during the second year. The warranty does not cover replaced recorders. a) Formulate this problem as a Markov chain and determine the transition matrix. b) Find the probability that the manufacturer will have to honor the warranty.arrow_forwardExample 13.4 A local manufacturer of copying equipment includes a repair warranty with each copier. Virtu- ally all of his equipment exhibit an increasing failure rate. Based on historical repair data, the failure rate for Model 25cc7 is accurately described by the function r(t) = 2.7786t'3, where t is measured in months of continuous operation. What is the probability that the time between two successive failures of this equipment exceeds two months of operation?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,