a)
To determine: The ordering plan and cost for lot for lot.
Introduction:
Lot for Lot:
The lot for lot method of requirements plan is the process where the planned order release will be equal to the net requirement of the period.
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the
b)
To determine: The ordering plan and cost for EOQ.
Introduction:
Economic order quantity (EOQ):
The economic order quantity is the number of units a firm must add to their stock while making each order. The notion of EOQ is to reduce the total cost of inventory of the firm.
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
c)
To determine: The ordering plan and cost for POQ.
Introduction:
Periodic order quantity (POQ):
The POQ is the standard quantity of units that will be ordered over a fixed period of time. This method is followed when the usage of raw materials is consistent and is predictable.
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
d)
To determine: The plan which has the lowest cost.
Want to see the full answer?
Check out a sample textbook solutionChapter 14 Solutions
Operations Management
- Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Assume lot-for- lot ordering. Below is information about the steppers and the quantity required for each parent. Item Lead Time On Hand Inventory Components Stepper 2 20 A(1), B(3), C(2) A 1 10 D(1), F(2) B 2 30 E(1), F(3) C 3 10 D(2), E(3) D 1 15 E 2 5 F 2 20 Develop a product structure diagram for Develop a net material requirements plan forarrow_forwardWhat information is needed to develop a make-to-order production plan? How does this differ from that needed for a make-to-stock plan?arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 9. Subscripts indicate quantity required for each parent. Assumelot-for-lot ordering. c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 2 3 4 5 6 7 8 9 (weeks) F Gross req Insert answer insert answer 2 On hand insert answer insert answer Net req insert answer insert answer Order receipt insert answer insert answer Order release insert answer insert answerarrow_forward
- Given the bill of material and the on-hand quantities below, compute the net requirements for each item. The gross requirement for A is 150 units. Summarize your solution in a table. Item On-Hand Inventory A 40 B 50 C 100 D 70 E 25arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 10. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. Item Lead Time On-Hand Inventory Components Stepper 2 10 A(2), B(2), C(1) A 1 10 D(1), F(2) B 2 20 E(1), F(3) C 3 10 D(2), E(3) D 2 15 E 2 5 F 2 20 c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 3 4 5 6 7 8 9 10 (weeks) F Gross req enter your response here enter your response here 2 On hand enter your response here enter your response here Net req enter your response here enter your response here Order…arrow_forwardDaily demand for an item is shown here. Assume a holdingcost of $0.50 per unit per day, a setup cost of $100 persetup, a lead time of one day and 70 units on hand. Deter-mine when a work order should be released for the itemand the size of the order using the L4L, EOQ, and POQ lotsizing techniques. Which technique produces the lowesttotal cost? Period 1 2 3 4 5 6 7 8 9 10Gross Requirement 50 30 25 35 40 50 35 45 70 75arrow_forward
- Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. Item Lead Time On-Hand Inventory Components Stepper 2 20 A(2), B(2), C(2) A 1 10 D(1), F(2) B 2 20 E(2), F(3) C 2 10 D(2), E(1) D 1 15 E 2 5 F 2 20 c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 1 2 3 4 5 6 7 8 (weeks) F Gross req 2 On hand Net req enter your response here enter your response here Order receipt enter your response here enter your…arrow_forwardA factory has just received an order for 100 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Item Lead Time (weeks) On Hand Inventory Scheduled receipts Order Policy Direct Components End item 2 30 lot for lot A(4), B(3), C(2) A 3 20 54 at week 3 lot for lot D(2) B 2 10 68 at week 4 lot for lot D(5) C 1 100 multiple of 60 D 1 20 min. of 500 Develop the material requirements plan (please print out an empty MRP table to work with), and determine what the "projected available balance" is for component D at week 8. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardMr. Waleed is running furniture manufacturing business. He required raw material on regular basis.He uses the best suitable methods of purchasing of material.He tried to used preparation of inventor budgets, perpetual inventory system, just-in- time, ABC analysis but none of the above suited to his business.Once he had to stop his production, when he was using Just-In- Time purchasing method. One day Mr.Waleed explain all the cost details to his cost accountant as follows: The normal usage was 50 Units.In case of low demand his minimum usage was only 25 units. During high demand time Mr. Waleed used to purchase 75 units.Mainly he required two types of raw material like Material 1 and Material 2, His reorder quantity for Martial 1 was 300 Units & For Material 2 was 500 Units.His cost accountant told him that they need 40 Units as average. Mr. Waleed was very good at planning, but in case of emergency he used to wait 1 day for material 1 and 2 days for material 2 to get…arrow_forward
- Product A is made from components B and C. Item B, inturn, is made from D and E. Item C also is an intermediateitem, made from F and H. Finally, intermediate item E ismade from H and G. Note that item H has two parents. Thefollowing are item lead times:a. What lead time (in weeks) is needed to respond to a cus-tomer order for product A, assuming no existing invento-ries or scheduled receipts?b. What is the customer response time if all purchased items(i.e., D, F, G, and H) are in inventory?c. If you are allowed to keep just one purchased item instock, which one would you choose?arrow_forwardProduct A is made from components B and C. Item B, inturn, is made from D and E. Item C also is an intermediateitem, made from F and H. Finally, intermediate item E ismade from H and G. Note that item H has two parents. Thefollowing are item lead times: a. What lead time (in weeks) is needed to respond to a cus-tomer order for product A, assuming no existing invento-ries or scheduled receipts?b. What is the customer response time if all purchased items(i.e., D, F, G, and H) are in inventory?c. If you are allowed to keep just one purchased item instock, which one would you choose?arrow_forward1. Which of the following is a type of inventory All of the above b. Work in Progress c. MRO d. Raw materialarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.