Textbook Question
Book Icon
Chapter 14, Problem 2.2VC

MRP at Wheeled Coach

Wheeled Coach, the world’s largest manufacturer of ambulances, builds thousands of different and constantly changing configurations of its products. The custom nature of its business means lots of options and special designs—and a potential scheduling and inventory nightmare. Wheeled Coach addressed such problems, and succeeded in solving a lot of them, with an MRP system (described in the Global Company Profile that opens this chapter). As with most MRP installations, however, solving one set of problems uncovers a new set.

One of the new issues that had to be addressed by plant manager Lynn Whalen was newly discovered excess inventory. Managers discovered a substantial amount of inventory that was not called for in any finished products. Excess Inventory was evident because of the new level of inventory accuracy required by the MRP system. The other reason was a new series of inventory reports generated by the IBM M A PICS MRP system purchased by Wheeled Coach. One of those reports indicates w here items are used and is known as the “Where Used” report. Interestingly, many inventory items were not called out on bills of material (BOMs) for any current products. In some cases, the reason some parts were in the stockroom remained a mystery.

The discovery of this excess inventory led to renewed efforts to ensure that the BOMs were accurate. With substantial work, BOM accuracy increased and the number of engineering change notices (ECNs) decreased. Similarly, purchase-order accuracy, with regard to both part numbers and quantities ordered, was improved. Additionally, receiving department and stockroom accuracy went up, all helping to maintain schedule, costs, and ultimately, shipping dates and quality.

Eventually, Lynn Whalen concluded that the residual amounts of excess inventory were the result, at least in part, of rapid changes in ambulance design and technology. Another source was customer changes made after specifications had been determined and materials ordered. This latter excess occurs because, even though Wheeled Coach’s own throughput time is only 17 days, many of the items that it purchases require much longer lead times.

Discussion Questions*

1. Why is accurate inventory such an important issue at Wheeled Coach?

2. Why does Wheeled Coach have excess inventory, and what kind of a plan would you suggest for dealing with it?

3. Be specific in your suggestions for reducing inventory and how to implement them.

*You may wish to view the video that accompanies this case before answering the questions.

Blurred answer
Students have asked these similar questions
Describe the similarities between MRP and DRP ?
Explain the sometimes  difficulties occurs with the MRP system ?
Explain the Process of MRP and its various steps?

Chapter 14 Solutions

OPERATIONS MANAGEMENT CUSTOM 12E >C<

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY