Chapter 14, Problem 24E

1.

To determine

Calculate the actual operating income for the period.

1.

Expert Solution
Check Mark

Explanation of Solution

Calculate the actual operating income for the period.

Actualoperatingincome=(ActualsalesrevenueActualvariablecostsActualfixedcosts)=($380,000$210,000$145,000)=$25,000

2.

To determine

Calculate the company’s master (static) budget operating income for the period.

2.

Expert Solution
Check Mark

Explanation of Solution

Calculate the company’s master (static) budget operating income for the period.

Master(static)budgetoperatingincome}=(BudgetedsalesBudgetedvariablecostsBudgetedfixedcosts)=$450,000$270,000$135,000=$45,000

3 (a) & 3 (b)

To determine

Calculate the total master (static) budget variance, in terms of operating income and identify whether the variance is favorable (F) or unfavorable (U).

3 (a) & 3 (b)

Expert Solution
Check Mark

Explanation of Solution

Calculate the company’s master (static) budget operating income for the period:

Totalmaster(static)budgetvariance=(ActualoperatingincomeMasterbudgetoperatingincome)=$25,000$45,000=$20,000U

Thus, the variance is unfavorable.

4 (a) and 4 (b).

To determine

Calculate the total flexible budget variance for the period and identify whether the variance is favorable or unfavorable.

4 (a) and 4 (b).

Expert Solution
Check Mark

Explanation of Solution

The first-level decomposition of the total master (static) budget variance in operating income is attained through the implementation of a flexible-budget (depending on actual sales volume for the period). In this situation, the flexible-budget operating income = $400,000$240,000$135,000 = $25,000 .

Calculate total flexible budget variance:

Total flexible budget variance=(ActualoperatingincomeFexiblebudgetoperatingincome)=$25,000$25,000=$0

Note 1: $400,000=$450,00045,000×40,000

Note 2: $240,000=$270,00045,000×40,000

4 (c) and 4 (d).

To determine

Calculate the sales volume variance and identify whether the variance is favorable or unfavorable.

4 (c) and 4 (d).

Expert Solution
Check Mark

Explanation of Solution

Calculate the sales volume variance and identify whether the variance is favorable or unfavorable.

Salesvolumevariance=(Flexible-budgetoperatingincomeMasterbudgetoperatingincome)=$25,000$45,000=$20,000U

Conclusion:

 Actual ResultsFlexible BudgetMaster budget
Unit sales40,00040,00045,000
Sales$380,000$400,000$450,000
Total variable expenses210,000240,000270,000
Contribution margin$170,000$160,000$180,000
Fixed expenses145,000135,000135,000
Operating income$25,000$25,000$45,000

Table (1)

Calculate total master (static) budget variance:

TotalMaster(Static)Budgetvariance}=MasterbudgetoperatingincomeActualoperatingincome=$45,000$25,000=$20,000U

Calculate flexible-budget variance:

Flexiblebudgetvariance=ActualresultsFlexiblebudget=$25,000$25,000=$0

Calculate sales volume variance:

Salesvolumevariance=(MasterbudgetoperatingincomeFlexiblebudgetoperatingincome)=$45,000$25,000=$20,000

5.

To determine

5.

Expert Solution
Check Mark

Explanation of Solution

  • The sales volume variance indicates the effect on operating profit of selling a different volume of sales associated to the budgeted volume reflected in the master budget. Likewise, the computation of the variance holds three other elements constant: “selling price per unit, variable cost per unit, and total fixed costs”.
  • It is to be noted that this variance could be explained with respect to contribution margin, in this context, the computation looks at the effect on contribution margin of selling an amount different from the sales volume shown in the master budget for the period.
  • The total flexible-budget variance indicates the composite impact on operating income of changes in three components: “selling price per unit, variable cost per unit, and total fixed costs:
  • Therefore, in computing the flexible-budget variance we “hold constant” sales volume. There is a zero flexible-budget variance, in this context.
  • Conversely, this does not indicate that there is “no variable cost flexible budget variance, no selling price variance or no fixed cost spending variance”. It just means that these three variances net to zero.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
What is Risk Management? | Risk Management process; Author: Educationleaves;https://www.youtube.com/watch?v=IP-E75FGFkU;License: Standard youtube license