![Operations Management: Sustainability and Supply Chain Management (12th Edition)](https://www.bartleby.com/isbn_cover_images/9780134130422/9780134130422_largeCoverImage.gif)
Operations Management: Sustainability and Supply Chain Management (12th Edition)
12th Edition
ISBN: 9780134130422
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 14, Problem 29P
Karl Knapps, Inc., has received the following orders:
The entire fabrication for these units is
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Coleman Rich, Ltd., has received the followingorders:
The entire fabrication for these units is scheduled on onemachine. There are 2,250 usable minutes in a week, and eachunit will take 65 minutes to complete. Develop a capacityplan, using lot splitting, for the 10-week time period
Coleman Rich, Ltd., has received the followingorders:Period 1 2 3 4 5 6 7 8 9 10Order size 60 30 10 40 70 10 40 30 40 0The entire fabrication for these units is scheduled on one machine.There are 2,250 usable minutes in a week, and each unit will take
65 minutes to complete. Develop a capacity plan, using lot split-ting, for the 10-week time period.
An assembly plant for the Blood Pressure RX, a portable blood pressure device, has
400
minutes available daily in the plant for the device, and the average demand is
80
units per day. Final assembly requires 6 separate tasks. Information concerning these tasks is given in the following table.
Task
Performance Time (minutes)
Task Must Follow Task Listed Below
A
4
-
B
1
-
C
1
A, B
D
3
C
E
4
D
F
2
E
b) Given the demand, what is the cycle time for this operation?
The cycle time for this operation is
enter your response here
minutes/unit (enter your response as a whole number).
c) What is the theoretical minimum number of workstations?
The theoretical minimum number of workstations is
enter your response here
stations (enter your response as a whole number and, if your unrounded answer includes decimal values,…
Chapter 14 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...Ch. 14 - What functions of the firm affect an MRP system?...
Ch. 14 - Prob. 11DQCh. 14 - Identify five specific requirements of an...Ch. 14 - What are the typical benefits of ERP?Ch. 14 - What are the distinctions between MRP, DRP, and...Ch. 14 - As an approach to inventory management, how does...Ch. 14 - What are the disadvantages of ERP?Ch. 14 - Use the Web or other sources to: a. Find stories...Ch. 14 - Prob. 18DQCh. 14 - Use the Web or other sources to identify what an...Ch. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Using the information in Problem 14.3, construct a...Ch. 14 - Using the information in Problem 14.3, construct a...Ch. 14 - Refer again to Problems 14.3 and 14.4. In addition...Ch. 14 - Refer again to Problems 14.3 and 14.5. In addition...Ch. 14 - a. Given the product structure and master...Ch. 14 - Prob. 11PCh. 14 - Based on the data in Figure 14.13, complete a net...Ch. 14 - Prob. 13PCh. 14 - A part structure, lead time (weeks), and on-hand...Ch. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Data Table for Problems 14.17 through 14.20 14.17...Ch. 14 - Develop an EOQ solution and calculate total...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - Prob. 26PCh. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Karl Knapps, Inc., has received the following...Ch. 14 - Coleman Rich, Ltd., has received the following...Ch. 14 - Prob. 31PCh. 14 - Using the data for the coffee table in Problem...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The ClickClock corporation produces clocks with six stations. Each station is manned by a human worker, who do the following tasks: These workers get paid $ 10 an hour. Ignore any Station Task Sequence Processing Time (secs) Task Heat-stake lens to bezel Inspect bezel Clean switch holes Install set switch in bezel Total time for A Check switch travel Clean inside bezel Install module in bezel Total time for B Install battery clip in module Heat-stake battery clip in module Install two batteries in module Check switch 14 2 26 A 3 10 Preparation 1 4 18 68 23 B 6 12 Preparation 2 7 25 60 8 20 9 20 Battery 10 22 Installation 11 8. Total time for C 70 Install band Inspect band Total time for D Cosmetic inspection Final test D 12 45 Band 13 13 Installation 58 E 14 4 Packaging 15 71 Preparation Total time for E 75 Place watch and cuff in display box Place cover in display box base 16 20 17 14 Watch 18 Place owner's manual and box into tub 30 packaging Total time for F 64arrow_forwardDescribe the techniques to deal with bottleneck operations and some of those techniques that does not decrease throughput time ?arrow_forwardExplain the techniques to deal with bottleneck operations and some of those techniques that does not decrease throughput time ?arrow_forward
- Balance the assembly line using Ranked Positional Weight method using the data in Table 2 and determine the idle time at each station. The cycle time for meeting the demand is 38 minutes. тable 2 Time Immediate Operation (min) predecessor A B 3 C 10 А, В D 13 E 19 24 22 16arrow_forwardIf the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed?arrow_forwardGiven the following data, can an order for 20 for delivery in week 4 be accepted?Calculate the ATP using the following table. On hand = 50 units.arrow_forward
- For manufacturing electric bus Total labor hours, estimation process, and summary resultsarrow_forwardYou've just been assigned the job of setting up an electric fan assembly line with the following tasks and precedence relationships The assemtly line wil be nunning 8 hours per day and 5 days per week, The demand forast is 600 Items per week. Your goal is to minimie the numbor of workstations necesary to complete enough units to satisfy the demand forecast. What is the takt time (in minutes) needed to produce the required number of units? (Integer Answer, do not put anything other than numbers.) What is the theoretical minimum number of workstations that you will need (apply the round-up rule)? (Integer Answer, do not put anything other than numbers.)arrow_forwardTots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information: component plastic time space cost to manufacture cost to purchase front 2 11 2 7 11 seat/frame 3 7 2 6 10 rear 0.5 2.5 0.2 2 5 available 60000 180000 35000 Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost. Use Excel's Solver to obtain the optimal solution. How many of each component should be manufactured vs. purchased? What is the overall cost? What are the binding constraints? Upload a screenshot of the spreadsheet that you used…arrow_forward
- Manufacturing Company uses FIFO method of accumulating costs in a two-department process. Materials are introduced at the inception of the process except for a special material which is added in department 2 at 60% completion as to overhead. Inspection is done at the end of the process in both departments. Production data for Department 2 are given below: In process, beginning, (80% labor, 70% overhead)2,000 Transferred in 14,900 In process, ending (40% labor, 20% overhead) 3,000 Normal spoilage 200 Abnormal spoilage (found at 30% completion as to laborand 15% as to overhead due to internal failure) 400 Cost data for the month:In process beginning:Transferred in 15,020 Special materials 1,900 Direct labor 4,388 Overhead 11,044 Current costs:Transferred in 137,080 Special materials 14,030 Direct labor 46,000 Overhead 113,564 The cost of units transferred to finished goods is?The cost of spoilage charged to revenue is?arrow_forwardTots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information: component plastic time space cost to manufacture cost to purchase front 2 11 2 7 11 seat/frame 3 7 2 6 10 rear 0.5 2.5 0.2 2 5 available 60000 180000 35000 The company obviously does not have the resources available to manufacture everything needed for the completion of 15,000 tricycles so has gathered purchase information for each component. Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost. (state the objective function, decision…arrow_forwardHow does synchronous manufacturing differ from MRP with respect to scheduling?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY