Question
Chapter 14, Problem 29P
Summary Introduction
To determine: The capacity plan for the 10 week period.
Introduction:
Capacity plan:
Capacity plan is the plan determined by a firm to meet its changing demand requirements. The plan is formulated keeping in mind the maximum design capacity of the firm.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Coleman Rich, Ltd., has received the followingorders:
The entire fabrication for these units is scheduled on onemachine. There are 2,250 usable minutes in a week, and eachunit will take 65 minutes to complete. Develop a capacityplan, using lot splitting, for the 10-week time period
Coleman Rich, Ltd., has received the followingorders:Period 1 2 3 4 5 6 7 8 9 10Order size 60 30 10 40 70 10 40 30 40 0The entire fabrication for these units is scheduled on one machine.There are 2,250 usable minutes in a week, and each unit will take
65 minutes to complete. Develop a capacity plan, using lot split-ting, for the 10-week time period.
You have been asked to put together a capacity plan for a critical operation at the Surefoot Sandal Company. Your capacity measure is number of machines. Three products (men’s, women’s, and children’s sandals) are manufactured. The time standards (processing and setup), lot sizes, and demand forecasts are given in the following table. The firm operates two 8-hour shifts, 5 days per week, 50 weeks per year. Experience shows that a capacity cushion of 5 percent is sufficient.
Time Standards
Product
Processing (hr/pair)
Setup (hr/pair)
Lot Size (pairs/lot)
Demand Forecast (pairs/yr)
Men’s sandals
0.05
0.5
240
80,000
Women’s sandals
0.10
2.2
180
60,000
Children’s sandals
0.02
3.8
360
120,000
a. How many machines are needed? b. If the operation currently has two machines, what is the capacity gap?
Chapter 14 Solutions
OPERATIONS MANAGEMENT W/ MYLAB <C> 2018
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Describe the techniques to deal with bottleneck operations and some of those techniques that does not decrease throughput time ?arrow_forwardYou've just been assigned the job of setting up an electric fan assembly line with the following tasks and precedence relationships The assemtly line wil be nunning 8 hours per day and 5 days per week, The demand forast is 600 Items per week. Your goal is to minimie the numbor of workstations necesary to complete enough units to satisfy the demand forecast. What is the takt time (in minutes) needed to produce the required number of units? (Integer Answer, do not put anything other than numbers.) What is the theoretical minimum number of workstations that you will need (apply the round-up rule)? (Integer Answer, do not put anything other than numbers.)arrow_forwardA manufacturing plant has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three one of the three assembly operations (the assembly operations are ‘parallel’). Use diagram titled "q3" attached as an image a) What is the bottleneck operation? b) What is the throughput time for the overall system? c) If the firm operates 10 hours a day, 21 days a month, what is the monthly and yearly capacity of the manufacturing process? d) Supposed that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new bottleneck time of the system? e) What is the new throughput time if the second drilling machine is added? f) What is the new hourly capacity if the second drilling machine is added?arrow_forward
- Canine Kernels Company (CKC) manufactures two differenttypes of dog chew toys (A and B, sold in 1,000-count boxes)that are manufactured and assembled on three differentworkstations (W, X, and Y) using a small-batch process (seeFigure 5.12). Batch setup times are negligible. The flowchartdenotes the path each product follows through the manu-facturing process, and each product’s price, demand perweek, and processing times per unit are indicated as well.Purchased parts and raw materials consumed during pro-duction are represented by inverted triangles. CKC can makeand sell up to the limit of its demand per week; no penaltiesare incurred for not being able to meet all the demand. Eachworkstation is staffed by a worker who is dedicated to workon that workstation alone, and is paid $6 per hour. Totallabor costs per week are fixed. Variable overhead costs are$3,500/week. The plant operates one 8-hour shift per day, or40 hours/week. Which of the three workstations, W, X, or Y,has the highest…arrow_forwardWhen many processes are occurring simultaneously, what type of answer does the capacity analysis get?arrow_forwardExplain the term traditional assembly line operations? how are these operations efficient?arrow_forward
- Product A is assembled from one B and two C’s. Each itemrequires one or more operations, as indicated by the circles in the product structure diagram. Assume lead time is neg-ligible. From the information given: a. Develop a load profile chart for each of the three workcenters.b. Level the loads. Discuss possible consequences ofshifting work to other periods.arrow_forwardGiven the following master production schedule require-ments and bill of labor, determine the work load in each work center for January. Given a 40-hour week and four weeks per month, how many workers would need to be as-signed to each work center to meet demand? Assume part-time workers are available.arrow_forwardAn assembly line must be designed to produce 40 containers per hour. The following data give the necessary information Table 1 TASK IMMEDIATE PREDECESSOR TASK TIME (sec) A None 60 B A 12 C B 35 D A 55 E D 10 F E 50 G F, C 5 Draw the precedence diagram. Compute the cycle time (in seconds) to achieve the desired output rate. What is the theoretical minimum number of stations? Assign the tasks to the workstation? What is the efficiency of the line? Calculate the idle timearrow_forward
- Understand how variability can reduce capacityand how to restore capacity via standardized work,buffers, or elimination of sequential workarrow_forwardMonique Food Processing Company produces light snacks that can be heated in a microwave. The following steps are included in the process: Steps Description Capacity (Units/Hour) 1 Prepare food 200 2 Measure and place in plastic pouch 175 3 Prepare cardboard box 200 4 Insert pouch into box 300 5 Shrink-wrap box 200 What are the key factors that determine when to add capacity? Why would an organization want to reduce its capacity?arrow_forwardThe following diagram describes a manufacture process where products go through four parallel three-step processes and then merge into a single line for two final steps. Capacities of each step are shown on the diagram. A) What is the current capacity of the entire system? B) If the capacity of one operation could be increased in order to increase the output of the system, which operation should it be, and what amount of increase?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY