Compute the takt time for a system where the total time per shift is 480 minutes, there is one shift, and workers arc given two 15-minute breaks and 45 minutes for lunch. Daily demand is 300 units.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Compute the takt time for a system where the total time per shift is 420 minutes, there is one shift, and workers are given 3 11-minute breaks and 40 minutes for lunch. Daily demand is 347 units.
Given the following information, compute the takt time: Total time per shift is 480 minutesper day, and there are two shifts per day. There are two 20-minute rest breaks and a 30-minuteexcel lunch break per shift. Daily demand is 80 units.
A work cell is required to make 100 computerized diagnostic assemblies (for installation into hybrid automobiles) each day. The cell currently works an eight hour shift, of which seven hours is available for productive work. These assemblies require five operations, with times of 1.5, 1.8, 1.4, 1.5, and 1.9 minutes each. What is takt time for this cell? How many workers will be needed?
Chapter 14 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
Ch. 14.S - Prob. 1DRQCh. 14.S - Prob. 2DRQCh. 14.S - Prob. 3DRQCh. 14.S - Prob. 4DRQCh. 14.S - Prob. 5DRQCh. 14.S - Prob. 6DRQCh. 14.S - Prob. 7DRQCh. 14.S - Prob. 8DRQCh. 14.S - Prob. 9DRQCh. 14.S - Prob. 10DRQ
Ch. 14.S - The probability that equipment used in a hospital...Ch. 14.S - The frequency of breakdown of a machine that...Ch. 14.S - Prob. 3PCh. 14 - Prob. 1DRQCh. 14 - Prob. 2DRQCh. 14 - Prob. 3DRQCh. 14 - Prob. 4DRQCh. 14 - Prob. 5DRQCh. 14 - Prob. 6DRQCh. 14 - Prob. 7DRQCh. 14 - Contrast push and pull methods ofmovi.ttg goods...Ch. 14 - Prob. 9DRQCh. 14 - Prob. 10DRQCh. 14 - Prob. 1TSCh. 14 - Prob. 2TSCh. 14 - Prob. 3TSCh. 14 - Prob. 1CTECh. 14 - Prob. 2CTECh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Determine the number of cycles per day and the...Ch. 14 - Given this set of daily service operations, and...Ch. 14 - Determine the number of cycles per day and a...Ch. 14 - Compute the takt time for a system where the total...Ch. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - What might Stephanie determine as the best...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Georgetown Pizza makes its favorite pan pizzas every day with three working shifts around the clock. The current completely cooked pizza-making process has a fixed cost of $24,000, and a variable cost of $2.75 per pizza. The owner is considering a different process that can make pizzas in two ways: completely cooked and selling at $13.98 per unit, or partially cooked with a selling price of $12.98 per unit. This alternate process has a fixed cost of $28,000, but a lower variable cost (because much less energy is used in baking) of $2.25 per pizza. a. Determine the breakeven quantity between the current pizza-making process and the alternate process.arrow_forwardIf the firm operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell?arrow_forwardYou have been asked to put together a capacity plan for a critical operation at the Surefoot Sandal Company. Your capacity measure is number of machines. Three products (men’s, women’s, and children’s sandals) are manufactured. The time standards (processing and setup), lot sizes, and demand forecasts are given in the following table. The firm operates two 8-hour shifts, 5 days per week, 50 weeks per year. Experience shows that a capacity cushion of 5 percent is sufficient. Time Standards Product Processing (hr/pair) Setup (hr/pair) Lot Size (pairs/lot) Demand Forecast (pairs/yr) Men’s sandals 0.05 0.5 240 80,000 Women’s sandals 0.10 2.2 180 60,000 Children’s sandals 0.02 3.8 360 120,000 a. How many machines are needed? b. If the operation currently has two machines, what is the capacity gap?arrow_forward
- There is a canteen set up serving food (Breakfast, Lunch, Snacks-tea, and Dinner) to 500 students in a B school. It has a huge well-furnished dining hall and has a serving zone where students queue to pick up their eatables. The Institute director, during his regular Gemba walks in the canteen, has seen a lot of inefficiency in the related operational processes and needs a major improvement. (a)Provide one relatable and relevant example of five of the eight wastes under Lean systems which are likely to be witnessed in the canteen. (b)Recommend lean tools & techniques/system solutions to be employed for curbing each of those five wastes with a line on justification. (c) Suggest three key enablers and measures track the progress on lean in the canteen.arrow_forwardMr. K’s is a very popular hair salon. It offers high-quality hair styling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parenthesis): Activity 1: Welcome a guest and offer homemade herb tea. (10 minutes) Activity 2: Wash and condition hair. (10 minutes) Activity 3: Neck, shoulder, and back stress release massage. (10 minutes) Activity 4: Design the hairstyle and do the hair. (25 minutes) Activity 5: Check out the guest. (5 minutes) Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1. S2 does Activities 2 and Activity 3. S3 does Activities 4 and Activity 5. a) Which server is the bottleneck of the process ? b) What is the utilization of server 2 ? c) What is the…arrow_forwardApples are prepared in a process with two resources. The first resource has a capacity of 2.1 apples per minute. The capacity of the second resource is 4.4 apples per minute. Demand for this process is 1.6 apples per minute. What is the cycle process in seconds?arrow_forward
- Georgetown Pizza makes favorite pan pizzas every day with three working shifts around the clock. The current completely cooked pizza making process has a fixed cost of $24,000, and a variable cost of $2.75 per pizza. The owner is considering a different process that can make pizzas in two ways: completely cooked and selling at $13.98 per unit, or partially cooked with a selling price of $12.98 per unit. This alternate process has a fixed cost of $28,000, but a lower variable cost (because much less energy is used in baking) of $2.25 per pizzac. If the owner expects to get $390,000 as a half year profit, how many units of completely cook pizzas, should Georgetown sell a year using the current pizza making process? d. Determine the annual design capacity for Georgetown’s production if the completely cook pizzas can be produced at 120 units per hour.arrow_forwardA copy center in an office building prepares bound reports for two clients. The center makes multiple copies (the lot size) of each report. The processing time to run, collate, and bind each copy depends on, among other factors, the number of pages. The center operates 250 days per year, with one 8-hour shift. Management believes that a capacity cushion of 15 percent (beyond the allowance built into time standards) is best. It currently has three copy machines. Based on the following table of information, determine how many machines are needed at the copy center. Item Client X Client Y Annual demand forecast (copies) 2,000 6,000 Standard processing time (hour/copy) 0.5 0.7 Average lot size (copies per report) 20 30 Standard setup time (hours) 0.25 0.40arrow_forwardVikiki Furniture, Inc. produces all types of office furniture. The "Executive Secretary" is a sofa-bed that has been designed using ergonomics to provide comfort during long work hours. The sofa-bed sells for $138. There are 580 minutes available during the day, and the average daily demand has been 65 items. There are eight tasks: Task performance time (min) task must follow task listed A 4 -- B 7 -- C 6 A, B D 5 C E 6 D F 7 E G 8 E H 6 F, G Total 49 min What is the Cycle time for this operation?arrow_forward
- Problem 3: What is the takt time for a production system thatoperates one shift given the following information?total time per shift = 480 minutesCoffee breaks = 2 20 - minute breaks per shiftLunch break = 60 minutesdaily demand = 360 unitsarrow_forward1. Dolls are fabricated in a process with two resources. The first resource has a capacity of 1.5 dolls per hour. The capacity of the second resource is 0.99 dolls per hour. The first resource has 7 workers and the second resource has 9 workers. Demand for this process is 1.1 dolls per hour. Wages are $19 per hour. What is the cost of direct labor? ($) _____ per unitarrow_forwardIn order to produce 1000 units of X in a week? units X is scheduled weekly for Operation B (due to 5% scrap ratio)? units X is scheduled weekly for Operation A (due to 2% scrap ratio) Based on your answer in part a, find the number of machines required to produce 1000units of X per week.? The total time required to perform Operation B = ? minutes per week? The total time required to perform Operation A = ? minutes per weekH= Available Time in a week = minutes /weekThusFA = ?FB = ?Since both of the operations A and B are performed on the same machine? machines are requiredarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY