Question
Chapter 15, Problem 2P
Summary Introduction
To draw: The Gantt chart for the given information.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day
4.
Job
D
was scheduled to begin early on day
2
and take
7.5
days. As of now (the review point after day
4),
it is 2 days ahead of schedule.
Job
E
should begin on day
1
and take
4
days. It was on time.
Job
F
was to begin on day
2,
but maintenance forced a delay of
0.5
day.
The job should now take
5
full days. It is now on schedule.
Job
G
is a day behind schedule. It started at the beginning of day
2
and should require
7
days to complete.
Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines).
Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks.
Ron Satter field's excavation company uses bothGantt scheduling charts and Gantt load charts.a) Today, which is the end of day 7, Ron is reviewing the Ganttchart depicting these schedules:• Job # 151 was scheduled to begin on day 3 and to ta ke6 days. As of now, it is I day ahead of schedule.• Job# 177 was scheduled to begin on day J and take 4 days.It is currently on time.• Job #1 79 was scheduled to start on day 7 and take 2 days. Itactually got started on day 6 and is progressing according toplan.• Job #211 was scheduled to begin on day 5, but missingequipment delayed it until day 6. It is progressing asexpected and should take 3 days.• Job #215 was scheduled to begin on day 4 and take 5 days.It got sta rted on time but has since fallen behind 2 days.Draw the Gantt scheduling chart for the activities described.b) Ron now wants to use a Ga ntt load chart to see how muchwork is scheduled in each of his three work teams: Able,Baker, and Charlie. Five jobs constitute the current…
Using Johnson's rule for 2-machine scheduling, the sequence is:
Scheduled Order
Job
1
▼
B
C
E
F
A
D
Part 2
2
▼
F
C
A
D
B
E
Part 3
3
▼
A
B
D
F
C
E
Part 4
4
▼
E
D
C
B
F
A
Part 5
5
▼
F
C
D
A
E
B
Part 6
6
▼
D
C
F
B
E
A
Part 7
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =
enter your response here
hours (enter your response as a whole number).
...
Question content area right
Part 1
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
Job
Operation 1 (hours)
Operation 2 (hours)
A
4
8
B
10
5
C
3
11
D…
Chapter 15 Solutions
OPERATIONS MANAGEMENT W/MY OM LAB
Ch. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQCh. 15 - Prob. 10DQ
Ch. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Prob. 26PCh. 15 - Prob. 27PCh. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Prob. 2.3VCCh. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following table contains information regarding jobs that are to be scheduled through one machine: Job Processing Time (Days) Due date A 4 20 B 12 30 C 2 15 D 11 16 E 10 18 F 3 5 G 6 9 Qus 1: Find the FCFS Schedule? Qus 2: Find the SOT Schedule? Qus 3:Find the DDate Schedule? Qus 4: What are the mean flow time and average lateness for each of the schedule above? Qus 5: Which priority rule is appropriate for job scheduling? Justify your answer.arrow_forwardPlease answer all. how to avoid timewasting; why scheduling is important, how we should schedule; how to meet deadlines.arrow_forwardDe Law Construction has a gotten some construction jobs to build some starter housing units in a few areas. The building time for each housing unit to be completed as well as the date that each unit is to be completed is shown in the table below. Today is Day 471. Which of the sequences, EDD OR SPT should the company use to sequence the order in which they do the jobs, assuming that because of resource constraints it cannot do the jobs simultaneously? HOUSING UNIT Building Time (days) Due Date Marabella 39 Day 502 Tabaquite 23 Day 528 San Juan 30 Day 515 Mayaro 33 Day 498 D’Abadie 41 Day 535 Preysal 40 Day 510 Some time after starting the jobs according to the sequence you decided on, it was found that because of inclement weather the last three housing units in the sequence have been delayed. You now have to prioritise and decide in which order to expedite those three jobs, using the Critical Ratio model. It is now…arrow_forward
- Three jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A B 1 5 4 2 7 7 3 3 5 Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forwardUsing the FCFS rule for scheduling, the sequence is ▼ 1-3-2 3-1-2 1-2-3 2-1-3 2-3-1 3-2-1 . Part 2 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 3 Using Johnson's rule for 2-machine scheduling, the sequence is ▼ 3-1-2 1-2-3 2-1-3 3-2-1 2-3-1 1-3-2 . Part 4 For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 5 Of the two developed schedules, ▼ Johnson's the FCFS rule gets the schedule finished sooner. ... Question content area right Part 1 Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing…arrow_forwardAt the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the beginning of the day 1 (today, which is a work day). All of the jobs are due at various times today. Your job is to evaluate four common sequencing rules. JOB DUE (IN HOURS) DURATION (HOURS REQUIRED) A 8 (this job is due in 8 hours) 1.65 B 5.5 (this job is due in 5.5 hours) 1.20 C 4.5 (this job is due after lunch in 4.5 hours) 0.85 D 6 (this job is due in 6…arrow_forward
- uestion 2:ID:_________________________Three jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B. The processing times are: JobA1 2 35 7 3B4 7 5Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forwardFive jobs must be scheduled for batch processing on a mainframe computer system. The processing times and the promised times for each of the jobs are listedhere.Job 1 2 3 4 5Processing time 40 min 2.5 hr 20 min 4 hr 1.5 hrPromised time 11:00 A.M. 2:00 P.M. 2:00 P.M. 1:00 P.M. 4:00 P.M.Assume that the current time is 10:00 A.M.a. If the jobs are scheduled according to SPT, find the tardiness of each job and themean tardiness of all jobs.b. Repeat the calculation in part (a) for EDD schedulingarrow_forwardResource-limited scheduling: is used to develop the shortest schedule when the quantity of resources is fixed is used to minimize the fluctuations in requirements for resources keeps a project on budget keeps a project within its required completion time a & d above b & d abovearrow_forward
- Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 C 2 B 3 E 4 A 5 D 6 F For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = nothing hours (enter your response as a whole number).arrow_forwardAn assembly department has six jobs waiting to be processed. It is now time zero and all jobs are ready to begin. Job Processing Time Due Date A 5 12 B 7 18 C 8 6 D 3 10 E 9 22 F 12 17 Which scheduling will be better to use, EDD or SPT and why Suppose there is a new method called Earliest difference first that arranges the jobs based on the difference between due date and the processing time, would this method be better than the results of part (1)arrow_forwardActivities A, B, and C are started at Week 0 and are the immediatepredecessors for Activity J. If the earliest finish times for the threeactivities are Week 11, Week 15, and Week 10, respectively, then the earlieststart time for J will be A. Week 10B. Week 11C. Week 12D. Week 15arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY