eXcel The BOM for product A given below
Part | on Hand | Week of land Time |
A | 75 | 1 |
B | 150 | 2 |
C | 50 | 1 |
D | 100 | 2 |
Assume the master
- a. Develop a materials plan for this product.
- b. What actions should be taken immediately?
- c. Project the inventory ahead for each part.
- d. If you were suddenly notified that part D will take three weeks to get instead of two weeks, what actions would you take?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The BOM for product A is given below:Assume the master schedule calls for 200 units of product A in week 5 and 250 units in week 6. a. Develop a materials plan for this product. b. What actions should be taken immediately? c. Project the inventory ahead for each part. d. If you were suddenly notified that part D will take three weeks to get instead of two weeks, what actions would you take?
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
Item
End
B
C
D
E
F
G
H
LT (wk)
1
2
3
3
1
2
1
2
Amount on hand
0
10
10
25
12
30
5
0
a. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.) The latest week
Note:-
Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
Answer completely.
14.) A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure 14. From the information shown, generate:
a) An indented bell of material for product A.
b) Net requirements for each part to produce 10 As in week 8 using lot-for-lot.
Figure 14:
Chapter 15 Solutions
OPER MGMT IN SUPPLY CHAIN ACCESS CARD
Ch. 15.7 - Prob. 1OLCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - With regard to inventory management, discuss the...Ch. 15 - Prob. 4DQCh. 15 - How much safety stock should be carried in a MRP...Ch. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Describe how MRP? concepts could be used for the...Ch. 15 - How are MRP and ERP related?Ch. 15 - The following information is given for a...Ch. 15 - eXcel The Old Hickory Furniture Company...Ch. 15 - Product A consists of subassemblies B and C....Ch. 15 - eXcel The BOM for product A given below Part on...Ch. 15 - The master scheduler in the ABC Widget Company is...Ch. 15 - A firm makes a basic scissors consisting of three...Ch. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - A small toy robot is assembled from sis parts: a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 3 1 1 1 1 3 1 3 Amount on hand 0 9 10 24 10 33 4 0 a. If 17 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 15. What is the latest week that the order can be started and still be ready to ship on time? The latest week isarrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 15 G(2), B(2) K 3 20 H(4), B(2) B 2 25 J 3 34 G 3 3 H 2 0 Click here for the Excel Data File a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)arrow_forwardGiven the product structure, master productionschedule, and inventory status in Figure 14.13, and assuming therequirements for each BOM item is I:a) develop a gross requirements plan for Item C;b) develop a net requirements plan for Item C.arrow_forward
- An end item’s demand forecasts for the next 6 weeks are 30 units, followed by forecasts of 25 units for weeks 7 through 10. The current on-hand inventory is 60 units. The order policy is to produce in lots of 100. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 11, 0, 0, 9, 0, 0, and 0 units. The lead time is 2 weeks.a. Develop an MPS for this end item.b. The marketing department has received six orders for this item in the following sequence:Order 1 is for 40 units to be delivered in period 3Order 2 is for 60 units to be delivered in period 4Order 3 is for 70 units to be delivered in period 6Order 4 is for 40 units to be delivered in period 3Order 5 is for 20 units to be delivered in period 5Order 6 is for 115 units to be delivered in period 9Assuming that the prospective MPS you developed in part (a) does not change, which orders would you be able to accept based on the available to promise (ATP)?arrow_forwardAn end item’s demand forecasts for the next 10 weeks are 30, 30, 30, 30, 20, 20, 30, 30, 30, and 30 units. The current onhand inventory is 100 units. The order policy is to produce in lots of 75. The booked customer orders for the item, starting with week 1, are 15, 38, 7, 5, 0, 3, 10, 0, 0, and 0 units. The lead time is 2 weeks.a. Develop an MPS for this end item.b. The marketing department has received five orders for this item in the following sequence:Order 1 is for 20 units to be delivered in period 1Order 2 is for 75 units to be delivered in period 4Order 3 is for 90 units to be delivered in period 6Order 4 is for 75 units to be delivered in period 7Order 5 is for 90 units to be delivered in period 10Assuming that the prospective MPS you developed in part (a) does not change, which orders would you be able to accept based on the available to promise (ATP)?arrow_forwardThe BOM for product A is shown in Figure 11.40, and datafrom the inventory records are shown in Table 11.9. In theMPS for product A, the MPS start row has 100 units in week 3and 200 in week 6. Develop the material requirements planfor the next 6 weeks for items C, D, and E. a. Develop the material requirements plan for the next6 weeks for items C, D, and E.b. What specific managerial actions are required inweek 1?arrow_forward
- Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?arrow_forwardA partially completed inventory record for the motor sub-assembly is shown in Figure 11.39.a. Complete the last three rows of the record by using theL4L rule.b. Complete the last three rows of the record by using thePOQ rule with P = 2. c. Complete the last three rows of the record by using thePOQ rule with P = 2.d. If it costs the company $1 to hold a unit in inventory fromone week to the next, and the cost to release an order is$50, which of the lot sizing rules used above will providethe lowest inventory holding + order release cost?arrow_forwardThe following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent. Item Lead Time Amount onHand DirectComponents End item 1 - L(2), C(1), K(3) L 1 8 B(2), J(3) C 3 14 G(2), B(2) K 3 18 H(4), B(2) B 1 24 J 4 34 G 3 38 H 3 - a. This part of the question is not part of your Connect assignment.b. If 44 units of the end item are to be assembled, how many additional units of B are needed? (You don’t need to develop the MRP tables.)Additional units c. An order for 44 units of the end item is scheduled to be shipped at the start of week 8. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You don’t need to develop the MRP tables.)The latest weekarrow_forward
- The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amounton Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)Additional units b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.) The latest weekarrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks),and quantities on hand. Item Lead Time Amount on Hand Direct ComponentsEnd 1 — L(2), C(1), K(3)L 2 10 B(2), J(3)C 3 15 G(2), B(2)K 3 20 H(4), B(2)B 2 30J 3 30G 3 5H 2 —a. If 40 units of the end item are to be assembled, how many additional units of B are needed?(Hint: You don’t need to develop an MRP plan.)b. An order for the end item is scheduled to be shipped at the start of week 8. What is the latestweek that the order can be started and still be ready to ship on time? (Hint: You don’t need todevelop an MRP plan.)arrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amounton Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) b.An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY