Textbook Question
Chapter 15, Problem 9P
A small toy robot is assembled from sis parts: a body, a head, two arms, and two legs. The firm uses a one-level bill of materials to assemble this product. The number of parts on hand and the lead times (weeks) to obtain more parts are shown below. There are no parts on order.
On Hand | Lead Time | |
Body | 25 | 2 |
Head | 50 | 1 |
Arm | 60 | 2 |
Leg | 80 | 1 |
- a. Assume that an order for 200 robots is received now for delivery at the beginning of week 4 and that it takes one week to assemble the parts once they are all available. Construct a complete material? plan for the robots. What actions should be taken immediately to implement the plan?
- b. The customer has called and asked if he could receive a portion of the 200 robots as soon as possible. How many robots can be assembled and delivered to him ASAP, and when would they arrive? What are the implications of this action?
- c. c The supplier of heads has just sent an e-mail that said it will take two weeks to deliver the heads instead of one week. What effect will this have on your materials plan from part a?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent.
Item
Lead Time
Amount onHand
DirectComponents
End item
1
-
L(2), C(1), K(3)
L
2
14
B(2), J(3)
C
3
30
G(2), B(2)
K
1
25
H(4), B(2)
B
4
15
J
2
10
G
4
5
H
2
-
a. Not available in Connect.b. If 46 units of the end item are to be assembled, how many additional units of B are needed? (You don’t need to develop the MRP tables.)Additional units ____ c. An order for 46 units of the end item is scheduled to be shipped at the start of week 11. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You don’t need to develop the MRP tables.)The latest week ____
Refer to the bill of materials for product A shown in Figure 11.23. If there is no existing inventory and no scheduled receipts, how many units of items G, E, and D must be purchased to produce five units of end item A?
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.
Item
Lead Time
Amount
Direct Components
on Hand
End
1
0
L(2), C(1), K(3)
L
1
10
B(2), J(3)
C
2
14
G(2), B(2)
K
2
19
H(4), B(2)
B
1
34
J
2
25
G
2
7
H
3
0
a. If 43 units of the end item are to be assembled, how many additional units of B are needed?
b. An order for the end item is scheduled to be shipped at the start of week 9. What is the latest week that the order can be started and still be ready to ship on time?
Chapter 15 Solutions
Loose Leaf for Operations Management in the Supply Chain: Decisions and Cases 7e
Ch. 15.7 - Prob. 1OLCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - With regard to inventory management, discuss the...Ch. 15 - Prob. 4DQCh. 15 - How much safety stock should be carried in a MRP...Ch. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Describe how MRP? concepts could be used for the...Ch. 15 - How are MRP and ERP related?Ch. 15 - The following information is given for a...Ch. 15 - eXcel The Old Hickory Furniture Company...Ch. 15 - Product A consists of subassemblies B and C....Ch. 15 - eXcel The BOM for product A given below Part on...Ch. 15 - The master scheduler in the ABC Widget Company is...Ch. 15 - A firm makes a basic scissors consisting of three...Ch. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - A small toy robot is assembled from sis parts: a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent. Item Lead Time Amount onHand DirectComponents End item 1 - L(2), C(1), K(3) L 1 8 B(2), J(3) C 3 14 G(2), B(2) K 3 18 H(4), B(2) B 1 24 J 4 34 G 3 38 H 3 - a. This part of the question is not part of your Connect assignment.b. If 44 units of the end item are to be assembled, how many additional units of B are needed? (You don’t need to develop the MRP tables.)Additional units c. An order for 44 units of the end item is scheduled to be shipped at the start of week 8. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You don’t need to develop the MRP tables.)The latest weekarrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amounton Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 17 G(2), B(2) K 4 22 H(4), B(2) B 3 30 J 4 29 G 4 3 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)Additional units b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.) The latest weekarrow_forwardRefer to this product tree If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed?arrow_forward
- You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 300 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.) K(1) L(5) M(3) J Determine the number of units of each item required. Item K: Item L: Item M:arrow_forwardZen product wants to decide whether to make-or buy an accessory item for one of ther products. It is projected that this item will sell for 515 each If the item is outsourced, there is virtually no cost other than the $6 per unit that they would pay their supplier. Internally, they have two choices Process A requires an investment of $120,000 for design and equipment, but results in a $4 per unit cost. Process B requees only a $100,000 investment, but its per unit cost is $5. Regardless of whether the item is subcontracted or produced internally, there is a 50% chance that they will sell 0.000 units, and a 50% chance that they will sell 100,000 units Draw the decision tree approptiate to the alternatives and outcomes stated. Using decision trees and EMV, what is their best choice?arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 2 clamps and 1 housing. Each clamp has 1handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand. Part 3 b) Determine the gross quantities needed of each item if you are to assemble 150 brackets. Base: enter your response here units (enter your response as a whole number). Spring: enter your response here units (enter your response as a whole number). Clamp: enter your response here units (enter your response as a whole number). Housing: enter your response here units (enter your response as a whole number). Handle: enter your response here units (enter your response as a whole number). Casting: enter your response here units (enter your response as a whole number). Bearing: enter…arrow_forward
- The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amounton Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) b.An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)arrow_forwardHip Replacements, Inc., has a master production schedule forits newest model, as shown below, a setup cost of $50, a holdingcost per week of $2, beginning inventory of 0, and lead time of1 week. What are the costs of using lot-for-lot for this l0-weekperiod? WEEK 1 2 3 4 5 6 7 8 9 10Gross requirements 0 0 50 0 0 35 15 0 100 0Scheduled receiptsProjected on hand 0 0 0 0 0 0 0 0 0 00Net requirements 0 0 50 0 0 35 15 0 100Planned order receipts 50 35 15 100Planned order releases 50 35 15 100arrow_forwardFigure shows the BOMs for two products, A and B. Table 1 shows the MPS quantity start date for each one. Table 2 contains data from inventory records for items C, D, and E. There are no safety stock requirements for any of the items.a. Determine the material requirements plan for items C, D, and E for the next 8 weeks.b. What specific managerial actions are required in week 1?c. Suppose that a very important customer places an emergency order for a quantity of product A. To satisfy this order, a new MPS of 200 units of product A is now required in week 5. Determine the changes to the material requirements plan if this order is accepted and note any problems that you detect. MPS Quantity Start Dates Date Product 1 2 3 4 5 6 7 8 A 125 95 150 130 B 80 70 Inventory Record Data Item Data Category C D E Lot-sizing rule L4L POQ 1P = 32 FOQ = 800 Lead time 3 weeks 2 weeks 1 weeks Scheduled receipts 200 (week 2) None 800 (week 1) Beginning…arrow_forward
- A firm that produces electric golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times, and quantities on hand is shown in the following table. Use this information to do each of the following: a. Develop a material requirements plan that will provide 200 golf carts by week 8, assuming lot-for-lot ordering. (Excel)arrow_forwardProduct A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?arrow_forwardProduct A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day toassemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 A’s are needed by day 7?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY