A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Given the information shown, do the following:
a. Determine the processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each sequence, compute the average job tardiness, the average flow time, and the average number of jobs at the work center. The list is in FCFS order.
b. Using the results of your calculations in part a, show that the ratio of average flow time and the average number of jobs measures are equivalent for all four sequencing rules.
c. Determine the processing sequence that would result using the S/O rule.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Trending nowThis is a popular solution!
![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Given the following information on job times and due dates, determine the optimal processingsequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each method, find the average jobflow time and the average job tardiness. Jobs are listed in order of arrival.JobJob Time(hours)Due Date(hours)a 3.5 7b 2.0 6c 4.5 18d 5.0 22e 2.5 4f 6.0 20
Processing time for eight projects, displayed in the sequence they arrived.
Project
P1
P2
P3
P4
P5
P6
P7
P8
Processing time (hours)
3
1
1
2
9
6
1
1.50
2. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow rate of the projects?
Note: Round your answer to 2 decimal places.
3. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow time of the projects?
Note: Round your answer to 1 decimal place.
4. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average inventory of the projects?
Note: Use your rounded answers from Parts 2 and 3. Round your answer to 1 decimal place.
5. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow rate of the projects?
Note: Round your answer to 2 decimal places.
6. Given the projects displayed in table above, if SPT is used to sequence…
Given the following information on job times and due dates.
Job
Job Time(Hours)
Due Date(Hours)
a
3.5
7
b
2.0
6
c
4.5
18
d
5.0
22
e
2.5
4
f
6.0
20
a-1. Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio.
Sequence for First come, first served
Sequence for Shortest processing time
Sequence for Earliest due date
Sequence for Critical ratio
a-2. For each method, find the average job flow time and the average job tardiness. (Round your answers to 2 decimal places.)
First Come, FirstServed
Shortest ProcessingTime
Earliest Due Date
Critical Ratio
Average flow time
Average job tardiness
Chapter 16 Solutions
OPERATIONS MANAGEMENT LOOSELEAF W/ CONN
Ch. 16 - Why is scheduling fairly simple for repetitive...Ch. 16 - Prob. 2DRQCh. 16 - What are Gantt charts? How are they used in...Ch. 16 - Prob. 4DRQCh. 16 - Briefly describe each of these priority rules: a....Ch. 16 - Why are priority rules needed?Ch. 16 - What problems not generally found in manufacturing...Ch. 16 - Explain forward and backward schedulings and each...Ch. 16 - Prob. 9DRQCh. 16 - Prob. 10DRQ
Ch. 16 - Prob. 11DRQCh. 16 - What general trade-offs are involved in sequencing...Ch. 16 - Prob. 2TSCh. 16 - Prob. 3TSCh. 16 - One approach that can be effective in reducing the...Ch. 16 - Doctors and dentists offices frequently schedule...Ch. 16 - Prob. 3CTECh. 16 - Use the assignment method to determine the best...Ch. 16 - Rework Problem 1, treating the numbers in the...Ch. 16 - Assign trucks to delivery routes so that total...Ch. 16 - Develop an assignment plan that will minimize...Ch. 16 - Use the assignment method to obtain a plan that...Ch. 16 - The following table contains information...Ch. 16 - Using the information presented in the following...Ch. 16 - The following table shows orders to be processed...Ch. 16 - A wholesale grocery distribution center uses a...Ch. 16 - The times required to complete each of eight jobs...Ch. 16 - Prob. 11PCh. 16 - A shoe repair operation uses a two-step sequence...Ch. 16 - The following schedule was prepared by the...Ch. 16 - The production manager must determine the...Ch. 16 - A foreman has determined processing times at a...Ch. 16 - Given the information in the following table,...Ch. 16 - Given the following information on job times and...Ch. 16 - Prob. 18PCh. 16 - The following table contains order-dependent setup...Ch. 16 - The following table contains order-dependent setup...Ch. 16 - Prob. 21PCh. 16 - Given this information on planned and actual...Ch. 16 - Given the following data on inputs and outputs at...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Prob. 1CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Eight jobs have arrived in the following order: Job Processing Time Due Date 1 7 23 2 3 9 3 5 8 4 2 11 5 6 16 6 9 18 7 14 40 8 4 31 Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places. Process in the order they have arrived Flow Time Lateness Tardiness Averagearrow_forwardThe times required to complete each of eight jobs in a two-machine flow shop are shown in thetable that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B.a. Determine a sequence that will minimize makespan time.b. Construct a chart of the resulting sequence, and find machine B’s idle time. c. For the sequence determined in part a, how much would machine B’s idle time be reduced bysplitting the last two jobs in half?TIME (hours)Job Machine A Machine Ba 16 5b 3 13c 9 6d 8 7e 2 14f 12 4g 18 14h 20 11arrow_forwardAn independent accountant is planning to prepare tax returns for six of her clients.Prior to her actually preparing each return, her secretary checks the client’s file to besure all the necessary documentation is there and obtains all the tax forms needed forthe preparation of the return. Based on past experience with the clients, her secretaryestimates that the following times (in hours) are required for preparation of the returnand for the accountant to complete the necessary paperwork prior to filing each return:Client Secretary Time Accountant Time1 1.2 2.52 1.6 4.53 2.0 2.04 1.5 6.05 3.1 5.06 0.5 1.5In what order should the work be completed in order to minimize the total timerequired for all six clients?arrow_forward
- What are the advantages and disadvantages of the shortest processing time (SPT) rule?arrow_forwardWorkPro is a small manufacturer. It uses a job process for production. The following sample of jobs are listed in the order that they were received. Job Due Date Operation Time P 5 1 Q 20 8 R 8 5 S 11 6 T 3 12 When the shortest operating time (SOT) rule is applied to the sample of jobs, the resulting sequence is: A. Choos the following answer choice. T, P, R, S, Q R, S, T, P, Q P, Q, R, S, T P, R, S, Q, T B. In the WorkPro example above, average flow time for the sample of jobs when sequenced by the shortest operating time (SOT) rule is approximately: 19.8 14.2 4.8 6.4 C. In the WorkPro example above, average lateness for the sample of jobs when sequenced by the earliest due date (EDD) rule is approximately: Group of answer choices 10.4 4.8 7.8 5.8 D. Using the sample of jobs in the WorkPro example above, the shortest operating time (SOT) rule appears more attractive than the earliest due date (EDD) rule…arrow_forwardThere are six jobs as below. The processing time (in days) and due date for each job are below. Job |arrow_forwardDan's Auto Detailing business performs two major activities: exterior cleanup and interior detailing. Based on the size of car and condition, time estimates for six cars on Monday morning are as shown in the accompanying table. Car Number 1 5 6 Exterior Interior 55 75 4 65 35 50 60 45 90 35 40 a. Sequence the cars so that all exterior cleanup is done first and total completion time is minimized. The sequence is -Select-- -Select- -Select- -Select- -Select-- -Select- 2 3 80 20arrow_forwardGiven the projects displayed in Table 18.21, if FCFS is used to sequence the jobs, whatis the average flow time of the projects (in hours)?arrow_forwardAssume the jobs displayed in Table 18.22 need to be processed on a single resource andare sequenced with the WSPT rule. What is the average flow rate of the jobs (in jobs perminute)?arrow_forwardDrew Rosen Automation Company estimates the data entry and verifying times for four jobs as follows: In what order should the jobs be done if the company has one operator for each job? Illustrate the time-phased flow of this job sequence graphically.arrow_forwardWhat are the benefits and drawbacks of the shortest processing time rule (SPT)?arrow_forwardThe constraints governing the jobs are as fo1lows: A and B are start jobs; A controls C, D and E; B controls F and J; G depends upon C; H depends on D; E and F control I and L; K follows J; L is also controlled by K; G, H, I and L are the last jobs. Draw the network,arrow_forwardarrow_back_iosSEE MORE QUESTIONSarrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY