Why is
To determine: The reason why scheduling is simple for repetitive system and complex for job shops.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
Explanation of Solution
The reason why scheduling is simple for repetitive system and complex for job shops is as follows:
In job shop scheduling, jobs should follow different kind of paths which would contain different processing times. The processing requirements would be available in wide range in job shop. In job shop scheduling, the scheduler should compete with rush order, specification changes, and variety in job. Hence, scheduling is complex for job shops.
The degree of uniformity high in the continuous systems would be high, which would make scheduling simple for the repetitive systems.
Want to see more full solutions like this?
Chapter 16 Solutions
EBK OPERATIONS MANAGEMENT
- Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 C 2 B 3 E 4 A 5 D 6 F For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = nothing hours (enter your response as a whole number).arrow_forwardHow do scheduling activities differ for projects, mass production, and process industries?arrow_forwardExplain in simple terms the five (5) essential process scheduling policy factors that must be taken into consideration throughout the scheduling process.arrow_forward
- What are the advantages of backward scheduling?arrow_forwardThe higher levels of the work breakdown structure (WBS) represent increasing amounts of detail while the lower levels represent broad categories of activities. True or False True False Duration is defined as the time from the beginning to the end of an activity. True or False A common resource constraint is availability. True or False Group of answer choices True False The _____ schedule is a summary level schedule that encompasses the entire project scope. Group of answer choices original milestone procurement master conceptual Which of the following is NOT true about a master schedule? Group of answer choices If the project is chosen, a master schedule is created. It has major events and dates such as starting date, important events, and the completion date. The master schedule is rarely part of a contract. Changes to the schedule must be approved using a documented change process with…arrow_forwardTrue or Fale Short-term scheduling is important to efficiency and to cost reduction, but its impact is not of strategic importance.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.