••• 16.8 Carol Cagle has a repetitive manufacturing plant producing trailer hitches in Arlington, Texas. The plant has an average inventory turnover of only 12 times per year. She has therefore determined that she will reduce her component lot sizes. She has developed the following data for one component, the safety chain clip:
Annual demand = 31,200 units
Daily demand = 120 units
Daily production (in 8 hours) = 960 units
Desired lot size (1 hour of production) = 120 units
Holding cost per unit per year = $12
Setup labor cost per hour = $20
How many minutes of setup time should she have her plant manager aim for regarding this component?
Want to see the full answer?
Check out a sample textbook solutionChapter 16 Solutions
MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Sustainability and Supply Chain Management
- Question 1a: What happens if there is a shortage in a component? What data is needed to assess the impact of this? Question 1b: Even if a firm experiences a supply disruption, it may not experience a shortage directly. Why? Question 1c: Suppose TTR on your own = 12 weeks, and TTR to switch to an outside supplier = 9 weeks. How would the TTS compare to the Time to Recover (TTR)? Question 1d: What measures could be taken to prevent or mitigate impact of shortage of critical components?arrow_forwardQ: Write a letter to a Production Manager for the demand of 50 Haier Company name air conditionersarrow_forwardQuestion 1 Determine whether the following statements are true or false. Statement T or F 1. JIT emphasizes continuous improvement, respect for people, and standard work practices 2. Different from JIT, Lean operations externally focused on the customer 3. Qualitative Methods are used when situation is vague and little data exist 4. Predict sales of existing products and services is called Demand forecasting 5. Forecasting is about predicting the future.arrow_forward
- Question 01: advantage and disadvantage of hardworking and cool working principle. in manufacturing processes.arrow_forwardQuestion-1- Please read the scenario below and answer the questions. The maximum word-count limit of each answer is 200 words. Mention separate heading for each part. Controlling inventory is one of Wheeled Coach’s toughest problems. Operating according to a strategy of mass customization and responsiveness, management knows that success is dependent on tight inventory control. Anything else results in an inability to deliver promptly, chaos on the assembly line, and a huge inventory investment. Wheeled Coach finds that almost 50% of the cost of every ambulance it manufactures is purchased materials. A large proportion of that 50% is in chassis (purchased from Ford), aluminum (from Reynolds Metal), and plywood used for flooring and cabinetry construction (from local suppliers). Wheeled Coach tracks these A inventory items quite carefully, maintaining tight security/control and ordering carefully so as to maximize quantity discounts while minimizing on-hand stock. Because of long lead…arrow_forwardQuestion-1- Please read the scenario below and answer the questions. The maximum word-count limit of each answer is 200 words. Mention separate heading for each part. Controlling inventory is one of Wheeled Coach’s toughest problems. Operating according to a strategy of mass customization and responsiveness, management knows that success is dependent on tight inventory control. Anything else results in an inability to deliver promptly, chaos on the assembly line, and a huge inventory investment. Wheeled Coach finds that almost 50% of the cost of every ambulance it manufactures is purchased materials. A large proportion of that 50% is in chassis (purchased from Ford), aluminum (from Reynolds Metal), and plywood used for flooring and cabinetry construction (from local suppliers). Wheeled Coach tracks these A inventory items quite carefully, maintaining tight security/control and ordering carefully so as to maximize quantity discounts while minimizing on-hand stock. Because of long lead…arrow_forward
- QUESTION 9 Which of the following is an example of a strategic performance measurement system? a. standard cost system b. balanced scorecard c. lean management system d. product costing systemarrow_forwardQuestion – 1 (200-250 words) Some products remain in the maturity stage of the PLC for long period of time, whereas others pass through quickly. List and explain briefly three possible conditions that may allow a product to remain in the maturity stage for a long period of time.arrow_forwardQ4 need in 10 minutwarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.