International Financial Management
14th Edition
ISBN: 9780357130698
Author: Madura
Publisher: Cengage
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
error_outline
This textbook solution is under construction.
Students have asked these similar questions
Two mutually exclusive investment projects are under consideration. It is assumed that the cash flows are statistically independent random variables with means and variances estimated as follows:
(a) For each project, determine the mean and standard deviation for the PWusing an interest rate of 15%.(b) From the results of part (a), which project would you recommend?
Calculate the payback period, net present value, and internal rate of return for Project A. Assume a discount rate of 10%. Should the firm accept or reject Project A? Explain. If Project A and Project B are mutually exclusive, which is the better choice? Explain. What are “non-conventional” cash flows? What issues arise when evaluating projects with “non-conventional” cash flows?
Project A
Project B
Year
Cash Flow
Year
Cash Flow
0
-$100,000
0
-$1
1
$70,000
1
$0
2
$0
2
$0
3
$50,000
3
$10
Which of the following statements is incorrect regarding project appraisal techniques?
At IRR, the NPV of a project is equal to 0
If the IRR of a project is 8%, its NPV calculated using a discount rate greater than 8%, will be less than 0
If the NPV of a project is greater than 0, then its PI will exceed 1.
If the PI of a project equals 0, then the project's initial cash outflow equals the PV of its cash inflows
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- Calculate the cash flows for each year. Based on these cash flows and the average project cost of capital, what are the projects NPV, IRR, MIRR, PI, payback, and discounted payback? Do these indicators suggest that the project should be undertaken?arrow_forwardCalculate the project cash flows for each year. Based on these cash flows and the average project cost of capital, what are the projects NPV, IRR, MIRR, PI, payback, and discounted payback? Do these indicators suggest that the project should be undertaken?arrow_forwardAssume San Lucas Corporation in MAD 26-1 assigns the following probabilities to the estimated annual net cash flows: a. Compute the expected value of the annual net cash flows. b. Determine the expected net present value of the equipment, assuming a desired rate of return of 10% and the expected annual net cash flows computed in part (a). Use the present value tables (Exhibits 2 and 5) provided in the chapter in determining your answer. c. Based on your results in parts (a) and (b), should San Lucas Corporation invest in the equipment?arrow_forward
- Project A has the following estimated cash flows and present values:Year Cash flow $ Discount factor@ 12% Present value $0 Cost (95 000) 1.0 (95 000) 1–5 Contributionper annum 50 000 3.605 180 250 1–5 Fixed costsper annum (25 000) 3.605 (90 125) 5 Residual value 20 000 0.567 11 340 The benefit of using sensitivity analysis in an investment appraisal would be:arrow_forwardSuppose that, for a certain potential investment project, the optimistic, most likely, and pessimistic estimates are as shown in the accompanying table. Solve, a. What is the AW for each of the three estimation conditions? b. It is thought that the most critical factors are useful life and net annual cash flow. Develop a table showing the net AW for all combinations of the estimates forthese two factors, assuming all other factors to be at their most likely values.arrow_forwardWhich of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows . a. A project’s NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV), then discounting the TV at the IRR to find its PV . b. The higher the WACC used to calculate the NPV, the lower the calculated NPV will be c. If a project’s NPV is greater than zero, then its IRR must be less than the WACC . d. If a project’s NPV is greater than zero, then its IRR must be less than zero. e. The NPVs of relatively risky projects should be found using relatively low WACCsarrow_forward
- Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV), then discounting the TV at the IRR to find its PV. b. The higher the WACC used to calculate the NPV, the lower the calculated NPV will be. c. If a project's NPV is greater than zero, then its IRR must be less than the WACC. d. If a project's NPV is greater than zero, then its IRR must be less than zero. e. The NPVs of relatively risky projects should be found using relatively low WACCs. Provide explanation for choicearrow_forwardWhich of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV), then discounting the TV at the WACC. b. The NPV of a relatively low-risk project should be found using a relatively high WACC. c. If a project's NPV is less than zero, then its IRR must be less than the WACC. d. The lower the WACC used to calculate it, the lower the calculated NPV will be. e. If a project's NPV is greater than zero, then its IRR must be less than zero.arrow_forwardUse the information provided to answer the questions Calculate the Accounting Rate of Return (on average investment) of Project B (expressed to twodecimal places).Calculate the Net Present Value of each project (with amounts rounded off to the nearest Rand). Use your answers from previous question to recommend the project that should be chosen. Motivateyour choice.arrow_forward
- Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively. Time 0 1 2 3 4 5 6 Cash Flow -1,040 140 460 660 660 260 660 Use the NPV decision rule to evaluate this project; should it be accepted or rejected?arrow_forwardTo calculate net present value of a project with normal cash flows, find the present value of the expected cash flows, and subtract A) retained earnings. B) the cost of the investment. C) the factor loading. D) the payback period.arrow_forwardA company considering a project with extremely risky cash flows decides to apply a premium to the discount rate used to evaluate the project. The management of the company has set the following limits regarding the use of premia on discount rates: If the CV of the project is less than 1, no premium is added. If the CV of the project is 1 or more, but less than 1.5, the discount rate is multiplied by 1.5 If the CV of the project is 1.5 or more, the discount rate is multiplied by 2. The project under consideration has a CV of 1.5 while the company’s WACC is 10%. What would the discount rate employed to evaluate the project be?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License