Question
Chapter 16, Problem 4P
Summary Introduction
To determine: The annual number of total orders
Concept introduction
The Economic Order Quantity is the order quantity at which the overall cost is minimum, given the set up or ordering cost, the annual demand and the inventory holding cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Hartley Electronics, Inc., in Nashville, produces short runs of custom airwave scanners for the defense industry. You
have been asked by the owner, Janet Hartley, to reduce inventory by introducing a kanban system. After several
hours of analysis, you develop the following data for scanner connectors used in one work cell. How many kanbans
do you need for this connector?
Daily demand
Lead time
Safety stock
1,600 connectors
3 days
0.50 day
Kanban size
500 connectors
Number of kanbans =
kanbans (round your response to the nearest whole number).
Titan fitness produces custom barbells for crossfitters. The owner, Ed, has asked you to reduce inventory by introducing a kanban system. After several hours of analysis, you developed the following data for a barbell part used in one work cell. How many kanbans do you need for this connector?
Hartley Electronics, Inc., in Nashville, producesshort runs of custom airwave scanners for the defense industry.The owner, Janet Hartley, has asked you to reduce inventory byintroducing a kanban system. After several hours of analysis, youdevelop the following data for scanner connectors used in onework cell. How many kanbans do you need for this connector?
Chapter 16 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Ch. 16 - Prob. 1EDCh. 16 - Prob. 1DQCh. 16 - Prob. 2DQCh. 16 - Prob. 3DQCh. 16 - Prob. 4DQCh. 16 - Prob. 5DQCh. 16 - Prob. 6DQCh. 16 - Prob. 7DQCh. 16 - Prob. 8DQCh. 16 - Prob. 9DQ
Ch. 16 - Prob. 10DQCh. 16 - Prob. 11DQCh. 16 - Prob. 12DQCh. 16 - Prob. 1PCh. 16 - Prob. 2PCh. 16 - Prob. 3PCh. 16 - Prob. 4PCh. 16 - Prob. 5PCh. 16 - Prob. 6PCh. 16 - Prob. 7PCh. 16 - Prob. 8PCh. 16 - Prob. 9PCh. 16 - Prob. 10PCh. 16 - Prob. 1.1VCCh. 16 - Prob. 1.2VCCh. 16 - Prob. 1.3VCCh. 16 - Prob. 2.1VCCh. 16 - Prob. 2.2VCCh. 16 - Prob. 2.3VCCh. 16 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Krupp Refrigeration, Inc., is trying to reduce inventory and wants you to install a kanban system for compressors on one of itsassembly lines. Determine the size of the kanban and the number of kanbans (containers) needed.Setup cost = $10Annual holding cost per compressor = $100Daily production = 200 compressorsAnnual usage = 25,000 (50 weeks * 5 days each * daily usage of 100 compressors)Lead time = 3 daysSafety stock = 1 2 day’s production of compressorsarrow_forwardThe production schedule at Mazda calls for 1,500 Mazdas to be produced during each of 22 production days in January and 1,050 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.14. The container (a delivery truck) size is 225 tires. The average waiting time plus material handling time is 0.15 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per container in January is 0.20 day. February processing time will average 0.30 day per container. How many containers should be authorized for January? How many containers should be authorized for February? containers. (Enter your response rounded up to the next whole number.) containers. (Enter your response rounded up to the next whole number.)arrow_forwardA supplier provides parts to a manufacturing company that demands frequent deliveries. At the present time it takes six hours to make a round trip between the supplier’s warehouse and the customer, including loading, travel, and unloading time. The lot size is 12 pallet loads on a truck, and the manufacturer uses 2 pallets per hour.a. How many trucks are needed to ship the pallets to the manufacturer?b. What is likely to happen if the truck breaks down?c. How can the supplier ensure that the customer does not run out of parts even in the face of delivery problems or other uncertainties?d. What will happen to the supplier if the manufacturer runs into trouble and shuts down for a period of six hours?arrow_forward
- Flores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $16 Annual holding cost subassembly $250 per subassembly 600 subassemblies Daily production Annual usage 62,500 (-50 weeks x5 days each x daily usage of 250 subassemblies) Lead time Safety stock The kanban size is (round your response to the nearest whole number). 2 days 1 day's production of subassembliesarrow_forwardFlores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost Annual holding cost subassembly Daily production Annual usage Lead time Safety stock $23 $200 per subassembly 550 subassemblies 50,000 (= 50 weeks x 5 days each x daily usage of 200 subassemblies) 3 days 1 day's production of subassemblies The kanban size is (round your response to the nearest whole number). The number of kanbans is (round your response to the nearest whole number).arrow_forward31 A supplier of instrument gauge clusters uses a kanban system to control material flow. The gauge cluster housings are transported six at a time. A fabrication center produces approximately 10 gauges per hour. It takes approximately three hours for the housing to be replenished. Due to variations in processing times, management has decided to keep 10 percent of the needed inventory as safety stock. How many kanban card sets are needed? Note: Round up your answer to the next whole number.arrow_forward
- The production schedule at Mazda calls for 1,250 Mazdas to be produced during each of 22 production days in January and 1,050 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.08. The container (a delivery truck) size is 250 tires. The average waiting time plus material handling time is 0.50 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per container in January is 0.50 day. February processing time will average 0.10 day per container. How many containers should be authorized for January? containers. (Enter your response rounded up to the next whole number.)arrow_forwardThe production schedule at Mazda calls for 1,200 Mazdas to be produced during each of 22 production days in January and 900 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from Gesundheit. The safety stock policy variable, a, is 0.15. The container (a delivery truck) size is 200 tires. The average waiting time plus materials handling time is 0.16 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing time per container in January is 0.10 day. February processing time will average 0.125 day per container. How many containers should be authorized for January? How many for February?arrow_forwardA company replaces its SKU’s at a rate of 25 pcs a day. In the past this qty tended to vary normally & have a std dev of 3 units per day. SKU’s are ordered from XYZ Supplier. LT is normally distributed with an average of 10 days & std dev of 2 days. What ROP should be used to achieve a service level of 95%.arrow_forward
- The production schedule at Mazda calls for 1,200 Mazdas to be produced during each of 22 production days in January and 900 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from Gesundheit. The safety stock policy variable, α, is 0.15. The container (a delivery truck) size is 200 tires. The average waiting time plus materials handling time is 0.16 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing time per container in January is 0.10 day. February processing time will average 0.125 day per container. How many containers should be authorized for January?How many for February?arrow_forwardHartley Electronics, Inc., in Nashville, producesshort runs of custom airwave scanners for the defense industry. The owner, Janet Hartley, has asked you to reduce inventory by introducing a kanban system. After several hours ofanalysis, you develop the following data for scanner connectors used in one work cell. How many kanbans do you needfor this connector?arrow_forwardWhat do lean manufacturers demand from their vendors? a. high-quality materials b. low-cost materials c. on-time deliveries d. all of these choicesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.