Question
Chapter 16, Problem 5P
Summary Introduction
To determine: The number of kanbans needed.
Concept introduction
The Economic Order Quantity is the order quantity at which the overall cost is minimum, given the set up or ordering cost, the annual demand and the inventory holding cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Titan fitness produces custom barbells for crossfitters. The owner, Ed, has asked you to reduce inventory by introducing a kanban system. After several hours of analysis, you developed the following data for a barbell part used in one work cell. How many kanbans do you need for this connector?
Tej Dhakar’s company wants to establish kanbans tofeed a newly established work cell. The following data have beenprovided. How many kanbans are needed?Daily demand 250 unitsLead time 12 daySafety stock 14 dayKanban size 50 units
Tej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following data have been provided.
Note:
This is a level production system.
Daily demand
200
units
Production lead time
2.00
days
Safety stock
1.00
day
Kanban size
50
units
How many kanbans are needed?
enter your response here
kanbans (round your response to the nearest whole number).
Chapter 16 Solutions
OPERTATIONS MGMT:SUSTAINABILITY
Ch. 16 - Prob. 1EDCh. 16 - Prob. 1DQCh. 16 - Prob. 2DQCh. 16 - Prob. 3DQCh. 16 - Prob. 4DQCh. 16 - Prob. 5DQCh. 16 - Prob. 6DQCh. 16 - Prob. 7DQCh. 16 - Prob. 8DQCh. 16 - Prob. 9DQ
Ch. 16 - Prob. 10DQCh. 16 - Prob. 11DQCh. 16 - Prob. 12DQCh. 16 - Prob. 1PCh. 16 - Prob. 2PCh. 16 - Prob. 3PCh. 16 - Prob. 4PCh. 16 - Prob. 5PCh. 16 - Prob. 6PCh. 16 - Prob. 7PCh. 16 - Prob. 8PCh. 16 - Prob. 9PCh. 16 - Prob. 10PCh. 16 - Prob. 1.1VCCh. 16 - Prob. 1.2VCCh. 16 - Prob. 1.3VCCh. 16 - Prob. 2.1VCCh. 16 - Prob. 2.2VCCh. 16 - Prob. 2.3VCCh. 16 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Tej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following data have been provided. Note: This is a level production system. Daily demand 200 units Production lead time 2.00 days Safety stock 1.00 day Kanban size 50 units How many kanbans are needed? nothing kanbans (round your response to the nearest whole number).arrow_forwardCreate a diagram that describes how Kanban systems workarrow_forwardA JIT system uses kanban cards to authorize movement of incoming parts. In one portion of thesystem, a work center uses an average of 100 parts per hour while running. The manager hasassigned an inefficiency factor of .20 to the center. Standard containers are designed to hold sixdozen parts each. The cycle time for parts containers is about 105 minutes. How many containersare needed?arrow_forward
- A JIT system uses kanban cards to authorize movement of incoming parts. In one portion of the system, a work center uses an average of 98 parts per hour while running. The manager has assigned an inefficiency factor of .28 to the center. Standard containers are designed to hold 6 dozen parts each. The cycle time for parts containers is about 105 minutes.arrow_forwardTej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following data have been provided. Note: This is a level production system. Daily demand 275 units Production lead time 0.50 day Safety stock 0.25 day Kanban size 50 units How many kanbans are needed? enter your response here kanbans (round your response to the nearest whole number).arrow_forwardneed kanban size as well as the bumber of kanbans please! Need only handwritten solution only (not typed one).arrow_forward
- Explain how the following kanbans work: Squares of Kanban?arrow_forwardCletus and Spike Company is implementing a Kanban system for a heated water bowl manufacturing line that produces 1,500 units in an eight-hour day. The heating element has a waiting time of 30 minutes and a processing time of one hour. The container size is 40 heating elements, and the safety factor is 15 percent. What is the maximum inventory of heating elements in the system?arrow_forwardStan Weakly can sort a bin of 130 letters in 20 minutes. He typically receives 550 letters an hour. A truck arrives with more bins every 30 minutes. The office uses a safety factor of 20%. How many kanbans are needed for the letter-sorting process? Please show working. Thank you!arrow_forward
- Cletus and Spike Company is implementing a Kanban system for a heated water bowl manufacturing line that produces 1,500 units in an eight-hour day. The heating element has a waiting time of 30 minutes and a processing time of one hour. The container size is 40 heating elements, and the safety factor is 15 percent. How many Kanban cards should be used? a. 9 b. 12 c. 2 d. 27arrow_forwardIf the kanban system is being employed, when will it be implemented?arrow_forwardA Kanban is a Japanese term for a production supervisor who is responsible for controlling the flow of production in many just-in-time sysarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.