Concept explainers
1.
Compute the total estimated gross profit on the contracts.
1.
Explanation of Solution
Contract:
Contract is an agreement among two parties or more parties which includes enforceable obligations and rights. A contract can be written, oral or implied by ordinary business practices.
Calculate the total estimated gross profit:
As of December 31 | |||
2019 | 2020 | 2021 | |
Contract Price | $20,000,000 | $20,000,000 | $20,000,000 |
Costs incurred to date | $8,000,000 | $16,000,000 | $18,000,000 |
Estimated costs to complete | $6,000,000 | $3,000,000 | $0 |
Total costs estimated to date | $14,000,000 | $19,000,000 | $18,000,000 |
Estimated gross profit | $6,000,000 | $1,000,000 | $2,000,000 |
Table (1)
2.
Compute the percentage of completion for 2019, 2020 and 2021.
2.
Explanation of Solution
Compute the percentage of completion for 2019:
Therefore, the percentage of completion for 2019 is 57.1%.
Compute the percentage of completion for 2020:
Therefore, the percentage of completion for 2020 is 84.2%.
Compute the percentage of completion for 2021:
Therefore, the percentage of completion for 2021 is 100%.
3.
Compute the percentage of completion for 2019, 2020 and 2021.
3.
Explanation of Solution
Compute the amount of income recognized for 2019:
Therefore, the amount of income recognized during 2019 is $3,426,000.
Compute the amount of income recognized for 2020:
Therefore, the amount of income recognized during 2020 is ($2,584,000).
Compute the amount of income recognized for 2021:
Therefore, the amount of income recognized during 2021 is $1,158,000.
4.
Journalize entries related to the project for 3 years.
4.
Explanation of Solution
Journal entry is a set of economic events which can be measured in monetary terms. These are recorded chronologically and systematically.
Accounting rules for Journal entries:
- To record increase balance of account: Debit assets, expenses, losses and credit liabilities, capital, revenue and gains.
- To record decrease balance of account: Credit assets, expenses, losses and debit liabilities, capital, revenue and gains.
Prepare journal entries:
Date | Account titles and explanation | Debit ($) | Credit ($) |
2019 | Construction in progress (inventory) | 8,000,000 | |
Accounts payable, cash, salaries, payables etc. | 8,000,000 | ||
(To record costs of construction) | |||
Construction expense | 8,000,000 | ||
Construction in progress (Refer to requirement 3) | 3,426,000 | ||
Construction revenue | 11,426,000 | ||
(To record gross profit) | |||
Accounts receivable | 8,000,000 | ||
Partial billings | 8,000,000 | ||
To record partial billings) | |||
Cash | 6,000,000 | ||
Accounts receivable | 6,000,000 | ||
(To record collections) | |||
2020 | Construction in progress (inventory) | 8,000,000 | |
Accounts payable, cash, salaries, payables etc. | 8,000,000 | ||
(To record costs of construction) | |||
Construction expense | 8,000,000 | ||
Construction in progress (Refer to requirement 3) | 2,584,000 | ||
Construction revenue | 5,416,000 | ||
(To record gross profit) | |||
Accounts receivable | 8,000,000 | ||
Partial billings | 8,000,000 | ||
To record partial billings) | |||
Cash | 6,000,000 | ||
Accounts receivable | 6,000,000 | ||
(To record collections) | |||
2021 | Construction in progress (inventory) | 2,000,000 | |
Accounts payable, cash, salaries, payables etc. | 2,000,000 | ||
(To record costs of construction) | |||
Construction expense | 2,000,000 | ||
Construction in progress (Refer to requirement 3) | 1,158,000 | ||
Construction revenue | 3,158,000 | ||
(To record gross profit) | |||
Accounts receivable | 4,000,000 | ||
Partial billings | 4,000,000 | ||
To record partial billings) | |||
Cash | 6,000,000 | ||
Accounts receivable | 6,000,000 | ||
(To record collections) | |||
Partial billings | 20,000,000 | ||
Construction in progress | 20,000,000 | ||
(To record and to close partial billings) |
Table (2)
5.
Explain the manner in which the project will be carried on the balance sheet for 2019, 2020 and 2021.
5.
Explanation of Solution
The manner in which the project is carried on the balance sheet for the year 2019, 2020 and 2021 is explained below:
As of December 31, | |||
Current assets | 2019 | 2020 | 2021 |
Accounts receivable | $2,000,000 | $4,000,000 | $2,000,000 |
Construction in progress | $11,426,000 | $16,842,000 | |
Less: Partial billings | $8,000,000 | $16,000,000 | |
Construction in progress in excess of billings | $3,426,000 | $842,000 |
Table (3)
Want to see more full solutions like this?
Chapter 17 Solutions
Intermediate Accounting: Reporting And Analysis
- Before starting to render his service, Paolo collected an advance payment of P2,000 for the acceptance of the job contract. When the required service from Paolo was completed, Paolo received P8,000 cash service fee after deducting the P2,000 advance payment, plus an office machine with cash price value of P3,000 and P2,500 cost to the seller. The gross service income of Paolo isarrow_forwardMyrta entered into a contract with "Big Builder on December 1, 2018 to remodel the interior of her Coffee Shop. The Contract required Big Builder to complete the project ata cost of $10,000 on or before January 1, 2019 (so she could open herCoffee Shop that day). Big Builder barely got started on the project by January 1, so Myrta terminated the Contract without paying Big Builder anything. Myrta then found a new Contractor, named "Better Builder who agreed to complete the same project by March 1, 2019 but at a cost of $11,500. Better Builder completed the project on March 1, 2019 and Myrta paid them $11,500. Happy the project is finally complete, Myrta still feels "ripped off by Big Builder and wants to sue them to recover her damages for breach of contract. Not only did Myrta have to pay $11,500 to Better Builder, but (i) she also had to pay a cleaning service $200 to clean up the construction mess Big Builder had left behind and (ii) she also lost an estimated $500 in profits she…arrow_forwardGeorge Co. enters into a contract to build an apartment for Jungle Co. For a fixed fee of P20,000,000. At contract inception, George Co. assesses its performance obligations in the contract and concludes that it has a single performance obligation that is satisfied over time. George Co. determines that the measure of progress that best depicts its performance in the contract is input method based on costs incurred. George estimates that the total contract costs would amount to P16,000.000 over the construction period. George incurs contract costs of P2,000,000 during the year. How much revenue is recognized for the year?arrow_forward
- In November 20X2, an entity contracts with a customer to refurbish a 3-storey building and install new elevators for a total consideration of ₱5,000,000. The promised refurbishment service, including the installation of elevators, is a single performance obligation satisfied over time. Total expected costs are ₱4,000,000, including ₱1,500,000 for the elevators. The entity determines that it acts as a principal because it obtains control of the elevators before they are transferred to the customer. A summary of the transaction price and expected costs is as follows: Transaction price ₱5,000,000 Expected costs: Elevators ₱1,500,000 Other costs 2,500,000 Total expected costs ₱4,000,000 The entity uses an input method based on costs incurred to measure its…arrow_forwardOn July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion on October 2019. The contract contains a penalty clause to the effect that the other party was to deduct P35,000 from the contract price for each week of delay. On the other hand, if the contractor was able to finish the building earlier than agreed, it will be rewarded an amount equal to P50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2018, the estimated costs of particular construction material amounting to P520,000 were bought for P780,000. The increase in the contract price related to this cost escalation was approved by the client. Completion was delayed for 4 weeks. The records show: 2017 2018 2019 Costs incurred P1,750,000 6,440,000 1,085,000 Estimated cost to complete 7,000,000 1,810,000 -- Progress billings…arrow_forwardBrown, a consulting engineer, agreed to sublet the making of the design drawings for bridge approaches to Black—provided that Brown secured the contract for designing this certain large bridge project. Assuming that Brown would get the job, Black contracted to employ White at a salary of $800 per month for one year. Brown failed to get the award. Is Black nonetheless obligated to hire White?arrow_forward
- Shaw Company engages Maya Company to produce a large machine, install the machine, and train their employees on the machine. The machine, installation, and training are distinct, and Maya determines that the contract includes three separate performance obligations. The machine, installation, and training typically cost $800,000, $100,000, and $100,000 respectively when each is provided in a separate contract. Shaw and Maya agree to a total contract price of $920,000. How much of the contract price should Maya allocate to the machine, installation, and training, respectively? $736,000; $92,000; $92,000 $800,000; $100,000; $100,000 $732,000; $94,000; $94,000 $736,000; $184,000arrow_forwardOn January 1, 20x1, Alpha Development Corporation entered into a contract with Omega Company to construct a new corporate headquarters on land owned by Omega. The contractor determines that the control of the building is passed to Omega as it is constructed. Therefore, the performance obligation is satisfied overtime. The contract price is P6,000,000, but the amount will be reduced or increased depending on when the construction of the building is completed. For each day before December 31, 20x3 that the building is completed, the promised consideration increases by P30,000. For each day after December 31, 20x3 that the building is incomplete, the promised consideration will be reduced by P30,000. The parties have also agreed that when the building is complete, it will be inspected and assigned a green building certification level. If thebuilding achieves the certification level specified in the contract, Alpha will be entitled to an incentive bonus ofP150,000.On December 31, 20x1,…arrow_forwardA contractor has a job which should be completed in 135 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 160 days. Of the 80 men, 50 are each paid 255 a day, 25 at 450 a day, and 5 at 790 a day. For each day beyond the original 135, the contractor has to pay 520 liquidated damages. Men are added so that he can complete the work on time. If of the additional men, 2 men are paid 470 a day, and the rest at 275 a day, would the contractor save the money by employing more men and not paying the fine? Show cashflow diagramarrow_forward
- Daniel agreed that he would erect an apartment building for Steven for $12 million and that Daniel would suffer a deduction of $12,000 per day for every day of delay. Daniel was twenty days late in finishing the job, losing ten days because of a strike and ten days because the material suppliers were late in furnishing materials. Daniel claims that he is entitled to payment in full (a) because the agreement as to $12,000 a day is a penalty and (b) because Steven has not shown that he has sustained any damage. Discuss each contention and decide.arrow_forwardOn April 1st, Bob the Builder entered into a contract of one-month duration to build a barn for Nolan. Bob is guaranteed to receive a base fee of $5,000 for his services in addition to a bonus depending on when the project is completed. Nolan created incentives for Bob to finish the barn as soon as he can without jeopardizing the structural integrity of the barn. Nolan offered to pay an additional 30% of the base fee if the project finished 2 weeks early and 10% if the project finished a week early. The probability of finishing 2 weeks early is 30% and the probability of finishing a week early is 60%. What is the expected transaction price if Bob estimates variable consideration as the expected value?arrow_forward
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage LearningIndividual Income TaxesAccountingISBN:9780357109731Author:HoffmanPublisher:CENGAGE LEARNING - CONSIGNMENT