1.
To compute: The equivalent units for direct material and conversion costs and assign cost to units completed and ending work in process.
Given information:
Beginning: Degree of completion: direct material 100%; conversion costs; 30%.
Ending: Degree of completion: direct material 100%; conversion costs; 80%.
2.
To compute: The total
Given information:
Standard cost per unit of direct materials is $5.75.
Standard cost per unit of conversion costs is $12.25.
3.
To compute: The total August variances for direct materials and conversion costs.
4.
To prepare: The
Want to see the full answer?
Check out a sample textbook solutionChapter 17 Solutions
Cost Accounting - Access (Custom Package)
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education