Financial and Managerial Accounting (Looseleaf) (Custom Package)
6th Edition
ISBN: 9781259754883
Author: Wild
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 18, Problem 3QS
Cost behavior estimation---high-low method P1
The following information is available for a company’s maintenance cost over the last seven months. Using the high-low method. Estimate both fixed and variable components of its maintenance cost.
Month | Maintenance Hours | Maintenance Cost |
June…………………………………… | 9 | $5,450 |
July…………………………………… | 18 | 6,900 |
August………………………………... | 12 | 5,100 |
September……………………………... | 15 | 6,000 |
October………………………………... | 21 | 6,900 |
November……………………………… | 24 | 8,100 |
December……………………………… | 6 | 3,600 |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
ces
w
2
The following information is available for a company's maintenance cost over the last seven months.
*
Month
June
July
August
September
October
November
December
7,750
8,560
3,700
Using the high-low method, estimate both the fixed and variable components of its maintenance cost.
Units Produced
110
170
130
160
220
250
70
Total cost at the high point
Variable costs at the high point:
Volume at the high point:
Variable cost per unit produced
Total variable costs at the high point
Total fixed costs
#
Total cost at the low point
Variable costs at the low point:
Volume at the low point:
Variable cost per unit produced
Total variable costs at the low point
13
Change in cost
Change in volume
3
(4
$
IDI
4
15-
%
Maintenance Cost
$4,780
6,400
5,320
6,130
5
High-Low method - Calculation of variable cost per unit produced
Cost at high point minus cost at low point
Volume at high point minus volume at low point
16
HA
49
6
Q Search
17
▶11
Problem 2
Java Company manufactures a product that is subject to wide seasonal
variations in demand. Unit costs are computed on a quarterly basis by dividing
each quarter's manufacturing costs (materials, labor, and overhead) by the
quarter's production in units. The company's estimated costs, by quarter, for
the coming year are given below:
Quarter
First
Second
Third
Fourth
Direct materials
Direct labor. ..
Manufacturing overhead. .
Total manufacturing costs....
P240,000 P120,000
96,000
228.000
P564,000
48,000
204.000
P372.000
P 60,000
24,000
192,000
P276,000
P180,000
72,000
216.000
P468,000
Number of units to be produced. .
Estimated cost per unit ...
80,000
P7.05
40,000
P9.30
20,000
P13.80
60,000
P7.80
Management finds the variation in unit costs to be confusing and difficult to
work with. It has been suggested that the problem lies with manufacturing
overhead, since it is the largest element of cost. Accordingly, you have been
asked to find a more suitable way of assigning…
Electronio ExperGecupancy Percentage
62
Month
January
April
August
6,200
6,600
68
7,200
78
December
5,500
50
Jsing the highllow two point method to:
1 Determine the variable cost per 1poercent of occupancy
2 Estimate the fixed costs per month
3 What is the estimated total electric expense at 62 pecent of ocoupancy?
ANSWER
Month
Electronic Expenses Oooupanoy Percentage
High
August
7,200
78
Low
December
5,500
50
Difference
1,700
28
1 Variable cost per 1% of ocoupanoy =
61
2 Total variable cost of electric expense for December =
Total fixed cost of electric expense for December =
3,035.71
2,464.29
Total variable cost of electric expense for August =
Total fixed cost of electrio expense for August =
4,735.71
2,464.29
3 Using the fixed cost for December as the total fixed cost for estimation
Total variable cost of electric expense at 62%. oooupancy =
Total fixed oost of electric expense at 62% occupanoy
Estimated total electric expense at 62% occupancy =
Chapter 18 Solutions
Financial and Managerial Accounting (Looseleaf) (Custom Package)
Ch. 18 - Prob. 1MCQCh. 18 - Prob. 2MCQCh. 18 - Prob. 3MCQCh. 18 - Prob. 4MCQCh. 18 - Prob. 5MCQCh. 18 - Prob. 1DQCh. 18 - Prob. 2DQCh. 18 - When output volume increases, do fixed costs per...Ch. 18 - How is the cost-volume-profit analysis useful?Ch. 18 - Prob. 5DQ
Ch. 18 - Prob. 6DQCh. 18 - Prob. 7DQCh. 18 - Prob. 8DQCh. 18 - Prob. 9DQCh. 18 - Prob. 10DQCh. 18 - Prob. 11DQCh. 18 - Prob. 12DQCh. 18 - Prob. 13DQCh. 18 - Prob. 14DQCh. 18 - Prob. 15DQCh. 18 - Prob. 16DQCh. 18 - Prob. 17DQCh. 18 - Prob. 18DQCh. 18 - Prob. 19DQCh. 18 - APPLE Should Apple use single product or...Ch. 18 - Prob. 21DQCh. 18 - Prob. 1QSCh. 18 - Prob. 2QSCh. 18 - Cost behavior estimation---high-low method P1 The...Ch. 18 - Prob. 4QSCh. 18 - Prob. 5QSCh. 18 - Prob. 6QSCh. 18 - Prob. 7QSCh. 18 - Prob. 8QSCh. 18 - Prob. 9QSCh. 18 - Prob. 10QSCh. 18 - Prob. 11QSCh. 18 - Prob. 12QSCh. 18 - Prob. 13QSCh. 18 - Prob. 14QSCh. 18 - Prob. 15QSCh. 18 - Prob. 16QSCh. 18 - Prob. 17QSCh. 18 - Following are five graphs representing various...Ch. 18 - Prob. 2ECh. 18 - Prob. 3ECh. 18 - Prob. 4ECh. 18 - Prob. 5ECh. 18 - Prob. 6ECh. 18 - Prob. 7ECh. 18 - Prob. 8ECh. 18 - Prob. 9ECh. 18 - Prob. 10ECh. 18 - Prob. 11ECh. 18 - Prob. 12ECh. 18 - Prob. 13ECh. 18 - Prob. 14ECh. 18 - Prob. 15ECh. 18 - Prob. 16ECh. 18 - Prob. 17ECh. 18 - Prob. 18ECh. 18 - Prob. 19ECh. 18 - Prob. 20ECh. 18 - Prob. 21ECh. 18 - Prob. 22ECh. 18 - Prob. 23ECh. 18 - Prob. 24ECh. 18 - Prob. 25ECh. 18 - Prob. 1PSACh. 18 - Prob. 2PSACh. 18 - Prob. 3PSACh. 18 - Prob. 4PSACh. 18 - Prob. 5PSACh. 18 - Prob. 6PSACh. 18 - Prob. 7PSACh. 18 - Prob. 1PSBCh. 18 - Prob. 2PSBCh. 18 - Prob. 3PSBCh. 18 - Prob. 4PSBCh. 18 - Prob. 5PSBCh. 18 - Prob. 6PSBCh. 18 - Prob. 7PSBCh. 18 - Prob. 18SPCh. 18 - Apple offers extended service contracts that...Ch. 18 - Prob. 2BTNCh. 18 - Prob. 3BTNCh. 18 - Prob. 4BTNCh. 18 - Prob. 5BTNCh. 18 - Prob. 6BTNCh. 18 - Prob. 7BTNCh. 18 - Prob. 8BTNCh. 18 - Prob. 9BTN
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- QS 18-4 (Algo) Measuring costs using high-low method LO P1 The following information is available for a company's maintenance cost over the last seven months. Month Units Produced June 110 July 170 August 138 September 160 October 220 November December 250 70 Maintenance Cost $ 5,050 6,850 5,650 6,550 8,350 9.250 3,850 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. High-Low method - Calculation of variable cost per unit produced Total cost at the high point Variable costs at the high point: Volume at the high point Variable cost per unit produced Total variable costs at the high point Total fixed costs Total cost at the low point Variable costs at the low point: Volume at the low point: Variable cost per unit produced Total variable costs at the low point Total fixed costsarrow_forwardU. 2TU 21. The following information is available for Sweet Corporation's Material X Annual usage Working days per year Normal lead time The units of Material X are required evenly throughout the year. What is the reorder point? a. 35 units 12,600 units 360 days 20 days b. 20" day c. 700 units d. 630 unitsarrow_forwardCH11_HW_QA2_LA Required 1: 1-a. Compute the throughput time for each month. 1-b. Compute the manufacturing cycle efficiency (MCE) for each month. 1-c. Compute the delivery cycle time for each month. (Round your answers to 1 decimal place.) Throughput Time Manufacturing Cycle Efficiency (MCE) Delivery Cycle Time Month 1 days % days Month 2 days % days Month 3 days % days Month 4 days % days Required 3: 3-a. (Month 5) Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE. 3-b. (Month 6) Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so…arrow_forward
- 8 The following data are average times per order over the last month. Wait time to start production Inspection time 16.2 days 1.8 days Process time 2.7 days Move time 2.6 days Queue time 8.2 days The manufacturing cycle efficiency (MCE) would be closest to: А. 29%. В. 82%. С. 46%. D. 18%. Е. None of the abovearrow_forwardExercise 18-3 (Part Level Submission) The controller of Norton Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs Total Maintenance Costs Total Month January February March April May June $2,590 2,890 3,490 4,390 3,090 5,530 Machine Hours 330 380 530 660 530 730 (a1) Determine the variable cost components using the high-low method. (Round variable cost to 3 decimal places e.g 12.250.) Variable cost per machine hourarrow_forwardUsing Least Square method compute for the variable and fixed cost Month Direct Labor Cost of Electricity Jan 170 4500 Feb 160 4225 Mar 150 4321 Apr 180 5250 May 173 4800 Jun 190 5100 Jul 210 4450 Aug 152 4200 Sep 220 5475 Oct 181 4760 Nov 177 4325 Dec 100 3975arrow_forward
- High-Low Method for a Service Company Continental Railroad decided to use the high-low method and operating data from the past six months to estimate the fixed and variable components of transportation costs. The activity base used by Continental Railroad is a measure of railroad operating activity, termed "gross-ton miles," which is the total number of tons multiplied by the miles moved. January February March April May June Transportation Costs Gross-Ton Miles $536,200 225,000 597,800 252,000 422,500 163,000 573,200 244,000 480,700 196,000 616,300 265,000 Determine the variable cost per gross-ton mile and the total fixed cost. Variable cost (Round to two decimal places.) Total fixed cost pearrow_forward--/1 Question 3 View Policies Current Attempt in Progress The standard rate of pay is $10 per direct labor hour. If the actual direct labor payroll was $39,200 for 4,000 direct labor hours worked, the direct labor price variance is O $1,000 favorable. O $800 unfavorable. O $1,000 unfavorable. O $800 favorable. hp fg 18 17 16arrow_forward← Chapter 5 Homework Question 1 of 6 January February March The controller of Rather Production has collected the following monthly cost data for analyzing the behavior of electricity costs. April May June July August September October November December < (a) Total Electricity Costs $2,500 3,000 3,600 4,500 3,200 4,900 4,100 3,800 5,100 4,200 3,300 5,860 Total Machine Hours 300 350 500 690 400 700 650 520 680 630 350 -/1 720 E :arrow_forward
- PROBLEM 14: MMM Company started operations in 2019. The following data are abstracted from the company's production and sales records: 2019 2020 2021 of units Number produced Number of units sold Unit production cost 116,250 108,750 P 4.50 P 5.20 P 5.80 900,000 120,000 75,000 101,250 97,500 Sales revenue 600,000 975,000 19. Using the FIFO cost flow assumption, the gross profit for the year ended December 31, 2021 is: PROBLEM 15: The following quarterly cost data have been accumulated for New DDD Manufacturing, Inc.: Raw materials, 1/1/2022 Purchases of raw materials 10,000 units at P6.00 8,500 units at P7.00 11,000 units at P7.50 Raw materials transferred to work in process Work in process, 1/1/2022 Direct labor Manufacturing overhead Work in process, 3/31/2022 21,500 units 5,600 units at P13.50 P 250,000 325,000 4,200 units at P13.75 20. If New Dehi uses the FIFO method for valuing raw materials inventories, compute for the cost of goods manufactured for the quarter ended March 31,…arrow_forward0O The manufacturing costs of Mocha Industries for 3 months of the year are as follows: Total Cost Production April $105,050 2,100 units May 112,190 2,940 June 123,410 4,260 Using the high-low method, determine the (a) variable cost per unit and (b) the total fixed costs. Round "Cost per unit" answer to two decimal places. a. Variable cost per unit per unit b. Total fixed costs Previous Next 3:26 PM 53°F Sunny a, (中岁 12/14/2021 甲 # 五 144arrow_forwardView Policies Current Attempt in Progress A company expected its annual overhead costs to be $692920 and machine hours to equal 101900 hours. Actual overhead was $744100, and actual machine hours totalled 97400 hours. How much is the company's predetermined overhead rate to the nearest cent, assuming overhead is applied based on machine hours? O $7.30 O $6.80 O $7.64 O $7.11 e Textbook and Media Save for Later Attempts: 0 of 3 used Submit Answerarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning
- Pkg Acc Infor Systems MS VISIO CDFinanceISBN:9781133935940Author:Ulric J. GelinasPublisher:CENGAGE L
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Pkg Acc Infor Systems MS VISIO CD
Finance
ISBN:9781133935940
Author:Ulric J. Gelinas
Publisher:CENGAGE L
What is Risk Management? | Risk Management process; Author: Educationleaves;https://www.youtube.com/watch?v=IP-E75FGFkU;License: Standard youtube license