Chapter 2, Problem 6QQ
Program Description Answer
A project life cycle is actually a collection of project phases.
Hence, the correct option is “A”.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
28.
Which of the following life cycle model can be chosen if the development team has less experience on similar projects?
a.
Spiral
b.
Waterfall
c.
RAD
d.
Iterative Enhancement Model
Which one, waterfall or agile, do you believe is better suited for a project with well-defined needs and limited potential for failure? Why? Keep in mind that you need at least two references to back up your argument.
You are the project manager of a hybrid project incorporating the planning of a predictive project and the workflow of iterations of Agile. How will you likely manage changes to the project scope in this approach?
a. Schedule and cost change control
b. Process change control
c. Product backlog prioritization
d. No changes are allowed to the project scope once it has been baselined
Chapter 2 Solutions
Information Technology Project Management
Ch. 2 - What does it mean to take a systems view of a...Ch. 2 - Explain the four frames of organizations. How can...Ch. 2 - Prob. 3DQCh. 2 - Describe how organizational culture is related to...Ch. 2 - Discuss the importance of top management...Ch. 2 - What are the phases in a traditional project life...Ch. 2 - Prob. 7DQCh. 2 - Define globalization, outsourcing, virtual teams,...Ch. 2 - Prob. 1QQCh. 2 - Prob. 2QQ
Ch. 2 - Prob. 3QQCh. 2 - Prob. 4QQCh. 2 - Prob. 5QQCh. 2 - Prob. 6QQCh. 2 - Prob. 7QQCh. 2 - Prob. 8QQCh. 2 - Prob. 9QQCh. 2 - Prob. 10QQCh. 2 - Prob. 1ECh. 2 - Prob. 2ECh. 2 - Search the Internet for two interesting articles...Ch. 2 - Prob. 4ECh. 2 - Prob. 5ECh. 2 - Research the trend of using virtual teams. Review...Ch. 2 - Prob. 7ECh. 2 - Prob. 8ECh. 2 - Prob. 9E
Knowledge Booster
Similar questions
- Which of the following is not a typical reason that project teams would use a predictive approach versus an agile approach to managing a project? The project has unclear up-front requirements. The project team is inexperienced and dispersed. Large risks are involved. The completion date is fairly rigid.arrow_forwardList and describe the three major steps in executing the project plan.arrow_forwardIn Agile software development, a ________ is one time-boxed iteration of a continuous development cycle. scrum backlog c. sprint d. context diagram There are 3 popular methods for developing information systems. Which method focuses on using multiple iterations and prototypes to develop a system incrementally and depends on user feedback? Structured Traditional c. Agile d. O-O e. none of these There are 4 primary system changeover methods that can be used when implementing a new system. Which one of the following is not one of the methods? Pilot Parallel c. Prototype d. Direct Cutover e. Phased Which one of the following would not be an advantage in using the Agile method to develop a system? Late changes in the requirements can be accommodated Lots of customer involvement and feedback in the process Requirements are clear at the outset and…arrow_forward
- Spiral software process models are widely studied but seldom applied. Do you endorse the spiral model for real-world software? Does the spiral model match your project? . If no, please explain using the spiral model's five drawbacks?arrow_forwardSystem development cost is impacted by the development model used. Which of the following development models is considered the highest in terms of cost compared to the other models? Select One Waterfall model Spiral model Incremental model Agile mode Which of the following statements is TRUE about Waterfall development model? Select One In waterfall model, system components can be developed separately. Takes into consideration the change of the requirements during the development process. Waterfall model is very efficient for projects that have well-known requirements at the beginning of the project. Waterfall model focuses on the constant re-evaluation of the design and risks involved. Agile model is similar to Extreme Programming model in terms of: Select One Agile model and Extreme Programming model have a fixed number of development iterations Agile model is not similar to Extreme Programming model in any way. To make sure requirements change is handled in…arrow_forward(1) Which one does not belong to the generic process framework? Development Modeling Construction Deployment Communication Planning (2) Software project plan is used to define the software engineering work by describing: Select 4 correct answer(s) risks problem schedule feedbacks resources stakeholders technical tasks (3) Software does not wear out. True False (4) Which type is not related to the process flow? Parallel Evolutionary Linear Iterative Spiral (5) An Incremental Process adapts as changes occur. True Falsearrow_forward
- Which approach, Agile or waterfall, do you believe is the best suitable for a project with well defined criteria and a minimal chance of failure? Why? Why? Ensure that you reference at least two sources in order to substantiate your argument.arrow_forwardDo you think waterfall or Agile would be better for a project with clear objectives and little likelihood of failure? Why? Why? To support your claim, provide at least two references.arrow_forwardDescribe the steps you will take to accommodate altered project parameters. As the nature of business necessitates constant adaptation, which software development life cycle model should be implemented? Justify?arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
- Fundamentals of Information SystemsComputer ScienceISBN:9781337097536Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781285196145Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos CoronelPublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781305627482Author:Carlos Coronel, Steven MorrisPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781337097536
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781285196145
Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos Coronel
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning