PRIN.OF CORPORATE FINANCE
13th Edition
ISBN: 9781260013900
Author: BREALEY
Publisher: RENT MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 22, Problem 9PS
Timing options Look back at the Malted Herring option in Section 22-2. How did the company’s analysts estimate the present value of the project? It turns out that they assumed that the probability of low demand was about 45%. They then estimated the expected payoff as (.45 × 176) + (.55 × 275) = 230. Discounting at the company’s 15% cost of capital gave a present value for the project of 230/1.15 = 200.
- a. How would this present value change if the probability of low demand was 55%? How would it change if the project’s cost of capital was higher than the company cost of capital at, say, 20%?
- b. Now estimate how these changes in assumptions would affect the value of the option to delay.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Tomodachi Co plans to invest in either Projects M or N which are described below. The company's cost of capital is 15%, the market return is 15% and the risk-free rate is 5%. The beta for project M is 1.20 and the beta for project N is 1.40. What is the NPV for Project M when using the risk-adjusted discount rate method of project evaluation?
Initial Investment
Project M
$700,000
Project N
$780,000
Year
1
$300,000
$220,000
2
$300,000
320,000
3
$300,000
380,000
4
$300,000
460,000
or
You must decide firm which of the proposed projects should be accepted for the upcoming year since only $6 million is available. Which projects should be accepted?
Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $3,225,000. The project's expected cash flows are:
Year
Cash Flow
Year 1
$375,000
Year 2
-125,000
Year 3
500,000
Year 4
400,000
If the company's WACC is 8% and the project has the same risk as the firm's average project, what is the project's modified internal rate of return (MIRR)?
Should you accept or reject this project?
At a discount rate of 8% the Net Present Value (NPV) of a project is 65 million. At a discount rate of 11% the NPV of the project is 27 million.
What is the Internal Rate of Return (IRR) (correct to one decimal place) using linear extrapolation?
A. 13,9%
B. 13,1%
C. 12,9%
D. 12,1%
And explain this question
Which of the following options could explain an adverse sales price variance?
A. An unplanned summer sale had been used to increase sales volumes
B. The government raised the rate of value added tax in the budget
C. Cost inflation had been higher than expected which had to be passed on to customers in order to maintain margins
D. Discounts to customers had been withdrawn
Chapter 22 Solutions
PRIN.OF CORPORATE FINANCE
Ch. 22 - Real options Respond to the following comments. a....Ch. 22 - Prob. 2PSCh. 22 - Real options True or false? a. Real-options...Ch. 22 - Prob. 4PSCh. 22 - Real options Describe each of the following...Ch. 22 - Expansion options Look again at the valuation in...Ch. 22 - Expansion options Look again at Table 22.2. How...Ch. 22 - Prob. 8PSCh. 22 - Timing options Look back at the Malted Herring...Ch. 22 - Prob. 10PS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- Hemmingway, Inc. is considering a $5 million research and development (R&D) project. Profit projections appear promising, but Hemmingway’s president is concerned because the probability that the R&D project will be successful is only 0.50. Furthermore, the president knows that even if the project is successful, it will require that the company build a new production facility at a cost of $20 million in order to manufacture the product. If the facility is built, uncertainty remains about the demand and thus uncertainty about the profit that will be realized. Another option is that if the R&D project is successful, the company could sell the rights to the product for an estimated $25 million. Under this option, the company would not build the $20 million production facility. The decision tree follows. The profit projection for each outcome is shown at the end of the branches. For example, the revenue projection for the high demand outcome is $59 million. However, the cost of the R&D project ($5 million) and the cost of the production facility ($20 million) show the profit of this outcome to be $59 – $5 – $20 = $34 million. Branch probabilities are also shown for the chance events. Analyze the decision tree to determine whether the company should undertake the R&D project. If it does, and if the R&D project is successful, what should the company do? What is the expected value of your strategy? What must the selling price be for the company to consider selling the rights to the product? Develop a risk profile for the optimal strategy.arrow_forwardInvestment Timing Option: Option Analysis Rework Problem 14-1 using the Black-Scholes model to estimate the value of the option. Assume that the variance of the project’s rate of return is 0.0687 and that the risk-free rate is 8%. 14–1 Investment Timing Option: Decision-Tree Analysis Kim Hotels is interested in developing a new hotel in Seoul. The company estimates that the hotel would require an initial investment of $20 million. Kim expects the hotel will produce positive cash flows of $3 million a year at the end of each of the next 20 years. The project’s cost of capital is 13%. a. What is the project’s net present value? b. Kim expects the cash flows to be $3 million a year, but it recognizes that the cash flows could actually be much higher or lower, depending on whether the Korean government imposes a large hotel tax. One year from now, Kim will know whether the tax will be imposed. There is a 50% chance that the tax will be imposed, in which case the yearly cash flows will be only $2.2 million. At the same time, there is a 50% chance that the tax will not be imposed, in which case the yearly cash flows will be $3.8 million. Kim is deciding whether to proceed with the hotel today or to wait a year to find out whether the tax will be imposed. If Kim waits a year, the initial investment will remain at $20 million. Assume that all cash flows are discounted at 13%. Use decision-tree analysis to determine whether Kim should proceed with the project today or wait a year before deciding.arrow_forwardGiorgio Co. is looking at an investment project with an internal rate of return of 10.8%. The initial outlay for the investment is $90,000. The hurdle rate or minimum acceptable rate of return is 10.2%.arrow_forward
- A project has expected cash flows with a present value of $75 million. The annual standard deviation of the project's returns is 35%. The company can delay the start of the project by 1 year to find out more about the demand for the product. If the company decides to go ahead with the project after 1 year, the company needs to invest $50 million. The risk-free rate is 5% (continuously compounded). What is the value of the option to delay (in $ million)?arrow_forwardHuang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($64 million) Below average 0.20 (10 million) Average 0.50 12 million Above average 0.20 16 million Boom 0.05 30 million Calculate the project's expected NPV, standaarrow_forwardConsider a project with free cash flows in one year of $90,000 in a weak economy or $117,000 in a strong economy, with each outcome being equally likely. The initial investment required for the project is $80,000, and the project's cost of capital is 15%. The risk-free interest rate is 5%. c. Suppose that to raise the funds for the initial investment the firm borrows $45,000 at the risk-free rate and issues new equity to cover the remainder. In this situation, calculate the value of the firm's levered equity from the project. What is the cost of capital for the firm's levered equity? d. What is the basic goal of financial management with respect to capital structure? Is there an easily identifiable capital structure that will maximize the value of the firm? Why or why not?arrow_forward
- Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($34 million) Below average 0.20 (16 million) Average 0.50 12 million Above average 0.20 16 million Boom 0.05 28 million Calculate the project's expected NPV, standard deviation, and coefficient of variation. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13. Do not round intermediate calculations. Round your answers to two decimal places. E(NPV): million σNPV: million CV:arrow_forwardHuang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($72 million) Below average 0.20 (12 million) Average 0.50 12 million Above average 0.20 18 million Boom 0.05 38 million Calculate the project's expected NPV, standard deviation, and coefficient of variation. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13. Do not round intermediate calculations. Round your answers to two decimal places. is there a way to do the standard deviation in excel? i am having trouble with the formulaarrow_forwardConsider a project with free cash flows in one year of $90,000 in a weak economy or $117,000 in a strong economy, with each outcome being equally likely. The initial investment required for the project is $80,000, and the project's cost of capital is 15%. The risk-free interest rate is 5%. a. Assume that to raise the funds for the initial investment the firm borrows $80,000 at the risk-free rate, calculate the value of the firm's levered equity. b. Assume that to raise the funds for the initial investment the firm borrows $30,000 at the risk-free rate and issues new equity to cover the remainder. Suppose we end up with a weak economy one year from now. What will be the cash flow that equity holders receive?arrow_forward
- Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 13 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. Time: 0 1 2 3 4 5 Cash flow: −$295,000 $53,800 $72,000 $117,000 $110,000 $69,200 Use the MIRR decision rule to evaluate this project. (Do not round intermediate calculations and round your final answer to 2 decimal places.)arrow_forwardSuppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 13 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. Time: 0 1 2 3 4 5 Cash flow: −$255,000 $61,800 $80,000 $133,000 $118,000 $77,200 Use the MIRR decision rule to evaluate this project. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Should this be Accepted or Rejectedarrow_forwardSuppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 13 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. Time: 0 1 2 3 4 5 Cash flow: −$240,000 $64,800 $83,000 $139,000 $121,000 $80,200 Use the MIRR decision rule to evaluate this project. (Do not round intermediate calculations and round your final answer to 2 decimal places.) MIRR: ____.__%arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
- Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License