Chapter 23, Problem 6DQ
To determine
Direct labor variances:
The difference between the actual labor cost in the production and the
-
- Labor rate variance.
- Labor time variance.
To Discuss: Whether the controller’s remark was correct.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Keating& Associates is a law firm specializing in labor relations employee-related work. Keating & Associates received feedback from Punch, Inc., that its bid for the labor contract work was too high. This feedback prompted Keating to review its work activities and how they are reflected in its job-costing system. The review included the detailed analysis of how past jobs used the firm’s resources and interviews with personnel about what factors drive the level of indirect costs. Management concluded that a system with two direct-cost categories (professional partner labor and professional associate labor) and two indirect-cost categories (general support and secretarial support) would yield more accurate job costs. Budgeted information for 2016 related to two direct cost categories is as follows: Professional Professional Partner labor…
As an assistant cost accountant for Mississippi Industries, you have been assigned to re-
view the activity base for the predetermined factory overhead rate. The president, Tony
Favre, has expressed concern that the over- or underapplied overhead has fluctuated
excessively over the years.
An analysis of the company's operations and use of the current overhead rate (direct
labor cost) has narrowed the possible alternative overhead bases to direct labor cost and
machine hours. For the past five years, the following data have been gathered:
2014
2013
2012
2011
2010
$ 790,000
777,000
$ 13,000
$ 870,000
$ 935,000
$ 760,000
777,000
$ (17,000)
Actual overhead
$ 845,000
Applied overhead
(Over-) underapplied overhead
882,000
924,000
840,000
$ (12,000)
$
11,000
24
5,000
Direct labor cost
$3,885,000
$4,410,000
$4,620,000
$4,200,000
$3,885,000
Machine hours
93,000
104,000
111,000
100,400
91,600
As an assistant cost accountant for Mississippi Industries, you have been assigned to review the activity base for the predetermined factory overhead rate. The president, Tony Favre, has expressed concern that the over- or underapplied overhead has fluctuated excessively over the years.An analysis of the company’s operations and use of the current overhead rate (direct labor cost) has narrowed the possible alternative overhead bases to direct labor cost and machine hours. For the past five years, the following data have been gathered:
Attachment
In teams:1. Calculate a predetermined factory overhead rate for each alternative base, assuming that rates would have been determined by relating the total amount of factory overhead for the past five years to the base.2. For each of the past five years, determine the over- or underapplied overhead based on the two predetermined overhead rates developed in part (1).3. Which predetermined overhead rate would you recommend? Discuss the basis for…
Chapter 23 Solutions
Working Papers, Chapters 1-17 for Warren/Reeve/Duchac's Accounting, 26th and Financial Accounting, 14th
Ch. 23 - What are the basic objectives in the use of...Ch. 23 - What is meant by reporting by the principle of...Ch. 23 - What are the two variances between the actual cost...Ch. 23 - The materials cost variance report for Nickols...Ch. 23 - a. What are the two variances between the actual...Ch. 23 - Prob. 6DQCh. 23 - Would the use of standards be appropriate in a...Ch. 23 - a. Describe the two variances between the actual...Ch. 23 - If variances are recorded in the accounts at the...Ch. 23 - Briefly explain why firms might use nonfinancial...
Ch. 23 - Prob. 23.1APECh. 23 - Direct materials variances Dvorak Company produces...Ch. 23 - Prob. 23.2APECh. 23 - Direct labor variances Dvorak Company produces a...Ch. 23 - Prob. 23.3APECh. 23 - Factory overhead controllable variance Dvorak...Ch. 23 - Prob. 23.4APECh. 23 - Factory overhead volume variance Dvorak Company...Ch. 23 - Prob. 23.5APECh. 23 - Standard cost journal entries Dvorak Company...Ch. 23 - Prob. 23.6APECh. 23 - Income statement with variances Prepare an income...Ch. 23 - Prob. 23.7APECh. 23 - Prob. 23.7BPECh. 23 - Prob. 23.1EXCh. 23 - Prob. 23.2EXCh. 23 - Budget performance report Genie in a Botile...Ch. 23 - Direct materials variances The following data...Ch. 23 - Direct materials variances Silicone Engine Inc....Ch. 23 - Standard direct materials cost per unit from...Ch. 23 - Standard product cost, direct materials variance...Ch. 23 - Direct labor variances The following data relate...Ch. 23 - Direct labor variances Reincarnation Bicycle...Ch. 23 - Direct tabor variances Greeson Clothes Company...Ch. 23 - Direct labor standards for nonmanufacturing...Ch. 23 - Direct labor standards for a service company One...Ch. 23 - Direct labor variances for a service company...Ch. 23 - Direct materials and direct labor variances At the...Ch. 23 - Flexible overhead budget Leno Manufacturing...Ch. 23 - Flexible overhead budget Wiki Wiki Company has...Ch. 23 - Factory overhead cost variances The following data...Ch. 23 - Factory overhead cost variances Blumen Textiles...Ch. 23 - Factory overhead variance corrections The data...Ch. 23 - Factory overhead cost variance report Tannin...Ch. 23 - Recording standards in accounts Cioffi...Ch. 23 - Recording standards in accounts The Assembly...Ch. 23 - Income statement indicating standard cost...Ch. 23 - Prob. 23.24EXCh. 23 - Nonfinancial performance measures Alpha University...Ch. 23 - Direct materials and direct labor variance...Ch. 23 - Flexible budgeting and variance analysis I Love My...Ch. 23 - Direct materials, direct labor, and factory...Ch. 23 - Factory overhead cost variance report Tiger...Ch. 23 - Standards for nonmanufacturing expanses Code Head...Ch. 23 - Direct materials and direct labor variance...Ch. 23 - Flexible budgeting and variance analysis Im Really...Ch. 23 - Direct materials, direct labor, and factory...Ch. 23 - Factory overhead cost variance report Feeling...Ch. 23 - Prob. 23.5BPRCh. 23 - Genuine Spice Inc. began operations on January 1...Ch. 23 - Ethics in Action Dash Riprock is a cost analyst...Ch. 23 - Prob. 23.2CPCh. 23 - Variance interpretation You have been asked to...Ch. 23 - Variance interpretation Vanadium Audio Inc. is a...
Knowledge Booster
Similar questions
- You mention changes and revisions to the standard cost systems. If you were the Operations manager of a manufacturing firm, what control would you have in place to assure those changes were proper and accurate? What assertions would apply here?arrow_forwardComment on the following statement made by a plant manager: “Meetings with my plant accountant are frustrating. All he wants to do is pin the blame on someone for the many variances he reports.”arrow_forwardPat Miranda, the new controller of Vault Hard Drives, Inc., has just returned from a seminar on the choice of the activity level in the predetermined overhead rate. Even though the subject did not sound exciting at first, she found that there were some important ideas presented that should get a hearing at her company. After returning from the seminar, she arranged a meeting with the production manager, J. Stevens, and the assistant production manager, Marvin Washington. Pat: I ran across an idea that I wanted to check out with both of you. It’s about the way we compute predetermined overhead rates. J.: We’re all ears. Pat: We compute the predetermined overhead rate by dividing the estimated total factory overhead for the coming year, which is all a fixed cost, by the estimated total units produced for the coming year. Marvin: We’ve been doing that as long as I’ve been with the company. J.: And it has been done that way at every other company I’ve worked at, except at most…arrow_forward
- As a plant accountant, you have been directed by the new plant manager to expense all manufacturing costs as they are incurred. Do you agree with this directive? Explain your answer, including comments concerning product and period costs.arrow_forwardThe management of a liquid cleaning product company is trying to decide whether to install a job or process costing system. The manufacturing vice president has stated that job costing gives the best control because it is possible to assign costs to specific lots of goods. The controller, however, has stated that job costing requires too much record-keeping. Would a process costing system meet the manufacturing vice president’s control objectives? Explain.arrow_forwardWhat is the purpose of the following control procedures (i.e., what threats is it designed to mitigate)? b. Reconciliation of labor costs (based on job-time ticket data) with payroll (based on time card data).arrow_forward
- Amber Company produces custom framing. For one job, the trainee assigned to cut the mat set the mat dimensions incorrectly into the computer. The mat was unusable and had to be discarded; another mat was cut to the correct dimensions. How is the cost of the spoiled mat handled? What additional costs can occur with the spoiled mat? What about retraining for the employee or punishment costs?arrow_forwardWhat internal control procedures would best prevent or detect the following problems? 1.The "rush-order" tag on a partially completed production job became detached from the materials and lost, resulting in a costly delay. 2. A production worker entering job-time data on an online terminal mistakenly entered 3,000 instead of 300 in the "quantity-completed" field. 3. A production worker entering job-time data on an online terminal mistakenly posted the completion of operation 562 to production order 7569 instead of production order 7596. 4.The quantity-on-hand balance for a key component shows a negative balance.arrow_forwardEthics and the Manager Terri Ronsin had recently been transferred to the Home Security Systems Division of National Home Products. Shortly after taking over her new position as divisional controller, she was asked to develop the division’s predetermined overhead rate for the upcoming year. The accuracy of the rate is important because it is used throughout the year and any underapplied or overapplied overhead is closed out to Cost of Goods Sold at the end of the year. National Home Products uses direct labor-hours in all of its divisions as the allocation base for manufacturing overhead. To compute the predetermined overhead rate, Terri divided her estimate of the total manufacturing overhead for the coming year by the production manager’s estimate of the total direct labor-hours for the coming year. She took her computations to the division’s general manager for approval but was quite surprised when he suggested a modification in the allocation base. Her conversation with the general…arrow_forward
- I REGREAT THAT I CANNOT FIND THE ANSWER OF QUESTION 6 & 7 IN THE WEBSIT? COULD YOU PLEASE HELP? Lisa Ronsin had recently been transferred to the Home Security Systems Division of National Home Products. Shortly after taking over her new position as divisional controller, she was asked to develop the division’s predetermined overhead rate for the upcoming year. The accuracy of the rate is important because it is used throughout the year and any underapplied or overapplied overhead is closed out to Cost of Goods Sold at the end of the year. National Home Products uses direct labor-hours in all of its divisions as the allocation base for manufacturing overhead. (6) What alternative ethical actions could Lisa take in this situation? Identify at least THREE alternative actions. (7) What is your proposed solution?arrow_forwardEthics Case. At Symond Company, production workers in the Painting Department are paid on the basis of productivity. The labor time standard for a unit of production is established through periodic time studies conducted by Douglas Management Consultants. In a time actual time required to complete a specific task by a worker is observed. Allowances are then made for preparation time, rest periods, and cleanup time. Bill Carson is one of several veterans in the Painting Department .Bill is informed by Douglas that he will be used in the time study for the beginning of a new product . The findings will be the basis for establishing the labor time standard of the next 6 months.During the test, Bill deliberately slows his normal work pace in an effort to obtain a labor time standard that will be easy to meet. Because it is a new product, the Douglas representatives who conducted the test is unaware that Bill did not give the test his best effort.arrow_forward"As long as the total actual factory overhead cost is not significantly different from the total standard applied factory overhead cost for the period, there is no need to conduct further analyses of the factory overhead variances." Do you agree? Why, or why not?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College