FUND. ACCOUNTING PRINCIPLES >CUSTOM<
FUND. ACCOUNTING PRINCIPLES >CUSTOM<
24th Edition
ISBN: 9781307417692
Author: Wild
Publisher: MCG/CREATE
bartleby

Concept explainers

Question
Book Icon
Chapter 26, Problem 5BPSB
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-1:

To Calculate:

Payback period for the project

Expert Solution
Check Mark

Answer to Problem 5BPSB

Payback period for the project is 2.4 years

Explanation of Solution

Payback period for the project is calculated as follows;

    Cash Flows Accumulated Cash Flows
    Period 1 $ 300,000 $ 300,000
    Period 2 $ 350,000 $ 650,000
    Period 3 $ 400,000 $1,050,000
    Period 4 $ 450,000 $1,500,000
    Payback Period = 2 Years + (800000-650000)/400000 = 2.4 Years
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-2:

To Calculate:

Breakeven time for the investment

Expert Solution
Check Mark

Answer to Problem 5BPSB

Breakeven time for the investment is 2.8 Years

Explanation of Solution

Breakeven time for the investment is calculated as follows:

    Cash Flows PV of $1 (10%)PV Accumulated PV
    A BC=A*B
    Period 1 $ 300,000 0.9091 $ 272,730.00 $ 272,730.00
    Period 2 $ 350,000 0.8264 $ 289,240.00 $ 561,970.00
    Period 3 $ 400,000 0.7513 $ 300,520.00 $ 862,490.00
    Period 4 $ 450,000 0.6830 $ 307,350.00 $ 1,169,840.00
    Breakeven Time = 2 Years +(800000-561970)/300520 =2.8 Years
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-3:

To Calculate:

The Net Present Value of the investment

Expert Solution
Check Mark

Answer to Problem 5BPSB

The Net Present Value of the investment is $369,840

Explanation of Solution

The Net Present Value of the investment is calculated as follows:

    Cash Flows PV of $1 (10%)PV
    A BC=A*B
    Period 1 $ 300,000 0.9091 $ 272,730
    Period 2 $ 350,000 0.8264 $ 289,240
    Period 3 $ 400,000 0.7513 $ 300,520
    Period 4 $ 450,000 0.6830 $ 307,350
    Total Present value $1,169,840
    Less: Initial investment $(800,000)
    Net Present value $ 369,840
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-4:

If the management should invest in the project

Expert Solution
Check Mark

Answer to Problem 5BPSB

Yes, the management should invest in the project.

Explanation of Solution

The Net Present Value of the investment is calculated as follows:

    Cash Flows PV of $1 (10%)PV
    A BC=A*B
    Period 1 $ 300,000 0.9091 $ 272,730
    Period 2 $ 350,000 0.8264 $ 289,240
    Period 3 $ 400,000 0.7513 $ 300,520
    Period 4 $ 450,000 0.6830 $ 307,350
    Total Present value $1,169,840
    Less: Initial investment $(800,000)
    Net Present value $ 369,840

The Net Present Value of the investment is $369,840; hence the management should invest in the project.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education