Financial Management: Theory & Practice
16th Edition
ISBN: 9781337909730
Author: Brigham
Publisher: Cengage
expand_more
expand_more
format_list_bulleted
Question
Chapter 26, Problem 6P
Summary Introduction
Calculate the value of option using Black Scholes model.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The return expected from the project no. 542 is 22 percent. The standard deviation of these return is 11 percent. If returns from the project are normally distributed. What is the chance that the project will result in a rate of return above 33 percent?
You're comparing two project and need to determine which is preferred. Both projects have an expected return of 15%. Project "A" has a standard deviation of 2.5. Project "B" has a variance of 9. A risk averse investor would pick:
Question 24 options:
Project "B" because the variance for project "A" is unkown
Project "A" because it has a lower standard deviation than project "B" but the same expected return
Project "A" because the standard deviation of project "B" is unknown
Project "B" because it has a lower variance than project "A"
An expansion project that has an expected return of 25% and a standard deviation of 30%. Find the project's coefficient of variation?
a) 1.32
b) 0.83
c) 1.20
d) 1.39
e) 1.26
Chapter 26 Solutions
Financial Management: Theory & Practice
Knowledge Booster
Similar questions
- Investment Timing Option: Option Analysis Rework Problem 14-1 using the Black-Scholes model to estimate the value of the option. Assume that the variance of the project’s rate of return is 0.0687 and that the risk-free rate is 8%. 14–1 Investment Timing Option: Decision-Tree Analysis Kim Hotels is interested in developing a new hotel in Seoul. The company estimates that the hotel would require an initial investment of $20 million. Kim expects the hotel will produce positive cash flows of $3 million a year at the end of each of the next 20 years. The project’s cost of capital is 13%. a. What is the project’s net present value? b. Kim expects the cash flows to be $3 million a year, but it recognizes that the cash flows could actually be much higher or lower, depending on whether the Korean government imposes a large hotel tax. One year from now, Kim will know whether the tax will be imposed. There is a 50% chance that the tax will be imposed, in which case the yearly cash flows will be only $2.2 million. At the same time, there is a 50% chance that the tax will not be imposed, in which case the yearly cash flows will be $3.8 million. Kim is deciding whether to proceed with the hotel today or to wait a year to find out whether the tax will be imposed. If Kim waits a year, the initial investment will remain at $20 million. Assume that all cash flows are discounted at 13%. Use decision-tree analysis to determine whether Kim should proceed with the project today or wait a year before deciding.arrow_forwardAPT An analyst has modeled the stock of Crisp Trucking using a two-factor APT model. The risk-free rate is 6%, the expected return on the first factor (r1) is 12%, and the expected return on the second factor (r2) is 8%. If bi1 = 0.7 and bi2 = 0.9, what is Crisp’s required return?arrow_forwardStandard deviation versus coefficient of variation as measures of risk Greengage, Inc., a successful nursery, is considering several expansion projects. All the alternatives promise to produce an acceptable return. Data on four possible projects appear in the following table: Project Expected return Range Standard deviation A 12.6% 5.7% 2.6% B 11.6% 6.2% 3.9% C 11.9% 5.9% 3.6% D 11.8% 6.1% 3.3% a. Which project is least risky, based on the range of possible outcomes? b. Which project has the lowest standard deviation? Explain why standard deviation may not be an entirely appropriate measure of risk for purposes of this comparison. c. Calculate the coefficient of variation for each project. Which project do you think Greengage's owners should choose?arrow_forward
- A project under consideration has an internal rate of return of 16% and a beta of 0.9. The risk-free rate is 6%, and the expected rate of return on the market portfolio is 16%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? c. What is the required rate of return on the project if its beta is 1.90? (Do not round intermediate calculations. Enter your answer as a whole percent.) d. If the project's beta is 1.90, should the project be accepted?arrow_forwardStandard deviation versus coefficient of variation as measures of risk Greengage Inc., a successful nursery, is considering several expansion projects. All the alterna-tives promise to produce an acceptable return. Data on four possible projects follow. Project Expected return Range Standard deviationA 12.0% 4.0% 2.9% B 12.5 5.0 3.2 C 13.0 6.0 3.5 D 12.8 4.5 3.0 a. Which project is least risky, judging on the basis of range? b. Which project has the lowest standard deviation? Explain why standard deviation may not be an entirely appropriate measure of risk for purposes of this comparison.c. Calculate the coefficient of variation for each project. Which project do you think Greengage’s owners should choose? Explain why.arrow_forwardAssume two investment opportunities have identical expected values of $60,000. Investment A has a variance of 5,000 and investment B has a variance of 18,000. We would expect a risk loving investor to prefer (Select all that applies) Group of answer choices a) A because it has more risk. b) B because of its higher potential earnings. c) A because it provides higher potential earnings. d) B because it has more risk.arrow_forward
- A project under consideration has an internal rate of return of 13% and a beta of 0.6. The risk-free rate is 8%, and the expected rate of return on the market portfolio is 13%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? Y/N c. What is the required rate of return on the project if its beta is 1.60? (Do not round intermediate calculations. Enter your answer as a whole percent.) d. If project's beta is 1.60, should the project be accepted? Y/Narrow_forward10) Given an optimal risky portfolio with expected return of 15%, standard deviation of 26%, and a risk free rate of 5%, what is the slope of the best feasible CAL? A) 0.64 B) 0.27 C) 0.08 D) 0.38 E) 0.36 Provide explanation for the correct answer.arrow_forwardPart a State Pr(a) ra Pr(b) rb 1 0.2 10% 0.25 12% 2 0.6 15% 0.40 20% 3 0.2 20% 0.35 18% Given the probability distribution above, determine (Calculate) and compare the: Expected return (means) Variance Standard deviation Part b How important is risk to returns and what are the key elements that must be analyzed in this regard before an investment decision is made? Discuss in no more than 200 words.arrow_forward
- A project has an expected net present value of $50,000 with a standard deviation of the net present value of $20,000. Assume that NPV is normally distributed. What is the probability that the project will have a negative NPV?arrow_forwardA project under consideration has an internal rate of return of 16% and a beta of 0.9. The risk free rate is 6% and the expected rate of return on the market portfolio is 16%. A. What is the required rate of return? B. Should the project be accepted? C. What is the required rate of return on the project if it's beta is 1.90? D. If the projects beta is 1.90 should the project be accepted?arrow_forwarda. Use the following information: E[rXOM] = 15.6%, standard deviationXOM = 15.9% E[rMS]=29.7%, standard deviationMS = 35.2% Correlation of returns: ρXOM,MS = 0.139, rf=10% If the optimal amount to invest in the first asset (w) is 0.43, what is the variance of the risky portfolio when w=0.43? (write in decimal format using 5 decimal places) b. When choosing the best point of the POS (the curved line connecting two possible assets you can invest in) you need to find the point that: 1.Has the greatest difference between it’s return and the risk free rate, thus leading to the best return 2. You must solve for the optimal y allocation in order to find the best point on the POS 3. The point with the lowest standard deviation 4. The point with the greatest Sharpe ratioarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT