Textbook Question
Chapter 3, Problem 11P
The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their durations, and what activities each must precede:
ACTIVITY | DURATION (WEEKS) | PRECEDES | |||
A (start) | 1 | B, C | |||
B | 1 | E | |||
C | 4 | F | |||
E | 2 | F | |||
F (end) | 2 | --- |
- a. Draw an AON diagram of the project, including activity durations.
- b. Define the critical path, listing all critical activities in chronological order.
- c. What is the project duration (in weeks)?
- d. What is the slack (in weeks) associated with any and all noncritical paths through the project?
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A project's activities must be completed in the sequence indicated below.
Activity
Immediately Preceding Activity
Duration in Weeks
A
-
3
B
-
20
C
-
15
D
-
10
E
-
5
F
A
4
G
D
3
H
D, E
10
I
F
3
J
B
10
K
G, H
7
L
B, I
5
The project ends with the intersection of activities: C, J, K and L
1- Use CPM to construct (Draw) the project Network and find the critical path.
2- How long is the project expected to take
The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in Chicago, their durations, and what activities each must precede: a) Draw an AOA diagram of the project, including activity durations.b) Define the critical path, listing all critical activities in chronological order.c) What is the project completion time (in weeks)?d) What is the slack (in weeks) associated with any and all noncritical paths through the project?
You are provided with the following information for a project, with activity durations given in weeks:
Activity Immediate Optimistic Most Likely Pessimistic
Predecessor Time (a) Time (m) Time (b)
A ____ 2 3 4
B ____ 2 4 6
C A 1 2 3
D B 3 6 9
E C, D 7 8 9
F D 4 7 10
G E 3 4 5
H E, F…
Chapter 3 Solutions
MYOMLAB W/O PEARSON ETEXT--INSTANT ACCE
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - Prob. 20DQCh. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - Prob. 2PCh. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Prob. 8PCh. 3 - Task time estimates for the modification of an...Ch. 3 - The activities described by the following table...Ch. 3 - The following is a table of activities associated...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below.ActivityDuration (days)Preceding activitiesA3NoneB3NoneC4AD9AE4B and CRequired:1. Draw a network diagram representing the sequence of activities and the dependence between them.2. Determine how long it will take to complete the job by conducting the forward pass3. By conducting the backward pass, identify the critical path and the non-critical path(s).Note:The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.arrow_forwardYou are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…arrow_forwardGiven the following information, a. Draw a project network. b. Complete the forward and backward pass, compute activity slack, and identify the critical path. c. How sensitive is the network schedule? Briefly justify your answer? d. Which activities have free slack? Activity Predecessor Duration (days) A None 10 B None 20 C A 10 D A 30 E B 10 F C 30 G C, D 20 H D, E 10 I F, G, H 20arrow_forward
- The estimated times and immediate predecessorsfor the activities in a project at George Kyparis’s retinal scan-ning company are given in the following table. Assume thatthe activity times are independent. a) Calculate the expected time and variance for each activity.b) What is the expected completion time of the critical path?What is the expected completion time of the other path inthe network?c) What is the variance of the critical path? What is the vari-ance of the other path in the network?d) If the time to complete path A–C is normally distributed,what is the probability that this path will be finished in22 weeks or less?e) If the time to complete path B–D is normally distributed,what is the probability that this path will be finished in22 weeks or less?f) Explain why the probability that the critical path will befinished in 22 weeks or less is not necessarily the probabil-ity that the project will be finished in 22 weeks or less.arrow_forwardA project has these activities, precedence relationships, and activity durations: Activity Immediate Predecessor Activity Activity Duration (Week)a * 3b * 4c * 3d c 12e b 5f a 7g e,f 3 a. Draw a CPM network for the project. b. Provide an overview for the project by computing the duration for each path. c. What is the critical path? What is the project's estimated duration?arrow_forwardA plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below. Activity Duration (days) Preceding activities A 3 None B 3 None C 4 A D 8 A E 2 B and C Required: 1. Draw a network diagram representing the sequence of activities and the dependence between them. 2. Determine how long it will take to complete the job by conducting the forward pass 3. By conducting the backward pass, identify the critical path and the non-critical path(s). Note: The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.arrow_forward
- a) Draw an AON diagram of the project, including activity durations. b) Define the critical path, listing all critical activities in chronological order. c) What is the project duration (in weeks)? d) What is the slack (in weeks) associated with any and all noncritical paths through the project?arrow_forwardGiven the following network, What is the critical path? How long will it take to complete this project? The duration, in days, follows the letter of each activity. Can activity B be delayed without delaying the completion of the project? If so, how many days?arrow_forwardConsider the following activities for a project. Answer the questions below. a. Assume the durations given are high confidence, create a network chart (don’t considerresources yet), and identify the critical path. What is the duration of the project? b. You aren’t quite ready to apply the critical chain project management yet, but you do want toeliminate multi-tasking. Eliminate any resource contention in your network. Identify the criticalpath now? What is the duration of the project? c. Apply the critical chain project management approach to this project. Create a new view ofyour project network, include a project buffer and any needed feeding buffers. What is the criticalchain? What is the duration of the project now?arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forwardPlease, I need help because I have no idea how to do any of these. 11. Building a backyard swimming pool consists of nine major activities. The activities and their immediate predecessors are shown. Develop the project network. For question number 12, you need to refer to question number 11. Also the first picture is for #11 and second picture(image) is for #12 12. Assume that the activity time estimates (in days) for the swimming pool construction project in Problem 11 are as follows: a. What are the critical activities? b. What is the expected time to complete the project? c. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY