Rich Cole Control Devices, Inc., produces custombuilt relay devices for auto makers. The most recent project undertaken by Cole requires 14 different activities. Cole’s managers would like to determine the total project completion time (in days) and those activities that the along the critical path. The appropriate data are shown in the following table.
a) What is the probability of being done in 53 days?
b) What date results in a 99% probability of completion?
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Additional Business Textbook Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Principles Of Operations Management
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Operations Management
Business in Action
- General Foundry’s project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing? What is the crash cost per week per activity and the total cost of crashing? TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSORS NORMAL CRASH NORMAL CRASH A — 2 1 22,000 23,000 B — 3 1 30,000 34,000 C A 2 1 26,000 27,000 D B 3 2 48,000 49,000 E C 4 2 56,000 58,000 F C 3 2 30,000 30,500 G D, E 5 2 80,000 83,000 H F, G 2 1 16,000 19,000arrow_forwardDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Activity Time (weeks) Time (weeks) A B 3 1 3 4 3 2 2 a) Based on the given information regarding the activities for the project, the project length с D E F G 2 8 6 Normal Cost $2,100 $2,300 $500 $2,400 $900 $3,400 $1,600 weeks Total Cost with Crashing Immediate Predecessor(s) $2,700 $3,000 $500 $2,700 $1,350 $4,900 $2,200 С D, Earrow_forwardThe following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.arrow_forward
- Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: No Type Cumulative Budgeted Cost (CBC) 2 Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) 1 3 TOTAL RM i. ii. iii. iv. 64,000 68,000 54,000 100,000 Percentage 64.0 Cost performance Index (CPI) [hint: CEV/CAC] Cost variance (VC) [hint: CEV-CAC] 68.0 54.0 a) Based on question 2(a), calculate and elaborate the various of indicators of cost performance for this project based on the respective below: 100.0 Forecasted cost of completion (FCAC) with action taken [hint: TBC/CPI] Forecasted cost of completion (FCAC) without any action taken [hint: CAC + [TBC-CEV]arrow_forwarda. Determine the expected activity completion times. b. Identify the critical path. *Please answer letter A and B above. Note: to = optimistic, tm = most likely, and te = expected time.arrow_forwardDevelop a project network. Determine the expected project completion time. What is the probability that the project completion time will be completed? With in 2 weeks earlier than the expected project completion time? With in 1.5 week more than the expected project completion time ?arrow_forward
- Coleman Rich Control Devices, I nc., producescustom-built relay devices for auto makers. The most recent projectundertaken by Rich requires 14 different activities. Rich's managerswould like to determine the total project completion time(in days) and those activities that lie along the critical path. Theappropriate data are shown in the following table.a) What is the probability of being done in 53 days?b) What date results in a 99% probability of completion?arrow_forwardDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Normal Activity Time (weeks) Time (weeks) Cost ABCDEFG 4 2 3 8 6 3 4 3 1 3 4 3 2 2 $2,100 $2,300 $600 $2,400 $800 $3,400 $1,400 Total Cost with Crashing Immediate Predecessor(s) $2,750 $2,900 $600 $2,680 $1,100 $4,600 $1,900 a) Based on the given information regarding the activities for the project, the project length b) The total cost required for completing this project on normal time = $ 13000. | | A B C D, E = 16 weeks. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 70. d) The maximum weeks by which the project can be reduced by crashing = 7 weeks. Total cost of crashing the…arrow_forwardPERT-CPMYu and Mi Company is planning to computerize its accounting system. Its IT consultant has determined thefollowing activities required to complete this project together with the time estimates and precedence relationships. a. Determine the expected project completion time and the variance.b. What is the project’s critical path?c. Determine the probability that the project will be completed in 40 weeks or less.arrow_forward
- By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B Barrow_forwardList two outputs for each of the Project Risk Management processes (note that the Implement Risk Responses process is not discussed in this chapter)arrow_forwardColeman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: Activity A B с D E F G a) The expected completion time of the project = a 4 1 6 5 1 2 1 Time (days) m 6 2 6 8 9 3 7 b 7 3 6 11 18 6 8 Immediate Predecessor(s) A A B, C D D Activity a H 4 I 1 J 2 K 8 2 1 6 M N days (round your response to two decimal places). Time (days) = m 4 6 5 9 4 2 8 b 6 8 7 11 6 3 10 Immediate Predecessor(s) E, F G, H K L, M The activities that represent the project's critical path are b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 53 days or less = decimal places). c) Using the standard normal table, the…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.