The appropriate PERT diagram for the given activity. Introduction: The longest time path for a network is known as critical path. The method of project management in which only one time factor per activity is used is known as critical path method.
The appropriate PERT diagram for the given activity. Introduction: The longest time path for a network is known as critical path. The method of project management in which only one time factor per activity is used is known as critical path method.
To determine: The appropriate PERT diagram for the given activity.
Introduction:
The longest time path for a network is known as critical path. The method of project management in which only one time factor per activity is used is known as critical path method.
b)
Summary Introduction
To determine: The critical path and project completion time.
Introduction:
The longest time path for a network is known as critical path. The method of project management in which only one time factor per activity is used is known as critical path method.
c)
Summary Introduction
To determine: The probability that the project will take more than 49 time periods to complete.
Introduction:
The longest time path for a network is known as critical path. The method of project management in which only one time factor per activity is used is known as critical path method.