Textbook Question
Chapter 3, Problem 29P
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
If per day indirect cost is 2000 per week, crash the following project to the point where the cost will be minimum.
A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of the task, and have spent $10,500. a. Determine the indices: AC, PV, and EV b. Derive the values for cost and schedule variances, as well as cost performance and schedule performance indices. Is this project ahead or behind on schedule, and is it ahead or behind on budget?
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. a) What is the expected (estimated) time for activity C?b) What is the variance for activity C?c) Based on the calculation of estimated times, what is the criticalpath?d) What is the estimated time of the critical path?e) What is the activity variance along the critical path?f) What is the probability of completion of the project before week 36?
Chapter 3 Solutions
Operations Management: Sustainability and Supply Chain Management, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - Prob. 20DQCh. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - Prob. 2PCh. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Prob. 8PCh. 3 - Task time estimates for the modification of an...Ch. 3 - The activities described by the following table...Ch. 3 - The following is a table of activities associated...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Additional Business Textbook Solutions
Find more solutions based on key concepts
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
What is precedent, and how does it affect common law?
Business in Action
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Peabody Coal Corporation recently completed the final feasibility report for a new general ledger accounting system. It has hired a consulting firm to program and install the new system. The consulting firm is charging $350,000 for the remaining tasks to be performed. These tasks are to be performed over the next 10 months as detailed in the Gantt chart in the diagram. The consulting firm is extremely concerned with the project staying on schedule because it is receiving a flat fee. The release of the final payment is contingent upon the system performing as stated in the contract and upon Peabody receiving appropriate documentation of the system.Requireda. Prepare a PERT diagram and indicate the critical path.b. What happens to the time frame of the implementation of the project if the manufacturer is 4 weeks late shipping the hardware?c. What happens if the data conversion does not go smoothly and takes an additional 3 weeks? d. Who should conduct the postimplementation review?…arrow_forwardPERT-CPM Maurice Publishing Inc. has a contract with Joan who authored the manual “Basics of ProjectManagement for Industrial Engineering and Engineering Management Students”. The simplifiedactivities associated with the production of the manual are given below. We are asked to developthe associated network for the project.arrow_forwardPROJECT A Project A is a planning, design and implementation infrastructure development project (about GHS 15 million in value and expected to take about three years from the start of planning to completion), which is well advanced in its planning component. While the project is progressing well in terms of time, cost and quality, there are a number of sustainability and stakeholder management issues with it. This project is being undertaken in an environmentally sensitive area in which leave several property owners who are quite concerned with the impact of the project on their environment. They are concerned that a thorough environmental risk assessment has not been undertaken with respect to the long-term impact on the sensitive bushland area in which they live. They are also concerned that completion of the project, through providing the basis for significant property development and destruction of bushland, will forever change the social fabric of their region. They have formed a…arrow_forward
- PROJECT A Project A is a planning, design and implementation infrastructure development project (about GHS 15 million in value and expected to take about three years from the start of planning to completion), which is well advanced in its planning component. While the project is progressing well in terms of time, cost and quality, there are a number of sustainability and stakeholder management issues with it. This project is being undertaken in an environmentally sensitive area in which leave several property owners who are quite concerned with the impact of the project on their environment. They are concerned that a thorough environmental risk assessment has not been undertaken with respect to the long-term impact on the sensitive bushland area in which they live. They are also concerned that completion of the project, through providing the basis for significant property development and destruction of bushland, will forever change the social fabric of their region. They have formed a…arrow_forwardThe following represents a project that should be scheduled using CPM a. Complete the table b. Draw the Network Diagram c. What is the critical path? d. What is the expected project completion time?' e. What is the probability of completing this project within 16 days?arrow_forwardThe Cove at UP is looking to open a new location. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. \ tasks predecessors task duration start 0 A start 7 B A 20 C A 34 D B 39 E C,D 6 F D 15 G E,F 33 end G 0 Guillermo has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: \ Metric Description ES Early start time for task EF Early finsh time for task LS Late start time for task LF Late finsh time for task TS Total slack for task FS Free slack for task IS Independent slack for task SS safety slack for task Please provide the CPM result for each of the following metrics: ES_{end} = LS_{D} = TS_{D} = EF_{G} = LF_{G} =arrow_forward
- For conducting a project seven activities should be performed but maximum availablemanpower is 17. Task duration and manpower requirement is given below. Project managersaid, “It is possible to complete the project without leveling the manpower". Evaluate thestatement of the PM. (Justified or Not-Justified)arrow_forwardExplain the following project situations using just the following schedule and cost information: a. PV = $10,000, AC = $12,000, EV = $10,500b. PV = $10,000, AC = $10,000, EV = $10,000c. PV = $10,000, AC = $9,000, EV = $10,000a. PV = $10,000, AC = $10,000, EV = $9,000arrow_forwardScott and Associates, Inc., is an accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experience of the leaders, the various leader-client assignments differ in terms of projected completion times. The possible assignments and the estimated completion times in days are as follows: Client Project Leader 1 2 3 Jackson 10 16 32 Ellis 14 22 40 Smith 22 24 34 Formulate the problem as a linear program, and solve. What is the total time required?arrow_forward
- Prepare the AOA network diagram,Calculate the total minimum completion time of the project, Crash the above project by 4 weeks and find the total crashing costarrow_forwardUse the following network and the data to perform the following: a) Prepare the manpower loaded Gantt chart with total floats of this project using early start and late times. Plot the manpower resource profile that shows the total number of laborers per day over the course of the project. Prepare the Gantt chart and the resource profile using the early start and finish dates of activities (not necessary to produce the late start and finish charts). b) Level the manpower resource given the constraint that the owner has only 14 workers to allocate to this project per day. Please try to do in excel. Thannksarrow_forwardAn architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity. Job Description Predecessor Expected time in days A Prepare preliminary sketches NA 2 B Outline specifications NA 1 C Prepare drawings A 3 D Write specifications A B 2 E Run prints C D 1 F Have specifications printed B D 3 G Assemble bid package E F 1arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY