Fundamentals Of Construction Estimating
4th Edition
ISBN: 9781337399395
Author: Pratt, David J.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 3RQ
What is the difference between an estimator’s quantity takeoff and a foreman’s material takeoff?
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
What is the difference between an estimator’s quantity takeoff and a foreman’s material takeoff?
How did you get these values here? Can you show the solutions.
a) What is valuation? Discuss the complete process of valuation of civil engineering structure
Chapter 3 Solutions
Fundamentals Of Construction Estimating
Ch. 3 - What is the objective of a quantity takeoff?Ch. 3 - Why is it recommended that estimators follow a...Ch. 3 - What is the difference between an estimator’s...Ch. 3 - Prob. 4RQCh. 3 - What are the two components that make up a takeoff...Ch. 3 - In what order are dimensions entered onto the...Ch. 3 - Why should a figured dimension be used in...Ch. 3 - Why should an estimator include headings and side...Ch. 3 - The cost of transportation of materials has to be...Ch. 3 - What level of accuracy should the estimator pursue...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Discuss subcontracting in construction. use 2 peer-reviewed articles (Published within the last 4 years)arrow_forwardSolve the following problem step by step so I can understand the calculations and the concept and theroy. Please show clear and neat workarrow_forwardIn the corner of a cellar is a pyramidal heap of coal. The base of the heap is an isosceles right triangle whose hypotenuse is 20 ft., and the altitude of the heap is 7 ft. If there are 35 cu. ft. in a ton of coal, how many tons are there in this heap? (Please provide diagram, thank you)arrow_forward
- G...Discuss on the various costs associated with aggregatearrow_forwardA contractor estimates that he could finish a project in 15 days if he has 20 men. At the start, he hired 10 men then after 6 days, 10 more men are added. How many days was the project delayed? A. 6 B 5 € 4 D 3 E None of the abovearrow_forwardConclusion of effect of modernization to estimating < Estimating are the fundamental of building construction as it provides all parties on information such as the overall cost of the building, the material needed to construct a building, resources needed to fulfil trades of work and even information on contractual aspect of construction project. (Please include your findings on the matters discuss above – Technologies is good initiative to estimation, it is not good, etc…)arrow_forward
- At the beginning of a job, what are the most important things to be determined?arrow_forwardA firm must make a bid on a contract to make 12 units of a new product. Engineering analysis indicates that the nature of this product and its manufacturing processes resemble those for the firm’s current model, so the firm decides to base its bid on the 85 percent learning rate it experienced on that model. If engineers estimate that the first unit will require 10 hours of labor, how many hours will the 12 unit require? How many hours will the firm take to make all 12 units?arrow_forwardI am still having trouble undertsanding this, can you please explain it betterarrow_forward
- Make a sketch of the flow chart depicting the steps in, and the cyclic nature of, a contractor’s cost accounting, cost reporting, and cost control systemarrow_forward(From Fundamentals of construction estimating book 4th edition ) 8.) If the output is expected to be on the high end of the scale, what would be the labor price to install 210 lb asphalt shingles based in Figure 12.5 data?arrow_forwardA can finish a work in 18days. B can do the same job in half the time taken A. Then working together what part of the same work they can finish in a day?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
What Is A Construction Takeoff? | Are They Still Necessary In Quantity Surveying?; Author: Metroun Quantity Surveying;https://www.youtube.com/watch?v=uTWoDPtcOjg;License: Standard Youtube License