Chapter 3, Problem 4DQ

Explanation of Solution

Key outputs of each process group:

The project management includes different processes and that processes provides different outputs as follows:

  • Project initiation
    • Stakeholder registration
    • Stakeholder management strategy
    • Project charter
  • Project planning
    • Activity list
    • Project management plan
    • Project schedule
    • Project scope statement
    • Risk management
    • Work breakdown structure
  • Project executing
    • Deliverables
    • Modification requests
    • ...

Blurred answer
Students have asked these similar questions
MCQ27: In CRC based design, a CRC Team consists of :(a) one or two users representatives(b) All(c) project co-ordinators(d) one or two system analysts
Process data flow diagram questions might help you explain and evaluate a technique.
Q: what is Unified process model? Write Unified process Characteristics. Explain with the help of Diagram.
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
MIS
Computer Science
ISBN:9781337681919
Author:BIDGOLI
Publisher:Cengage
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning