EBK INFORMATION TECHNOLOGY PROJECT MANA
8th Edition
ISBN: 8220101360656
Author: SCHWALBE
Publisher: YUZU
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 3, Problem 6QQ
A work breakdown structure, project schedule, and cost estimates are outputs of the ____________ process.
- a. initiating
- b. planning
- c. executing
- d. monitoring and controlling
- e. closing
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
The time of an activity in a phase of a project given as optimistic 1 day, most likely 3 days, pessimistic 5 days, then activity estimate time will be_______________.
a. 3 days
b. 5 days
c. 1 day
d. 4 days
A project has been defined to contain the following list of activities along with their required times for completion:
Construct Gantt Chart, Network Diagram and Critical Path for the below chart:
Immediate
Activity No.
Predecessors
ABCDEFGHI
Activity
Collect requirements
Analyze processes
Analyze data
Design processes
Design data
Design screens
Design reports
Program
Test and Document
Install
Time (weeks)
3
2447NWONN
6
3
5
A
B
B
C
C,D
D,E
F,G
G
H₁I
10 Which of the following is a classic organizational structure?
A Functional
B Projectized
C Composite
D Matrix
11 Defining a new project or a new phase of an existing project relates
to
A Initiating process.
B. Planning process
C Scope management process
D. Control process
12 If you are developing a Project Management Plan, how should you determine
the level of detail to be included in the plan?
A Always only provide a summary or high level plan
B Include only the details your manager specifically requested
C Always provide the maximum level of detail possible
D. Provide the level of detail based on the project complexity and application area
13 Midway through a project, a project manager determined that the project was
running way behind schedule. If the project manager needs to shorten the project
schedule, without changing the project scope, which of the following schedule
compression techniques could be applied?
A. Crashing
B. Reserve Analysis
C. Forecasting
D. Last Tracking
14.…
Chapter 3 Solutions
EBK INFORMATION TECHNOLOGY PROJECT MANA
Ch. 3 - Prob. 1QQCh. 3 - ____________ processes include coordinating people...Ch. 3 - Prob. 3QQCh. 3 - Prob. 4QQCh. 3 - Prob. 5QQCh. 3 - A work breakdown structure, project schedule, and...Ch. 3 - Prob. 7QQCh. 3 - ____________ involves measuring progress toward...Ch. 3 - Which of the following is not a typical reason...Ch. 3 - Many people use ____________ to have a standard...
Ch. 3 - Briefly describe what happens in each of the five...Ch. 3 - Approximately how much time do good project...Ch. 3 - Why do organizations need to tailor project...Ch. 3 - Prob. 4DQCh. 3 - What are some of the typical challenges project...Ch. 3 - Prob. 6DQCh. 3 - Research a project management method, such as...Ch. 3 -
Read the “ResNet Case Study,” which is available...Ch. 3 - Prob. 4ECh. 3 - Prob. 5ECh. 3 - Prob. 6ECh. 3 - Prob. 7ECh. 3 - Prob. 8ECh. 3 - Prob. 9E
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- What is the value of a statement of vision and objectives? Why is it needed before a project plan is developed?arrow_forward____________ involves measuring progress toward project objectives and taking corrective actions. Initiating Planning Executing Monitoring and controlling Closingarrow_forwardWho is the best judge of effort estimates for project tasks and action steps? Why?arrow_forward
- Answer the following questions based on project planning Software Engineering: 1. Explain the looping process that occurs from the project scheduling! What criteria can be used to assume the loop process can be terminated?2. What is the difference between forward scheduling and backward scheduling, use the example [https://iansommerville.com/software-engineering-book/web/planning-activities/]? Also compare the Critical Path results of the two scheduling approaches?3. Is there a difference in Release Planning vs. Iteration Planning in making software using an Agile approach?4. Explain the level of accuracy of the Project Cost Estimation with COCOMO II?5. Explain how to get the estimated source line of code (SLOC)?arrow_forward9. A Project can be characterized as _____ . a. Every project may not have a unique and distinct goal. b. Project is routine activity or day-to-day operations. c. Project does not comes with a start time and end time. d. None of the above.arrow_forwardA project estimator is working on estimates for a project that is very similar to a previous project, in that it has many of the same features and those features have similar costs. Each feature or deliverable will represent the same percentage of the total cost as it did for the previous project. He is using the _________ method of top-down estimating. a. ratio b. consensus c. apportion d. function point e. learning curvesarrow_forward
- QUESTION 1 Assume you are the project manager in the software development team at Software Solutions assigned to work on the finance app. Project planning is undeniably one of the most important tasks a project manager will have to do. Planning takes place at three stages in a project life cycle. Explain to your project team what project planning entails, as well as planning during the THREE (3) stages in a project life cycle. Include in your explanation the concept of project scheduling and what exactly will be estimated during the software project.arrow_forwardExplain the notion of project planning. Which considerations should be taken into account while estimating schedules?arrow_forward-----------------is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date. a. Parkinson’s Law b. Scrum c. Critical path analysis d. Critical chain schedulingarrow_forward
- What process involves identifying and controlling the functional and physical design characteristics of products and their support documentation, and ensures that the descriptions of the project's products are correct and complete? 37 Select one: O a. Project management information systems O b. NPV analysis O c. Configuration management O d. Project time managementarrow_forwardQUESTION 12 Which of the following is not the activity of Project Planning? O Define the problem Build prototype O Produce the project schedule O Confirm feasibilityarrow_forwardA project has been defined to contain the following list of activities along with their required times for completion. Task Immediate Activity 1 Collect requirements 2 3 4 5 6 a. b. Analyses process and data Design process, screen, and report Program Test and document Install Show the critical path? Time (week) 3 5 4 6 7 4 Predecessors 1 1 2 2,3 4,5 Calculate the earliest completion time for the project?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Security (MindTap Cours...Computer ScienceISBN:9781337102063Author:Michael E. Whitman, Herbert J. MattordPublisher:Cengage LearningManagement Of Information SecurityComputer ScienceISBN:9781337405713Author:WHITMAN, Michael.Publisher:Cengage Learning,
- Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningFundamentals of Information SystemsComputer ScienceISBN:9781305082168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Security (MindTap Cours...
Computer Science
ISBN:9781337102063
Author:Michael E. Whitman, Herbert J. Mattord
Publisher:Cengage Learning
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
9.1.2 Software Development Approaches; Author: EIToppo;https://www.youtube.com/watch?v=Z9znuSQ7Sz8;License: Standard YouTube License, CC-BY