Question
Chapter 4, Problem 111P
Summary Introduction
To determine: The number of workers to be working and the way allocation should be made for the next five weeks.
Linear programming:
It is a mathematical modeling procedure where a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A furniture factory makes two types of wooden tables,large and small. See the flowchart below .Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart. a. What is the capacity of the system, and what is thebottleneck? b. What are the throughput times for batches of large and small tables? c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?
Consider a two-step process that handles three types of customers. Each resourceis staffed by one employee. Type 1 customers spend 5 minutes at resource 1 and 2 minutesat resource 2. Type 2 customers also spend 5 minutes at resource 1, but spend 10 minutes atresource 2. Finally, type 3 customers spend no time at resource 1 and 8 minutes at resource2. Each hour, the demand is 10 customers of type 1, 4 customers of type 2, and 2 customers oftype 3. Where in the process is the bottleneck? What is the flow rate for each customer type?
A book binder has one printing press, one binding machine and manuscripts of 7 different books. The times required for performing printing and binding operations for different books are shown below.
Book
1
2
3
4
5
6
7
Printing time (hours)
20
90
80
20
120
15
65
Binding time (hours)
25
60
75
30
90
35
50
Decide the optimum sequence of processing of books in order to minimize the total time required to bring out all the books.
Chapter 4 Solutions
Practical Management Science
Ch. 4.2 - Prob. 1PCh. 4.2 - Prob. 2PCh. 4.2 - Prob. 3PCh. 4.2 - Prob. 4PCh. 4.2 - Prob. 5PCh. 4.2 - Prob. 6PCh. 4.3 - Prob. 7PCh. 4.3 - Prob. 8PCh. 4.3 - Prob. 9PCh. 4.3 - Prob. 10P
Ch. 4.3 - Prob. 11PCh. 4.3 - Prob. 12PCh. 4.4 - Prob. 13PCh. 4.4 - Prob. 14PCh. 4.4 - Prob. 15PCh. 4.4 - Prob. 16PCh. 4.4 - Prob. 17PCh. 4.4 - Prob. 18PCh. 4.4 - Prob. 19PCh. 4.5 - Prob. 20PCh. 4.5 - Prob. 21PCh. 4.5 - Prob. 22PCh. 4.5 - Prob. 23PCh. 4.5 - Prob. 24PCh. 4.5 - Prob. 25PCh. 4.6 - Prob. 26PCh. 4.6 - Prob. 27PCh. 4.6 - Prob. 28PCh. 4.6 - Prob. 29PCh. 4.7 - Prob. 30PCh. 4.7 - Prob. 31PCh. 4.7 - Prob. 32PCh. 4.7 - Prob. 33PCh. 4.7 - Prob. 34PCh. 4.7 - Prob. 35PCh. 4.7 - Prob. 36PCh. 4.7 - Prob. 37PCh. 4.7 - Prob. 38PCh. 4.7 - Prob. 39PCh. 4.7 - Prob. 40PCh. 4.8 - Prob. 41PCh. 4.8 - Prob. 42PCh. 4.8 - Prob. 43PCh. 4.8 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63PCh. 4 - Prob. 64PCh. 4 - Prob. 65PCh. 4 - Prob. 66PCh. 4 - Prob. 67PCh. 4 - Prob. 68PCh. 4 - Prob. 69PCh. 4 - Prob. 70PCh. 4 - Prob. 71PCh. 4 - Prob. 72PCh. 4 - Prob. 73PCh. 4 - Prob. 74PCh. 4 - Prob. 75PCh. 4 - Prob. 76PCh. 4 - Prob. 77PCh. 4 - Prob. 78PCh. 4 - Prob. 79PCh. 4 - Prob. 80PCh. 4 - You want to take out a 450,000 loan on a 20-year...Ch. 4 - Prob. 82PCh. 4 - Prob. 83PCh. 4 - Prob. 84PCh. 4 - Prob. 85PCh. 4 - Prob. 86PCh. 4 - Prob. 87PCh. 4 - Prob. 88PCh. 4 - Prob. 89PCh. 4 - Prob. 90PCh. 4 - Prob. 91PCh. 4 - Prob. 92PCh. 4 - Prob. 93PCh. 4 - Prob. 94PCh. 4 - Prob. 95PCh. 4 - Prob. 96PCh. 4 - Prob. 97PCh. 4 - Prob. 98PCh. 4 - Prob. 99PCh. 4 - Prob. 100PCh. 4 - Prob. 101PCh. 4 - Prob. 102PCh. 4 - Prob. 103PCh. 4 - Prob. 104PCh. 4 - Prob. 105PCh. 4 - Prob. 106PCh. 4 - Prob. 107PCh. 4 - Prob. 108PCh. 4 - Prob. 109PCh. 4 - Prob. 110PCh. 4 - Prob. 111PCh. 4 - Prob. 112PCh. 4 - Prob. 113PCh. 4 - Prob. 114PCh. 4 - Prob. 115PCh. 4 - Prob. 116PCh. 4 - Prob. 117PCh. 4 - Prob. 118PCh. 4 - Prob. 119PCh. 4 - Prob. 120PCh. 4 - Prob. 121PCh. 4 - Prob. 122PCh. 4 - Prob. 123PCh. 4 - Prob. 124PCh. 4 - Prob. 125PCh. 4 - Prob. 126PCh. 4 - Prob. 127PCh. 4 - Prob. 128PCh. 4 - Prob. 129PCh. 4 - Prob. 130PCh. 4 - Prob. 131PCh. 4 - Prob. 132PCh. 4 - Prob. 133PCh. 4 - Prob. 134PCh. 4 - Prob. 135P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- EU Company manufactures two different types of life vests (A and B) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see Figure 1). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product’s price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. EU can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $6 per hour for an entire week, regardless of how much the worker is used. Total labor costs per week are fixed. Variable overhead costs are $1,500/week. The plant operates one 8-hour shift per day, or 40 hours/week. Which of the three workstations, W,…arrow_forwardA bank recently finished construction of a new building in the downtown business district. You have been asked to help them arrange the various departments of its check processing division to minimize the workflow (Summation LxD) in its operations. The movement of checks between departments is shown in the table below. Department 4 (the check distribution department) must be in the room with the elevator. Only lateral movement is allowed (no diagonal movement allowed) from the center of one department to the center of the destination department. Each department is 50 feet x 50 feet. What is the Summation LxD of the recommended layout? 10,640 feet 15,960 feet 26,600 feet 38,800 feet None of the above Which of the potential layouts shown above should be recommended to the bank management? (Below is the potential layouts) Layout A Layout B Layout C Layout D None of the abovearrow_forwardA production line is a set of sequential operations established in a factory plant where components are assembled to make a finished product or where materials are put through a refining process to produce an end-product that is suitable for onward consumption. Ford have seven production lines in their manufacturing plant for their automotive parts where each production line produces 120, 100, 80, 116, 77, 94, 112 output per day. (a) As the Production Manager at Ford, you are required to submit the daily report of the production plant. Calculate the mean, median, and mode from the data based on the output that has been provided. (b) Also calculate the three critical parameters for measuring spread in the following ways: Range Variance Standard Deviationarrow_forward
- An order for 200 units of a product is processed on work centers A and B. The set up time on A is 45 minutes and the run time is 5 minutes per piece. The set up time on B is 40 minutes and the run time is 8 minutes per piece. The wait time between the two operations is 2 hours. The move time between A and B is 15 minutes. Wait time after operation B is 1 hour and the move time into stores is 50 minutes. There is no queue at either work station. Calculate the total manufacturing lead time for the order.arrow_forwardA process improvement team is working to improve the production output at the Johnson Manufacturing plant’sHeader Cell that manufactures a key component, headers, used in commercial air conditioners. A header is partof the circulatory system of a commercial air conditioner that moves coolant between various components suchas the evaporator coil and the condenser coil. Currently, the header production cell is scheduled separately fromthe main work in the plant. Often, individual headers are not sequenced to match the product they go into on thefinal assembly line in a timely fashion, and so the product can sit in queue waiting for a headerarrow_forwardRaquel’s Landscaping Company has contracted for several landscaping jobs. Each job requires preparing the areas (identifying the locations and types of plants, preparing the soil, etc.) and then planting the trees, bushes, and shrubs. The expected time for each of the jobs is shown next. Job Preparingthe Area (days) Planting(days) R 3 2 S 1 3 T 4 5 U 8 5 V 6 4 W 4 3 Raquel is concerned with efficiency. She believes it is probably more efficient to use SPT (shortest processing time) as her priority rule. (a) Develop a sequence using SPT based on processing time for preparing the area. (If two of more jobs have the same processing time, list them alphabetically.) Preparing the Area select a job select a job select a job…arrow_forward
- A producer has three products, A, B, and C, which are composed from many of the same raw materials and subassemblies by the same skilled workforce. Each unit of product A uses 15 units of Raw Material X, one Purge System Subassembly, one Case, one Power Cord, three Labour Hours in the Assembly Department, and one Labour Hour in the Finishing Department. Each unit of product B uses 10 units of Raw Material X, five units of Raw Material Y, two Purge System Subassemblies, one Case, one Power cord, five Labour Hours in the Assembly Department, and 90 minutes in the Finishing Department. Each unit of product C uses five units of Raw Material X, 25 units of Raw Material Y, two Purge System Subassemblies, one Case, a Power Cord, seven Labour Hours in the Assembly Department, and Three Labour Hours in the Finishing Department. Labour between the Assembly and Finishing departments is not transferable, but workers within each department work on any of the three products. There are three…arrow_forwardA producer has three products, A, B, and C, which are composed from many of the same raw materials and subassemblies by the same skilled workforce. Each unit of product A uses 15 units of Raw Material X, one Purge System Subassembly, one Case, one Power Cord, three Labour Hours in the Assembly Department, and one Labour Hour in the Finishing Department. Each unit of product B uses 10 units of Raw Material X, five units of Raw Material Y, two Purge System Subassemblies, one Case, one Power cord, five Labour Hours in the Assembly Department, and 90 minutes in the Finishing Department. Each unit of product C uses five units of Raw Material X, 25 units of Raw Material Y, two Purge System Subassemblies, one Case, a Power Cord, seven Labour Hours in the Assembly Department, and Three Labour Hours in the Finishing Department. Labour between the Assembly and Finishing departments is not transferable, but workers within each department work on any of the three products. There are three…arrow_forwardPrevost Chemicals manufactures an industrial solvent at its only processing plant. A liquid chemical and labor are the two primary inputs. All other resources are included in manufacturing overhead. The plant never has any work-in-process or finished goods inventories. Information from the previous four periods of production follows: Period 1 Period 2 Period 3 Period 4 Chemical input (gallons) 125,000 129,280 128,000 120,000 Labor input (hours) 12,500 11,200 15,000 10,100 Solvent sales (gallons) 110,000 113,120 120,000 103,020 Average price of chemical per gallon $ 2.00 $ 2.10 $ 1.95 $ 2.25 Average wage rate per hour 28.00 26.00 31.00 34.00 Average sales price per gallon 10.26 10.00 9.80 10.60 Manufacturing overhead (total) 236,000 245,312 245,400 243,080 Required: c. Compute the total factor productivity for the four periods.arrow_forward
- Metal frames for kick scooters are manufactured in two stages: Stamping and assembly. Each frame is made up of two pieces: one part A and one part B. Currently, the stamping machine rotates its production between 120 part A’s and 120 part B’s. In the stamping machine, setup times and production rates for each part are follows: Part A Part B Setup time (mins) 70 110 Production rate (parts per hour) 80 80 Completed parts move to assembly stage only when the entire batch is produced. At assembly, parts are assembled manually to form the finished products. The two parts and a number of small purchased components are required for each unit of final product. Each product requires 30 minutes of labor time to assemble. There are 15 workers in assembly. There is sufficient demand to sell every scooter the system can make. At the current batch size, what is the capacity of stage 1 (stamping) in [units per hour]? At the current batch size, which stage is the…arrow_forwardGreen Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/40 of a day and 1/75 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop. A T1 truck and a C1 car yield profits of $275 and $225, respectively, per vehicle sold. The aim of the objective function for Green Vehicle Inc. should be to Maximize the objective value. The optimum solution is: Number of trucks to be produced per day = nothing (round your response to two decimal places).arrow_forward(Electro Corporation) The Electro Corporation manufactures two electrical products: air conditioners and fans. The assembly process for each is similar in that both require a certain amount of wiring and drilling. Each air conditioner takes 3 hours of wiring and 2 hours of drilling. Each fan must go through 2 hours of wiring and 1 hour of drilling. During the next production period, at most 240 hours of wiring time are available and at most 140 hours of drilling time may be used. Each air conditioner sold yields a profit of $25. Each fan assembled may be sold for a $15 profit. Formulate an LP of this product mix problem to find the best combination of air conditioners and fans for the highest total profit.max pX 1 + qX 2 (Total profit) s.t. aX 1 + bX 2 u (Wiring) cX 1 + dX 2 v (Drilling) X 1, X 2 0(Hint: Let X1 = number of air conditioners and X2 = number of fans)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,