Solid Waste Engineering
3rd Edition
ISBN: 9781305635203
Author: Worrell, William A.
Publisher: Cengage Learning,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 4, Problem 4.12P
To determine
The other cost to be recommended for the calculation.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What are the ways in which to store the tirfor machine?
A contractor estimates that
he could finish a project in
15 days if he has 20 men. At
the start, he hired 10 men
then after 6 days, 10 more
men are added. How many
days was the project
delayed?
A. 6
B 5
€ 4
D 3
E None of the above
How do Labor, materials, and equipment involve considerable risks?
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Please solve the remaining sub parts. Thank youarrow_forwardA client plans to construct a manufacturing plant that involves multiple engineering disciplines. Calculate the total engineering fees including taxes based on the following: Mechanical Works, $1,540,000 Electrical Works, $1,780,000 Earth Works, $950,000 Civil Works, $2,125,100 Environmental Works, $1,325,000 Basis B fees = 9% There are no office fees Taxes = 13%arrow_forwardWhat is meant by the following expressions?a. CIFb. 2/10 E.O.M.c. 2/10 net 30d. ROGe. Bill of ladingarrow_forward
- A light manufacturing firm has set up a project for develop- ing a new machine for one of its production lines. The most likely estimated cost of the project itself is $1,000,000, but the most optimistic estimate is $900,000 while the pessimists predict a project cost of $1,200,000. The real problem is that even if the project costs are within those limits, if the project itself plus its implementation costs exceed $1,425,000, the project will not meet the firm’s NPV hurdle. There are four cost categories involved in adding the prospective new machine to the production line: (1) engineering labor cost, (2) nonengineering labor cost, (3) assorted material cost, and (4) production line downtime cost. The engineering labor requirement has been estimated to be 600 hours, plus or minus 15 percent at a cost of $80 per hour. The nonengineering labor requirement is esti- mated to be 1,500 hours, but could be as low as 1,200 hours or as high as 2,200 hours at a cost of $35 per hour. Assorted…arrow_forwardI am still having trouble undertsanding this, can you please explain it betterarrow_forwardHi! help me with this please. Thank you so much! TRUE OR FALSE. EXPLAIN. Resale value is exactly the same as scrap value.arrow_forward
- Calculate the formwork material cost per use, given the following:Purchase cost = $25/sf; gross area of forms for each use = 4,000 sf x 1.15 = 4,600 sfExpected to be used for five years, 60 times each yearSalvage value = 10%Annual interest rate = 6%arrow_forwardHow did you get these values here? Can you show your solutions.arrow_forwardDetermine the Average Cost if the total cost of the production is $150 and the total numbers of production unit is $100.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,