Textbook Question
Chapter 4, Problem 6CQ
Which of the following statements about takt time and cycle time is true?
- a. Takt time only depends on demand, not capacity. Cycle time does depend on capacity.
- b. Takt time only depends on capacity, not demand. Cycle time depends on demand.
- c. Takt time and cycle time only depend on capacity.
- d. Takt time and cycle time only depend on demand.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which of the following statements about takt time and cycle time is true?a. Takt time only depends on demand, not capacity. Cycle time does depend on capacity.b. Takt time only depends on capacity, not demand. Cycle time depends on demand.c. Takt time and cycle time only depend on capacity.d. Takt time and cycle time only depend on demand.
Please do not give solution in image formate thanku
Some of your constraints have slack. What does that mean?
Select one:
A. Slack indicates how much one additional unit of the resource is worth.
B. If more of the resource were available, then profit could increase.
C. There is more of the resource than is needed for the best solution.
D. Slack indicates the total number of hours.
Consider Bruno who manages an underwriting team in an insurance firm. Recently, the management of Bruno’s firm informed him of their decision to create a new risk assessment team, consisting of data scientists with machine learning expertise, and reduce the size of Bruno’s underwriting team. Bruno’s underwriting team will now work with the new risk assessment team in order to determine whether to provide insurance to applicants.
Graphically illustrate the impact of the management’s restructuring decision on the firm’s production function. Your diagram should have the amount of human intelligence on the horizontal axis and the number of decisions on whether to provide insurance on the vertical axis. Fully label your diagram. Note that there are no actual numbers given in this question: you may make them up or simply use appropriate notations. Briefly explain the key information of your diagram.
Chapter 4 Solutions
OPERATIONS MANAGEMENT (LL)-W/ACCESS
Ch. 4 - Prob. 1CQCh. 4 - Prob. 2CQCh. 4 - Prob. 3CQCh. 4 - Prob. 4CQCh. 4 - Prob. 5CQCh. 4 - Which of the following statements about takt time...Ch. 4 - Prob. 7CQCh. 4 - Prob. 8CQCh. 4 - How does the target manpower change as the demand...Ch. 4 - What happens to the target manpower if the labor...
Ch. 4 - Which of the following actions does not relate to...Ch. 4 - Prob. 12CQCh. 4 - Prob. 13CQCh. 4 - Prob. 14CQCh. 4 - Specialization typically leads to a higher average...Ch. 4 - Prob. 16CQCh. 4 - Prob. 17CQCh. 4 - Prob. 18CQCh. 4 - Prob. 1PACh. 4 - Prob. 2PACh. 4 - Prob. 3PACh. 4 - Prob. 4PACh. 4 - Prob. 5PACh. 4 - Prob. 6PACh. 4 - Prob. 1C
Additional Business Textbook Solutions
Find more solutions based on key concepts
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Mary Williams, owner of Williams Products, is evaluating whether to introduce a new product line. After thinkin...
Operations Management: Processes and Supply Chains (11th Edition)
What is precedent, and how does it affect common law?
Business in Action
The Big Black Bird Company (BBBC) has a large order for special plastic-lined military uniforms to be used in a...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Mack's guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically, out of the 100 guitars that begin production each month, only 82 percent are considered good enough to sell. The other 18 percent are scrapped due to quality problems that are identified after they have completed the production process. Each guitar sells for $260. Because some of the production process is automated, each guitar only requires 88 labor hours. Each employee works an average of 160 hours per month. Labor is paid at $10 per hour, materials cost is $42 per guitar, and overhead is $4,200. a. The labor productivity ratio for Mack's guitar fabrication shop is $26.65 per hour. b. The multifactor productivity ratio for Mack's guitar fabrication shop is (Enter your response rounded to two decimal places.)arrow_forwardMack's guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically, out of the 100 guitars that begin production each month, only 80 percent are considered good enough to sell. The other 20 percent are scrapped due to quality problems that are identified after they have completed the production process. Each guitar sells for $260. Because some of the production process is automated, each guitar only requires 10 labor hours. Each employee works an average of 160 hours per month. Labor is paid at $10 per hour, materials cost is $42 per guitar, and overhead is $4,000.a. The labor productivity ratio for Mack's guitar fabrication shop is $___per hour. (Enter your response rounded to two decimal places.) b.The multifactor productivity ratio for Mack's guitar fabrication shop is __(Enter your response rounded to two decimal places.) After some study, the operations manager Darren Funk recommends 3 options to improve the company's multifactor…arrow_forwardConsider a process consisting of three resources. Assume there exists unlimited demandfor the product.• Resource 1 has a processing time of 6 minutes per unit.• Resource 2 has a processing time of 3 minutes per unit.• Resource 3 has a processing time of 5 minutes per unit.All three resources are staffed by one worker.a. Draw a process flow diagram of this process.b. What is the capacity of resource 2?c. What is the bottleneck in the process?d. What is the utilization of resource 2?e. How long does it take the process to produce 200 units starting with an empty system,assuming this is a worker-paced process?arrow_forward
- Mack's guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically, out of the 100 guitars that begin production each month, only 82 percent are considered good enough to sell. The other 18 percent are scrapped due to quality problems that are identified after they have completed the production process. Each guitar sells for $240. Because some of the production process is automated, each guitar only requires 10 labor hours. Each employee works an average of 160 hours per month. Labor is paid at $10 per hour, materials cost is $40 per guitar, and overhead is $3,800. Part 2 a. The labor productivity ratio for Mack's guitar fabrication shop isarrow_forwardCubway, the sandwich shop, is run by Jim, Tim and Kim. When a customer arrives, Jim spends 5 minutes taking order from the customer. After this, Tim prepares bread and Kim prepares filling for the order. These activities are performed in parallel, and take 6 and 12 minutes respectively. Jim then assembles the bread and filling, which takes 4 minutes of his time. Finally, Tim spends 1 minutes in delivering the order and taking payment. What is maximum number of sandwiches Cubway can make per hour? (In other words, what is the capacity of the process in sandwiches per hour?)arrow_forward1. A work system has five stations that have process times of 5, 12, 4, 9, and 8. What is the throughput time of the system? A) 9 B) 18 C) 4 D) 7 E) 12 2. Outsourcing manufacturing is also known as: A) concurrent manufacturing. B) contract manufacturing. C) hollow manufacturing. D) sublease manufacturing E) license manufacturing.arrow_forward
- A supervisor drafts the department's hiring plan for the next six months and decides how many new employees will be needed. According to the time horizon, this is a ------- lan. A Long-term B Intermediate C-Program D-Short-term E Projectarrow_forward2-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”, and “inspect”. If the capacity of activity “cook” determines the process capacity, which of the following statements are true? a- Activity “cook” is a bottleneck activity. b- The activity time of all the other five activities is shorter than activity "cook". c- Cycle time of the process of making hotdogs is equal=1/capacity of activity “cook”. d- Increasing the capacity of activity “grind” can increase the capacity of the process of making hotdogs. All statements are correct Only statement 'b' is correct Only statements 'a' and 'b' are correct Only statements 'a', 'b' and 'c' are correct Only statement 'a' is correct Only statement 'd' is correctarrow_forwardHow does the target manpower change as the demand rate increases?a. The target manpower increases.b. The target manpower stays the same.c. The target manpower decreases.d. Cannot determine from the given information.arrow_forward
- What is the maximum utilization a resource can achieve?a. A value equal to the demandb. A value equal to the capacityc. There is no maximum utilization.d. 1.00arrow_forwardConsider a process consisting of five resources that are operated 8 hours per day. Theprocess works on three different products, A, B, and C: Demand for the three different products is as follows: product A, 40 units per day;product B, 50 units per day; and product C, 60 units per day.a. What is the bottleneck?b. What is the flow rate for each flow unit, assuming that demand must be served in the mixdescribed above (i.e., for every four units of A, there are five units of B and six units of C)?arrow_forwardHRD System at PT. Angin Ribut wants to add a sub system to handle employee leave and overtime. The leave allowance provided by PT Angin Ribut is 12 days per year, however each year it will increase by 1 day until the maximum leave allowance reaches 20 days. Leave can be taken per half day. More than three hours will count as half a day. Overtime process is similar to leave, can be taken per half day. Every time an employee applies for leave, he must get approval from his immediate supervisor. If approved, the annual leave allowance will be reduced according to the number of days on the leave request. For each agreement on overtime, the employee's leave allowance will increase according to the number of overtime days in the employee's request. An administrator is responsible for granting leave per year. The leave allowance will be forfeited if it is not used until March of the following year, except with the approval of the President Director, the leave allowance can be extended. The…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY