A company must decide which type of machine to buy, and how many units of that type, given the following information:
Product demand and processing times for the equipment are:
a. How many machines of each type would be required to handle demand if the machines will operate 8 hours a day, 250 days a year, and what annual capacity cushion in processing time would result for each?
b. With high certainty of annual demand, which type of machine would be chosen if that was an important consideration?
c. If purchasing and operating costs are taken into account, which type of machine would minimize total costs, given your answer for part a? Operating costs are $6/hr for type 1 and $5/hr for type 2.
a)
To determine: The number of machines of each type required to handle the demand and its capacity.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Determine the number of machines of each type required and its capacity:
It is given that the machines will operate 60 minutes per hour, 8 hours per day and 250 days per year.
Determine the minutes available for machine type 1:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 1 is 120,000 minutes per year.
Determine the processing requirement of product 001 using machine type 1:
It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 1. Hence, the processing requirements of product 001 using machine type 1 is 48,000 minutes.
Determine the processing requirement of product 002 using machine type 1:
It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 1. Hence, the processing requirements of product 002 using machine type 1 is 90,000 minutes.
Determine the processing requirement of product 003 using machine type 1:
It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 1. Hence, the processing requirements of product 003 using machine type 1 is 90,000 minutes.
Determine the total processing requirement using machine type 1:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.
Determine the needed number of machine type 1:
It is calculated by dividing the total processing requirement and available minutes for machine type 1. Hence, the needed number of machine type 1is 2 machines.
Determine the capacity of the machines:
It is calculated by multiplying the number of machine type 1 needed and the available minutes for machine type 1. Hence, the capacity of the machine is 240,000 minutes.
Determine the capacity cushion:
It is calculated by subtracting total processing requirement from capacity of machines.
Determine the minutes available for machine type 2:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 2 is 120,000 minutes per year.
Determine the processing requirement of product 001 using machine type 2:
It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 2. Hence, the processing requirements of product 001 using machine type 2 is 72,000 minutes.
Determine the processing requirement of product 002 using machine type 2:
It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 2. Hence, the processing requirements of product 002 using machine type 2 is 90,000 minutes.
Determine the processing requirement of product 003 using machine type 2:
It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 2. Hence, the processing requirements of product 003 using machine type 2 is 54,000 minutes.
Determine the total processing requirement using machine type 2:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.
Determine the needed number of machine type 2:
It is calculated by dividing the total processing requirement and available minutes for machine type 2. Hence, the needed number of machine type 2 is 2 machines.
Determine the capacity of the machines:
It is calculated by multiplying the number of machine type 2 needed and the available minutes for machine type 2. Hence, the capacity of the machine is 240,000 minutes.
Determine the capacity cushion:
It is calculated by subtracting total processing requirement from capacity of machines.
b)
To determine: The machine type that can be chosen for the high and low certainty of demand.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Determine the machine type that can be chosen for the high and low certainty of demand:
The machine with the high capacity cushion should be selected, if the firm faced high certainty of annual demand. hence, machine type 2 should be selected.
The machine with the low capacity cushion should be selected, if the firm faced low certainty of annual demand. hence, machine type 1 should be selected.
c)
To determine: The machine type that would minimize the total cost, if purchasing and operating costs are considered.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Operating cost is given as $6 per hour for type 1 and $5 per hour for type 2.
Determine the purchase cost for machine type 1:
It is calculated by multiplying the number of machines and cost of type 1 machine. Hence, the purchase cost for machine type 1 is $20,000.
Determine the total operating time for machine type 1:
Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.
Determine the total operating cost:
Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $22,800.
Determine the total cost:
It is calculated by adding the purchasing cost of machine type 1 and total operating cost. Hence, the total cost is $42,800.
Determine the purchase cost for machine type 2:
It is calculated by multiplying the number of machines and cost of type 2 machine. Hence, the purchase cost for machine type 2 is $28,000.
Determine the total processing requirement using machine type 2:
Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.
Determine the total operating cost:
Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $18,000.
Determine the total cost:
It is calculated by adding the purchasing cost of machine type 2 and total operating cost. Hence, the total cost is $46,000.
Hence, Machine type 1 would minimize the total cost.
Want to see more full solutions like this?
Chapter 5 Solutions
OPERATIONS MANAGEMENT (LL+CONNECT)
- A manufacturer of ballet shoes has determined that its production facility has a design capacity of 300 shoes per week. Theeffective capacity, however, is 230 shoes per week. What is themanufacturer’s capacity utilization relative to both design andeffective capacity if output is 200 shoes per week?arrow_forwardAn airline company must plan its fleet capacity and its long-term schedule of aircraft usage. For one flight segment, theaverage number of customers per day is 70, which represents a 65 percent utilization rate of the equipment assigned to theflight segment. If demand is expected to increase to 84 cus-tomers for this flight segment in three years, what capacityrequirement should be planned? Assume that managementdeems that a capacity cushion of 25 percent is appropriatearrow_forwardIf a plant has an effective capacity of 6,500 andan efficiency of 88%, what is the actual (planned) output?arrow_forward
- A manager must decide which type of machine to buy, A, B, or C. Machines costs are as follows: Machine Cost A $40,000 B $30,000 C $80,000 Product forecast, processing times on the machines, and setup times are as follows: Processing Time Per Unit (minutes) Product Annual Demand A B C Setup Times (minutes) Production Lots (units) 1 16,000 3 4 2 20 200 2 12,000 4 5 3 35 100 3 6,000 5 6 3 60 50 4 30,000 2 4 1 15 500 Machines operate 10 hours a day, 250 days a year. The manager wants to have a capacity cushion of 10%. a. Assume that only purchasing costs are being considered. Which machines would have the lowest total cost, and how many of that machines would be needed? b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $11 each, B machines have an hourly operating cost of $10 each, and C machines have an hourly operating cost of $12 each. Which alternative would…arrow_forwardAvis Company is a car rental company that is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 2 minutes. The average traveling time (round-trip) is 20 minutes.a. How many Avis buses are traveling to and from the airport?b. The branch manager wants to improve the service and suggests dispatching buses every 0.5 minutes. She argues that this will reduce the average traveling time from the airport to the Avis offices to 2.5 minutes. Is she correct? If your answer is negative, what will the average traveling time be?arrow_forwardStapleton Manufacturing intends to increase capacity through the addition of new equipment. Two vendors have presented proposals. The fixed cost for proposal A is $65,000, and for proposal B, $34,000. The variable cost for A is $10, and for B, $14. The revenue generated by each unit is $18.a) What is the crossover point in units for the two o ptions?b) At an expected volume of8,300 units, which alternative shouldbe chosen?arrow_forward
- EMV APPLIED TO CAPACITY DECISION Southern Hospital Supplies, a company that makes hospital gowns, is considering capacity expansion.APPROACH: c Southern’s major alternatives are to do nothing, build a small plant, build a medium plant, or build a large plant. The new facility would produce a new type of gown, and currently the po-tential or marketability for this product is unknown. If a large plant is built and a favorable market ex-ists, a profit of $100,000 could be realized. An unfavorable market would yield a $90,000 loss. However, a medium plant would earn a $60,000 profit with a favorable market. A $10,000 loss would result froman unfavorable market. A small plant, on the other hand, would return $40,000 with favorable marketconditions and lose only $5,000 in an unfavorable market. Of course, there is always the option of doingnothing.Recent market research indicates that there is a .4 probability of a favorable market, which meansthat there is also a .6 probability of an…arrow_forwardAn executive conference center has the physical ability to handle 1,100 participants. However, conference management personnel believe that only 1,000 participants can be handled effectively for most events. The last event, although forecasted to have 1,000 participants, resulted in the attendance of only 950 participants. What are the utilization and efficiency of the conference facility?arrow_forwardA small firm intends to increase the capacity of a bottleneck operation by adding a new machine.Two alternatives, A and B, have been identified, and the associated costs and revenues have beenestimated. Annual fixed costs would be $40,000 for A and $30,000 for B; variable costs per unitwould be $10 for A and $11 for B; and revenue per unit would be $15.b. At what volume of output would the two alternatives yield the same profit?arrow_forward
- In a job shop, effective capacity is only 43 percent of design capacity, and actual output is 71 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?a. The Design Capacity needed to achieve the required actual job outputs = (round to whole number)b. The Effective Capacity needed to achieve the required actual job outputs = (round to whole number)arrow_forwardA manager must decide which type of machine to buy, A, B, or C. Machine costs are as follows: Machine CostA $40,000B $30,000C $80,000Product forecasts and processing times on the machines are as follows: Processing Time per Unit (minutes) Product Annual Demand A B C 1 16000 3 4 2 2 12000 4 4 3 3 6000 5 6 4 4 30000 2 2 1 a.) Assume that machines operate 10 hours a day, 250 days a year. If we only consider purchasing costs, which machine would have the lowest total cost? b.) Assume machines operate 10 hours a day, 250 days a year. If we select machine A, how many machine A do we need? (Use common sense to decide the answer.)arrow_forwardAn airline company must plan its fleet capacity and long-term schedule of aircraft usage. For oneflight segment, the average number of customers per day is 70, which represents a 65 percentageutilization rate of the equipment assigned to the flight segment. If demand is expected toincrease to 84 customers for this flight segment in three years, and management requires acapacity cushion of 25 percent, calculate the following: i. the planned capacity requirement. ii. the maximum number of customers the flight segment can accommodate.iii. the efficiency rate of the flight segment assuming that the current effective capacity of theflight segment is 93 customers.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,